Possession date of Relliance Lashkaria Solitaire (MahaRERA P51800048357): 31 October 2027, moved from 31 October 2026 (12 months later). It has 55 homes (1 BHK, 2 BHK and 3 BHK, 630–905 sq ft carpet), 29% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800048357, and currently active.

Source: MahaRERA website — records for P51800048357, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Relliance Lashkaria Solitaire?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Relliance Lashkaria Solitaire has moved

  1. 31 October 2026

    Completion date given when the project was registered

  2. 31 October 2027

    Extended at the builder's request (MahaRERA application EA08062621274)

    Reason the builder gave MahaRERA:
    “Subject: Intimation of Delay and Request for Extension of Project Completion Date for "Lashkaria Solitaire" (RERA Registration No. P51800048357) Respected sir/Madam This letter is to formally inform Maharashtra Real Estate Regulatory Author…” Read the full reason“Subject: Intimation of Delay and Request for Extension of Project Completion Date for "Lashkaria Solitaire" (RERA Registration No. P51800048357) Respected sir/Madam This letter is to formally inform Maharashtra Real Estate Regulatory Authority about the delay in the completion of our registered project, "Lashkaria Solitaire" located in Adarsh nagar near lotus petrol pump, Link road, Andheri west, Mumbai 400102. The project, with RERA Registration No. P51800048357, had an original completion date of 31 october 2026. We request an extension until 31 October 2027. Despite our best efforts to m…”

Source: Relliance Lashkaria Solitaire’s extension records on MahaRERA (P51800048357), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Relliance Lashkaria Solitaire

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800048357
Status
Registered and active
Builder
RELLIANCE REALTY
Location
Andheri West, Mumbai · 400102
Project type
Others
Registered on
27 Dec 2022
Completion date at registration
October 2026
Latest completion date
October 2027
Delay so far
12 months
Homes
55
Sold or booked
29%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Relliance Lashkaria Solitaire, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Lashkaria Solitaire100%40%20%0%

Commencement certificate (CC), as filed on MahaRERA

  • Lashkaria Solitaire: covers TOP OF STILT OUT OF APPROVED GROUND FLOOR + 19th FLOOR HABITABLE FLOORS.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Relliance Lashkaria Solitaire every 1–2 months.

Relliance Lashkaria Solitaire: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK630 – 63540
3 BHK90514
1 BHK6301
  • Buildings: Lashkaria Solitaire (20 floors, 55 units)
  • Car parking: 56 covered
  • Land: 1,393 sq m (about 0.3 acres) · sanctioned built-up 5,392 sq m
  • Boundaries filed include: ORIENTAL COLLEGE, ADARSH NAGAR
  • Land, as filed: CTS NO 1-A(pt), 34(pt), 39(pt), 40(pt), 41(pt)
  • Map: Get directions

The builder’s record and reviews

MS Relliance Construction (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 3 still being built, 2 past the promised date (typically 37 months late). 7 complaints on MahaRERA across 3 projects.

Read Google reviews of Relliance Lashkaria Solitaire →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Relliance Lashkaria Solitaire: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Relliance Lashkaria Solitaire

What is the possession date of Relliance Lashkaria Solitaire?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Relliance Lashkaria Solitaire in Andheri West, Mumbai is 31 October 2027 — 12 months later than 31 October 2026, the date given at registration.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Relliance Lashkaria Solitaire?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Relliance Lashkaria Solitaire's builder has filed on MahaRERA, the official one, is 31 October 2027, already 12 months later than the 31 October 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Relliance Lashkaria Solitaire extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Relliance Lashkaria Solitaire's builder applied to MahaRERA to extend the completion date once: to 31 October 2027, giving the reason "Subject: Intimation of Delay and Request for Extension of Project Completion Date for "Lashkaria Solitaire" (RERA Registration No. P51800048357) Respected sir/Madam This letter is to formally inform Maharashtra Real Estate Regulatory Authority about the delay in the completion of our registered project, "Lashkaria Solitaire" located in Adarsh nagar near lotus petrol pump, Link road, Andheri west, Mumbai 400102. The project, with RERA Registration No. P51800048357, had an original completion date of 31 october 2026. We request an extension until 31 October 2027. Despite our best efforts to m…".

What is the RERA number of Relliance Lashkaria Solitaire?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Relliance Lashkaria Solitaire in Andheri West, Mumbai is P51800048357.

Is Relliance Lashkaria Solitaire registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Relliance Lashkaria Solitaire is registered as P51800048357 and its status is "Registered and active".

What is the current construction status of Relliance Lashkaria Solitaire? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Relliance Lashkaria Solitaire's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Lashkaria Solitaire is 40% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.

Does Relliance Lashkaria Solitaire have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Relliance Lashkaria Solitaire safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Relliance Lashkaria Solitaire is registered on MahaRERA as P51800048357, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Relliance Lashkaria Solitaire?

Relliance Lashkaria Solitaire is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Relliance Lashkaria Solitaire are 630 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Relliance Lashkaria Solitaire?

For a flat in Relliance Lashkaria Solitaire (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Relliance Lashkaria Solitaire received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Relliance Lashkaria Solitaire is still under construction, with 31 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Relliance Lashkaria Solitaire uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Relliance Lashkaria Solitaire was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Relliance Lashkaria Solitaire's possession date changes?

The latest dates are on Relliance Lashkaria Solitaire's MahaRERA page (P51800048357). GharKundli's Kundli Watch sends a free WhatsApp update on Relliance Lashkaria Solitaire every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Relliance Lashkaria Solitaire have?

According to GharKundli's check of MahaRERA records (updated October 2026), Relliance Lashkaria Solitaire has one building filed: Lashkaria Solitaire with 20 floors and 55 units.

What are the flat sizes (carpet area) in Relliance Lashkaria Solitaire?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Relliance Lashkaria Solitaire: 2 BHK: 630 to 635 sq ft carpet (40 homes); 3 BHK: 905 sq ft carpet (14 homes); 1 BHK: 630 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Relliance Lashkaria Solitaire have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 56 covered car parking spaces for Relliance Lashkaria Solitaire.

How big is the land of Relliance Lashkaria Solitaire?

According to GharKundli's check of MahaRERA records (updated October 2026), Relliance Lashkaria Solitaire stands on 1,393 sq m of land (about 0.3 acres), with 5,392 sq m of sanctioned built-up area.

What is the track record of Relliance Lashkaria Solitaire's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), MS Relliance Construction (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 3 still being built, 2 past the promised date (typically 37 months late). 7 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Relliance Lashkaria Solitaire?

Google Maps has reviews of Relliance Lashkaria Solitaire written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Relliance Lashkaria Solitaire?

Relliance Lashkaria Solitaire by RELLIANCE REALTY is in Andheri West, Mumbai, pincode 400102, Maharashtra, and is registered on MahaRERA as P51800048357, per GharKundli's check of MahaRERA records. Its boundaries filed there include ORIENTAL COLLEGE, ADARSH NAGAR. Its land is filed as CTS NO 1-A(pt), 34(pt), 39(pt), 40(pt), 41(pt). GharKundli lists all 117 MahaRERA projects in Jogeshwari West (400102).

How many flats are in Relliance Lashkaria Solitaire, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Relliance Lashkaria Solitaire has 55 homes in 1 tower registered on MahaRERA, and 29% of them are sold or booked.

When was Relliance Lashkaria Solitaire registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Relliance Lashkaria Solitaire was registered on MahaRERA on 27 December 2022. GharKundli did not find a title report on the land on file there.

Does Relliance Lashkaria Solitaire have any legal issues or court cases?

No court cases are listed for Relliance Lashkaria Solitaire on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Relliance Lashkaria Solitaire?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RELLIANCE REALTY.

All projects with possession due in 2027 in Mumbai Suburban →