by MS AMANN RAJ HOUSING AND DEVELOPMENT CORPORATION (Relliance) · Andheri West, MumbaiAlso near Borivali West, Vile Parle East, Kandivali

Possession date of THE ZONE: 30 December 2026, moved from 31 January 2021 (71 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800006553, and currently active. 5 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about THE ZONE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of THE ZONE has moved

  1. 31 January 2021

    Completion date given when the project was registered

  2. 31 January 2022

    Extended at the builder's request (MahaRERA application EXT51800008759)

    Reason the builder gave MahaRERA: “DUE TO NON AVAILABILITY OF FURTHER CC AND COVID-19 PANDEMIC THE PROJECT WAS NOT ABLE TO BE COMPLETED ON ABOVE MENTIONED DATE.”
  3. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800011587)

    Reason the builder gave MahaRERA: “DUE TO NON AVAILABILITY OF FURTHER CC AND COVID-19 PANDEMIC THE PROJECT WAS NOT ABLE TO BE COMPLETED PLEASE GRANT FURTHER EXTENSION TILL 30/06/2025”
  4. 30 June 2026

    Extended at the builder's request (MahaRERA application EA14082502376)

    Reason the builder gave MahaRERA:
    “This letter is to formally inform Maharashtra Real Estate Regulatory Authority about the delay in the completion of our registered project, "The Zone." located in Chanadavarker road Borivali West, Mumbai 400092 The project with RERA Registr…” Read the full reason“This letter is to formally inform Maharashtra Real Estate Regulatory Authority about the delay in the completion of our registered project, "The Zone." located in Chanadavarker road Borivali West, Mumbai 400092 The project with RERA Registration No. PS1800006553, had an original completion date of June 2025. The COVID-19 pandemic led to significant disruptions in the supply chain, severe labor shortages due to lockdowns, and a complete halt in construction activities for an extended period. These events were entirely beyond our control and created a domino effect of delays Furthermore, the…”
  5. 30 December 2026

    Extended at the builder's request (MahaRERA application EA25052621088)

    Reason the builder gave MahaRERA:
    “This letter is to formally inform Maharashtra Real Estate Regulatory Authority about the delay in the completion of our registered project, "The Zone," located in Chanadavarker road, Borivali West, Mumbai 400092. The project, with RERA Regi…” Read the full reason“This letter is to formally inform Maharashtra Real Estate Regulatory Authority about the delay in the completion of our registered project, "The Zone," located in Chanadavarker road, Borivali West, Mumbai 400092. The project, with RERA Registration No. P51800006553, had an original completion date of 30 June 2026, The COVID-19 pandemic led to significant disruptions in the supply chain, severe labor shortages due to lockdowns, and a complete halt in construction activities for an extended period. These events were entirely beyond our control and created a domino effect of delays. Furthermor…”

Source: THE ZONE’s extension records on MahaRERA (P51800006553), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on THE ZONE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 complaints, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800006553
Status
Registered and active
Builder
MS AMANN RAJ HOUSING AND DEVELOPMENT CORPORATION
Location
Andheri West, Mumbai · 400092
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
January 2021
Latest completion date
December 2026
Delay so far
71 months
Homes
0
Sold or booked
100%
Towers
1
Complaints on MahaRERA
5
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of THE ZONE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AMANN SOLITAIRE B WING100%100%100%40%

Commencement certificate (CC), as filed on MahaRERA

  • AMANN SOLITAIRE B WING: covers PLINTH LEVEL

Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE ZONE every month.

THE ZONE: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space403 – 5,73954
  • Buildings: AMANN SOLITAIRE B WING (11 floors, 54 units)
  • Car parking: 79 covered
  • Land: 1,248 sq m (about 0.3 acres) · sanctioned built-up 520 sq m · recreational space 678 sq m
  • Boundaries filed include: CHANDAVARKAR ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

MS Relliance Construction (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 3 still being built, 2 past the promised date (typically 37 months late). 7 complaints on MahaRERA across 3 projects.

Read Google reviews of THE ZONE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

THE ZONE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about THE ZONE

What is the possession date of THE ZONE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE ZONE in Andheri West, Mumbai is 30 December 2026 — 71 months later than 31 January 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for THE ZONE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date THE ZONE's builder has filed on MahaRERA, the official one, is 30 December 2026, already 71 months later than the 31 January 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of THE ZONE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), THE ZONE's builder applied to MahaRERA to extend the completion date 4 times: to 31 January 2022, giving the reason "DUE TO NON AVAILABILITY OF FURTHER CC AND COVID-19 PANDEMIC THE PROJECT WAS NOT ABLE TO BE COMPLETED ON ABOVE MENTIONED DATE."; to 30 June 2025, giving the reason "DUE TO NON AVAILABILITY OF FURTHER CC AND COVID-19 PANDEMIC THE PROJECT WAS NOT ABLE TO BE COMPLETED PLEASE GRANT FURTHER EXTENSION TILL 30/06/2025"; to 30 June 2026, giving the reason "This letter is to formally inform Maharashtra Real Estate Regulatory Authority about the delay in the completion of our registered project, "The Zone." located in Chanadavarker road Borivali West, Mumbai 400092 The project with RERA Registration No. PS1800006553, had an original completion date of June 2025. The COVID-19 pandemic led to significant disruptions in the supply chain, severe labor shortages due to lockdowns, and a complete halt in construction activities for an extended period. These events were entirely beyond our control and created a domino effect of delays Furthermore, the…"; to 30 December 2026, giving the reason "This letter is to formally inform Maharashtra Real Estate Regulatory Authority about the delay in the completion of our registered project, "The Zone," located in Chanadavarker road, Borivali West, Mumbai 400092. The project, with RERA Registration No. P51800006553, had an original completion date of 30 June 2026, The COVID-19 pandemic led to significant disruptions in the supply chain, severe labor shortages due to lockdowns, and a complete halt in construction activities for an extended period. These events were entirely beyond our control and created a domino effect of delays. Furthermor…".

What is the RERA number of THE ZONE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of THE ZONE in Andheri West, Mumbai is P51800006553.

Is THE ZONE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), THE ZONE is registered as P51800006553 and its status is "Registered and active".

What is the construction status of THE ZONE?

According to GharKundli's check of MahaRERA records (updated October 2026), THE ZONE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AMANN SOLITAIRE B WING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does THE ZONE have complaints on MahaRERA?

5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is THE ZONE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), THE ZONE is registered on MahaRERA as P51800006553, its completion date has moved 71 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if THE ZONE's possession date changes?

The latest dates are on THE ZONE's MahaRERA page (P51800006553). GharKundli's Kundli Watch sends a free WhatsApp update on THE ZONE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does THE ZONE have?

According to GharKundli's check of MahaRERA records (updated October 2026), THE ZONE has one building filed: AMANN SOLITAIRE B WING with 11 floors and 54 units.

How much parking does THE ZONE have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 79 covered car parking spaces for THE ZONE.

How big is the land of THE ZONE?

According to GharKundli's check of MahaRERA records (updated October 2026), THE ZONE stands on 1,248 sq m of land (about 0.3 acres), with 520 sq m of sanctioned built-up area and 678 sq m of recreational open space.

What is the track record of THE ZONE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), MS Relliance Construction (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 3 still being built, 2 past the promised date (typically 37 months late). 7 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of THE ZONE?

Google Maps has reviews of THE ZONE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is THE ZONE?

THE ZONE by MS AMANN RAJ HOUSING AND DEVELOPMENT CORPORATION (Relliance) is in Andheri West, Mumbai (pincode 400092), near Borivali West, Vile Parle East, Kandivali, Maharashtra, and is registered on MahaRERA as P51800006553, per GharKundli's check of MahaRERA records. Its boundaries filed there include CHANDAVARKAR ROAD.

How many homes are in THE ZONE?

According to GharKundli's check of MahaRERA records (updated October 2026), THE ZONE has 0 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was THE ZONE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), THE ZONE was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on THE ZONE?

No court cases are listed for THE ZONE on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of THE ZONE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MS AMANN RAJ HOUSING AND DEVELOPMENT CORPORATION, the company Relliance files this project under.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Andheri West

All 362 projects in Borivali West (400092) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.