Kush Emerald
by Kush Housing LLP · Opp. Mandapeshwar Post Office, MumbaiAlso near Dahisar, Borivali West, Borivali East
Possession date of Kush Emerald: 31 March 2027, moved from 31 December 2025 (15 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800048045, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Kush Emerald?
How the possession date of Kush Emerald has moved
31 December 2025
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA03092502501)
Reason the builder gave MahaRERA:
“However due to RTI COMPLAINT by one of the dissenting society member, we have received First Stop Notice from Archaeological Survey of India (ASI), Sion Fort, Sion East, Mumbai dated 17.10.2023. Accordingly, we had applied to the ASI depart…” Read the full reason
“However due to RTI COMPLAINT by one of the dissenting society member, we have received First Stop Notice from Archaeological Survey of India (ASI), Sion Fort, Sion East, Mumbai dated 17.10.2023. Accordingly, we had applied to the ASI department for issuing NOC for carrying out further construction work. Due to some technical reasons, NOC from ASI was not available. So we had to apply to central government department i.e. National Monuments Authority (NMA) for obtaining NOC wherein application for the same was made dated 04.11.2023. Accordingly, we received NOC from NMA dated 17.05.2024. Aft…”
Source: Kush Emerald’s extension records on MahaRERA (P51800048045), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Kush Emerald
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800048045
- Status
- Registered and active
- Builder
- Kush Housing LLP
- Location
- Opp. Mandapeshwar Post Office, Mumbai · 400103
- Project type
- Residential / Group Housing
- Registered on
- 8 Dec 2022
- Completion date at registration
- December 2025
- Latest completion date
- March 2027
- Delay so far
- 15 months
- Homes
- 88
- Sold or booked
- 21%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Kush Emerald, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Kush Emerald | 100% | 100% | 50% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Kush Emerald: covers STILT SLAB LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kush Emerald every month.
Kush Emerald: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 610 – 689 | 58 |
| 1 BHK | 365 – 428 | 30 |
- Buildings: Kush Emerald (11 floors, 88 units)
- Car parking: 62 covered
- Land: 2,128 sq m (about 0.5 acres) · sanctioned built-up 3,975 sq m · recreational space 321 sq m
The builder’s record and reviews
Kush Buildcon (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 8 months); 3 still being built, 2 past the promised date (typically 10 months late). 2 complaints on MahaRERA across 2 projects.
Read Google reviews of Kush Emerald →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kush Emerald: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Kush Emerald
What is the possession date of Kush Emerald?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kush Emerald in Opp. Mandapeshwar Post Office, Mumbai is 31 March 2027 — 15 months later than 31 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Kush Emerald?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kush Emerald's builder has filed on MahaRERA, the official one, is 31 March 2027, already 15 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Kush Emerald extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Kush Emerald's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "However due to RTI COMPLAINT by one of the dissenting society member, we have received First Stop Notice from Archaeological Survey of India (ASI), Sion Fort, Sion East, Mumbai dated 17.10.2023. Accordingly, we had applied to the ASI department for issuing NOC for carrying out further construction work. Due to some technical reasons, NOC from ASI was not available. So we had to apply to central government department i.e. National Monuments Authority (NMA) for obtaining NOC wherein application for the same was made dated 04.11.2023. Accordingly, we received NOC from NMA dated 17.05.2024. Aft…".
What is the RERA number of Kush Emerald?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kush Emerald in Opp. Mandapeshwar Post Office, Mumbai is P51800048045.
Is Kush Emerald registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kush Emerald is registered as P51800048045 and its status is "Registered and active".
What is the construction status of Kush Emerald?
According to GharKundli's check of MahaRERA records (updated October 2026), Kush Emerald's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Kush Emerald is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does Kush Emerald have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Kush Emerald safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kush Emerald is registered on MahaRERA as P51800048045, its completion date has moved 15 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Kush Emerald's possession date changes?
The latest dates are on Kush Emerald's MahaRERA page (P51800048045). GharKundli's Kundli Watch sends a free WhatsApp update on Kush Emerald every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kush Emerald have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kush Emerald has one building filed: Kush Emerald with 11 floors and 88 units.
What are the flat sizes (carpet area) in Kush Emerald?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Kush Emerald: 2 BHK: 610 to 689 sq ft carpet (58 homes); 1 BHK: 365 to 428 sq ft carpet (30 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Kush Emerald have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 62 covered car parking spaces for Kush Emerald.
How big is the land of Kush Emerald?
According to GharKundli's check of MahaRERA records (updated October 2026), Kush Emerald stands on 2,128 sq m of land (about 0.5 acres), with 3,975 sq m of sanctioned built-up area and 321 sq m of recreational open space.
What is the track record of Kush Emerald's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Kush Buildcon (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 5 finished, 2 within the promised date and 3 needed more time (typically 8 months); 3 still being built, 2 past the promised date (typically 10 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Kush Emerald?
Google Maps has reviews of Kush Emerald written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Kush Emerald?
Kush Emerald by Kush Housing LLP is in Opp. Mandapeshwar Post Office, Mumbai (pincode 400103), near Dahisar, Borivali West, Borivali East, Maharashtra, and is registered on MahaRERA as P51800048045, per GharKundli's check of MahaRERA records.
How many homes are in Kush Emerald?
According to GharKundli's check of MahaRERA records (updated October 2026), Kush Emerald has 88 homes in 1 tower registered on MahaRERA, and 21% of them are sold or booked.
When was Kush Emerald registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kush Emerald was registered on MahaRERA on 8 December 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Kush Emerald?
No court cases are listed for Kush Emerald on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Kush Emerald?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kush Housing LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Kush Emerald
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400103
- Crescent Heights
- SEA ROCK CHS LTD
- SIANNA HEIGHTS
- THE ERICA
- BORIVALI MADHUMAS CHSL
- DYNAMIX 36
- GREEN ACRES
- MAYFAIR AANGAN
Other projects by Kush Housing LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.