Rajlaxmi Heights CHSL
by RAJMUDRA CONSTRUCTIONS PRIVATE LIMITED · Borivali East, Mumbai 400066Also near Borivali West, Mandapeshwar, Dahisar
What’s in the report? →Possession date of Rajlaxmi Heights CHSL (MahaRERA P51800047301): 30 September 2027, moved from 30 May 2025 (24 months later). It has 48 homes (1 BHK, 1 Room Kitchen and 2 BHK, 229–520 sq ft carpet), 48% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800047301, and currently active. Its completion date has moved from May 2025 to September 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800047301, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Rajlaxmi Heights CHSL?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Rajlaxmi Heights CHSL has moved
30 May 2025
Completion date given when the project was registered
31 May 2026
Extended at the builder's request (MahaRERA application EXT51800027762)
Reason the builder gave MahaRERA:
“This is to inform you that our project name RAJLAXMI HEIGHTS CHSL located at Borivali East Bearing Rera No P51800047301 We would like to clarify that due to unforeseen circumstances, we are unable to meet the necessary time period of the co…” Read the full reason
“This is to inform you that our project name RAJLAXMI HEIGHTS CHSL located at Borivali East Bearing Rera No P51800047301 We would like to clarify that due to unforeseen circumstances, we are unable to meet the necessary time period of the completion of the project which is 30 May 2025. Whereas the work that was delayed was due to widening of Road permissions upto 9 meters from concerned authorities and BMC R/C Ward. We. Rajmudra Constructions Private Limited hereby state that the necessary procedures have been completed and the final road widening permission upto 9 meters has been successful…”31 May 2027
Extended at the builder's request (MahaRERA application EA16062621394)
Reason the builder gave MahaRERA:
“Subject: Submission of Technical Reasons for Delay in Completion of the Project - RAJLAXMI HEIGHTS CHSL, Maha RERA Reg. No. P51800047301 Respected Sir, We, RAJMUDRA CONSTRUCTIONS PVT. LTD. are the promoters of the real estate project known…” Read the full reason
“Subject: Submission of Technical Reasons for Delay in Completion of the Project - RAJLAXMI HEIGHTS CHSL, Maha RERA Reg. No. P51800047301 Respected Sir, We, RAJMUDRA CONSTRUCTIONS PVT. LTD. are the promoters of the real estate project known as "RAJLAXMI HEIGHTS CHSL" bearing Maha RERA Registration No. P51800047301. Technical Reasons for Delay in Completion of the project is as under: al Labor Shortage b) Escalation in cost due to stop work for 9 meter road permission in 2024 c) Cost Escalation in Building material d) Low Sale Impact. Thanking you. Yours sincerely,”30 September 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Rajlaxmi Heights CHSL’s extension records on MahaRERA (P51800047301), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Rajlaxmi Heights CHSL
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the September 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800047301
- Status
- Registered and active
- Builder
- RAJMUDRA CONSTRUCTIONS PRIVATE LIMITED
- Location
- Borivali East, Mumbai · 400066
- Project type
- Residential / Group Housing
- Registered on
- 17 Oct 2022
- Completion date at registration
- May 2025
- Latest completion date
- September 2027
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 48
- Sold or booked
- 48%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Rajlaxmi Heights CHSL, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RAJLAXMI HEIGHTS CHSL | 100% | 91% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- RAJLAXMI HEIGHTS CHSL: covers proposed building comprising of stilt + 1st to 9th floor as per approved amended plans dtd. 06.03.2025.
Latest CC order on MahaRERA: dated 01/04/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rajlaxmi Heights CHSL every 1–2 months.
Rajlaxmi Heights CHSL: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 370 | 20 |
| 2 BHK | 466 – 520 | 18 |
| 1 Room Kitchen | 229 – 252 | 10 |
- Buildings: RAJLAXMI HEIGHTS CHSL (11 floors, 48 units)
- Land: 730 sq m (about 0.2 acres) · sanctioned built-up 1,959 sq m
- Land, as filed: 2160/1
- Map: Get directions
The builder’s record and reviews
Rajmudra Constructions has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 13 months late). No complaints on MahaRERA.
Read Google reviews of Rajlaxmi Heights CHSL →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Rajlaxmi Heights CHSL: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Rajlaxmi Heights CHSL
What is the possession date of Rajlaxmi Heights CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Rajlaxmi Heights CHSL in Borivali East, Mumbai is 30 September 2027 — 24 months later than 30 May 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Rajlaxmi Heights CHSL?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Rajlaxmi Heights CHSL's builder has filed on MahaRERA, the official one, is 30 September 2027, already 24 months later than the 30 May 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Rajlaxmi Heights CHSL extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajlaxmi Heights CHSL's builder applied to MahaRERA to extend the completion date 2 times: to 31 May 2026, giving the reason "This is to inform you that our project name RAJLAXMI HEIGHTS CHSL located at Borivali East Bearing Rera No P51800047301 We would like to clarify that due to unforeseen circumstances, we are unable to meet the necessary time period of the completion of the project which is 30 May 2025. Whereas the work that was delayed was due to widening of Road permissions upto 9 meters from concerned authorities and BMC R/C Ward. We. Rajmudra Constructions Private Limited hereby state that the necessary procedures have been completed and the final road widening permission upto 9 meters has been successful…"; to 31 May 2027, giving the reason "Subject: Submission of Technical Reasons for Delay in Completion of the Project - RAJLAXMI HEIGHTS CHSL, Maha RERA Reg. No. P51800047301 Respected Sir, We, RAJMUDRA CONSTRUCTIONS PVT. LTD. are the promoters of the real estate project known as "RAJLAXMI HEIGHTS CHSL" bearing Maha RERA Registration No. P51800047301. Technical Reasons for Delay in Completion of the project is as under: al Labor Shortage b) Escalation in cost due to stop work for 9 meter road permission in 2024 c) Cost Escalation in Building material d) Low Sale Impact. Thanking you. Yours sincerely,". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Rajlaxmi Heights CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Rajlaxmi Heights CHSL in Borivali East, Mumbai is P51800047301.
Is Rajlaxmi Heights CHSL registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajlaxmi Heights CHSL is registered as P51800047301 and its status is "Registered and active".
What is the current construction status of Rajlaxmi Heights CHSL? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajlaxmi Heights CHSL's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RAJLAXMI HEIGHTS CHSL is 91% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Rajlaxmi Heights CHSL have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Rajlaxmi Heights CHSL safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajlaxmi Heights CHSL is registered on MahaRERA as P51800047301, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Rajlaxmi Heights CHSL?
Rajlaxmi Heights CHSL is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Rajlaxmi Heights CHSL are 229 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Rajlaxmi Heights CHSL?
For a flat in Rajlaxmi Heights CHSL (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Rajlaxmi Heights CHSL received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Rajlaxmi Heights CHSL is still under construction, with 30 September 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Rajlaxmi Heights CHSL a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajlaxmi Heights CHSL is a redevelopment: 17 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Rajlaxmi Heights CHSL uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Rajlaxmi Heights CHSL was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Rajlaxmi Heights CHSL's possession date changes?
The latest dates are on Rajlaxmi Heights CHSL's MahaRERA page (P51800047301). GharKundli's Kundli Watch sends a free WhatsApp update on Rajlaxmi Heights CHSL every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Rajlaxmi Heights CHSL have?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajlaxmi Heights CHSL has one building filed: RAJLAXMI HEIGHTS CHSL with 11 floors and 48 units.
What are the flat sizes (carpet area) in Rajlaxmi Heights CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Rajlaxmi Heights CHSL: 1 BHK: 370 sq ft carpet (20 homes); 2 BHK: 466 to 520 sq ft carpet (18 homes); 1 Room Kitchen: 229 to 252 sq ft carpet (10 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Rajlaxmi Heights CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajlaxmi Heights CHSL stands on 730 sq m of land (about 0.2 acres), with 1,959 sq m of sanctioned built-up area.
What is the track record of Rajlaxmi Heights CHSL's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajmudra Constructions has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 13 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Rajlaxmi Heights CHSL?
Google Maps has reviews of Rajlaxmi Heights CHSL written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Rajlaxmi Heights CHSL?
Rajlaxmi Heights CHSL by RAJMUDRA CONSTRUCTIONS PRIVATE LIMITED is in Borivali East, Mumbai, pincode 400066 (near Borivali West, Mandapeshwar, Dahisar), Maharashtra, and is registered on MahaRERA as P51800047301, per GharKundli's check of MahaRERA records. Its land is filed as 2160/1. GharKundli lists all 228 MahaRERA projects in Borivali East (400066).
How many flats are in Rajlaxmi Heights CHSL, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajlaxmi Heights CHSL has 48 homes in 1 tower registered on MahaRERA, and 48% of them are sold or booked.
When was Rajlaxmi Heights CHSL registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Rajlaxmi Heights CHSL was registered on MahaRERA on 17 October 2022. GharKundli did not find a title report on the land on file there.
Does Rajlaxmi Heights CHSL have any legal issues or court cases?
No court cases are listed for Rajlaxmi Heights CHSL on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Rajlaxmi Heights CHSL?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAJMUDRA CONSTRUCTIONS PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of Rajlaxmi Heights CHSL
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Borivali East (400066)
- Rajendra Nagar Swagat CHSL
- Rajendra Nagar Omsai Co-operative Housing Society Limited
- Paras Darshan
- Rustomjee Summit
- DTG Ashford
- H. Rishabraj AER
- Megh Mahal CHSL
- Parshuram Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.