Aakash Golden Jubilee

by Aakash Ashish Realtors Limited · Oshiwara, Jogeshwari West, Mumbai 400102Also near Jogeshwari East, Goregaon EastRegistered on MahaRERA as “Golden Jubilee”

What’s in the report? →

Possession date of Aakash Golden Jubilee (MahaRERA P51800048287): 31 December 2026, moved from 31 December 2025 (12 months later). It has 50 homes (1 Room Kitchen, 2 BHK and 3 BHK, 302–1774 sq ft carpet), 31% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800048287, and currently active.

Source: MahaRERA website — records for P51800048287, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Aakash Golden Jubilee?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Aakash Golden Jubilee has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA04022619715)

    Reason the builder gave MahaRERA:
    “I, Mr. Aakash R. Jajodia, Authorized Representative of Aakash Ashish Realtors Limited, carrying on project bearing MahaRERA Registration No. P51800048287, submit that there has been a delay in completion of the project due to pending intern…” Read the full reason“I, Mr. Aakash R. Jajodia, Authorized Representative of Aakash Ashish Realtors Limited, carrying on project bearing MahaRERA Registration No. P51800048287, submit that there has been a delay in completion of the project due to pending internal and final finishing works.The delay is unintentional, and we are making sincere efforts to complete the remaining work and obtain the Occupation Certificate at the earliest.”

Source: Aakash Golden Jubilee’s extension records on MahaRERA (P51800048287), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Aakash Golden Jubilee

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800048287
Status
Registered and active
Builder
Aakash Ashish Realtors Limited
Location
Oshiwara, Jogeshwari West, Mumbai · 400102
Project type
Others
Registered on
22 Dec 2022
Completion date at registration
December 2025
Latest completion date
December 2026
Delay so far
12 months
Homes
50
Sold or booked
31%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Aakash Golden Jubilee, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Golden Jubilee100%100%100%70%

Commencement certificate (CC), as filed on MahaRERA

  • Golden Jubilee: covers Re-endorsement of C.C. up to 15th part floor and Further C.C. up to top of 17th (part) upper floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aakash Golden Jubilee every 1–2 months.

Aakash Golden Jubilee: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK946 – 1,11822
2 BHK623 – 63420
Office Space228 – 2,05711
1 Room Kitchen302 – 3966
6 BHK1,7742
  • Buildings: Golden Jubilee (21 floors, 61 units)
  • Land: 1,730 sq m (about 0.4 acres) · sanctioned built-up 5,329 sq m · recreational space 268 sq m
  • Land, as filed: 433 & 534 & NEW CTS NO. 433A & 433B
  • Map: Get directions

The builder’s record and reviews

Aakash Ashish Realtors (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA.

Read Google reviews of Aakash Golden Jubilee →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aakash Golden Jubilee: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aakash Golden Jubilee

What is the possession date of Aakash Golden Jubilee?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aakash Golden Jubilee in Oshiwara, Jogeshwari West, Mumbai is 31 December 2026 — 12 months later than 31 December 2025, the date given at registration.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Aakash Golden Jubilee?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aakash Golden Jubilee's builder has filed on MahaRERA, the official one, is 31 December 2026, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Aakash Golden Jubilee extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Golden Jubilee's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "I, Mr. Aakash R. Jajodia, Authorized Representative of Aakash Ashish Realtors Limited, carrying on project bearing MahaRERA Registration No. P51800048287, submit that there has been a delay in completion of the project due to pending internal and final finishing works.The delay is unintentional, and we are making sincere efforts to complete the remaining work and obtain the Occupation Certificate at the earliest.".

What is the RERA number of Aakash Golden Jubilee?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aakash Golden Jubilee in Oshiwara, Jogeshwari West, Mumbai is P51800048287.

Is Aakash Golden Jubilee registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Golden Jubilee is registered as P51800048287 and its status is "Registered and active".

What is the current construction status of Aakash Golden Jubilee? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Golden Jubilee's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Golden Jubilee is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Aakash Golden Jubilee have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Aakash Golden Jubilee safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Golden Jubilee is registered on MahaRERA as P51800048287, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aakash Golden Jubilee?

Aakash Golden Jubilee is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Aakash Golden Jubilee are 302 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Aakash Golden Jubilee?

For a flat in Aakash Golden Jubilee (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Aakash Golden Jubilee received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Golden Jubilee is still under construction, with 31 December 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Aakash Golden Jubilee a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Golden Jubilee's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.

Has Aakash Golden Jubilee uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Aakash Golden Jubilee was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Aakash Golden Jubilee's possession date changes?

The latest dates are on Aakash Golden Jubilee's MahaRERA page (P51800048287). GharKundli's Kundli Watch sends a free WhatsApp update on Aakash Golden Jubilee every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aakash Golden Jubilee have?

According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Golden Jubilee has one building filed: Golden Jubilee with 21 floors and 61 units.

What are the flat sizes (carpet area) in Aakash Golden Jubilee?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Aakash Golden Jubilee: 3 BHK: 946 to 1118 sq ft carpet (22 homes); 2 BHK: 623 to 634 sq ft carpet (20 homes); 1 Room Kitchen: 302 to 396 sq ft carpet (6 homes); 6 BHK: 1774 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Aakash Golden Jubilee?

According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Golden Jubilee stands on 1,730 sq m of land (about 0.4 acres), with 5,329 sq m of sanctioned built-up area and 268 sq m of recreational open space.

What is the track record of Aakash Golden Jubilee's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Ashish Realtors (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Aakash Golden Jubilee?

Google Maps has reviews of Aakash Golden Jubilee written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aakash Golden Jubilee?

Aakash Golden Jubilee by Aakash Ashish Realtors Limited is in Oshiwara, Jogeshwari West, Mumbai, pincode 400102 (near Jogeshwari East, Goregaon East), Maharashtra, and is registered on MahaRERA as P51800048287, per GharKundli's check of MahaRERA records. Its land is filed as 433 & 534 & NEW CTS NO. 433A & 433B. GharKundli lists all 117 MahaRERA projects in Jogeshwari West (400102).

How many flats are in Aakash Golden Jubilee, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Golden Jubilee has 50 homes in 1 tower registered on MahaRERA, and 31% of them are sold or booked.

When was Aakash Golden Jubilee registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aakash Golden Jubilee was registered on MahaRERA on 22 December 2022. GharKundli did not find a title report on the land on file there.

Does Aakash Golden Jubilee have any legal issues or court cases?

No court cases are listed for Aakash Golden Jubilee on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Aakash Golden Jubilee?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aakash Ashish Realtors Limited.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Jogeshwari West (400102)

All 117 projects in Jogeshwari West (400102) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.