by Right Channel Buildcon LLP · Malad East, Mumbai 400097Also near Malad West Dely, Motilal NagarRegistered on MahaRERA as “Hill Star”

What’s in the report? →

Possession date of Right Hill Star (MahaRERA P51800048810): 30 June 2027, moved from 31 December 2024 (30 months later). It has 20 homes (1 BHK, 1 Room Kitchen and 2 BHK, 265–531 sq ft carpet), 90% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800048810, and currently active.

Source: MahaRERA website — records for P51800048810, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Right Hill Star?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Right Hill Star has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800025774)

    Reason the builder gave MahaRERA: “Due to shortage of construction material specially RMC and Steel construction activity is running beyond scheduled time So; to complete the building we may take another 9-12 months’ time period”
  3. 30 June 2027

    Extended at the builder's request (MahaRERA application EA23022619963)

    Reason the builder gave MahaRERA:
    “We have already completed entire RCC structure, Internal & External Plaster, Floorings within flats, Doors & Windows, Sanitary & Electrical Fittings, Staircases, Lifts Wells and Lobbies, Overhead and Underground Water tank, External plumbin…” Read the full reason“We have already completed entire RCC structure, Internal & External Plaster, Floorings within flats, Doors & Windows, Sanitary & Electrical Fittings, Staircases, Lifts Wells and Lobbies, Overhead and Underground Water tank, External plumbing i.e. most of the finishing work of the building has been completed but due to road construction work undergoing nearby, the site was affected for 3 to 4 months due to which, the work could not got completed as per timelines. Though Installations of lifts, firefighting equipment’s work are completed to about 95%. So, to complete the remaining work of bui…”

Source: Right Hill Star’s extension records on MahaRERA (P51800048810), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Right Hill Star

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800048810
Status
Registered and active
Builder
Right Channel Buildcon LLP
Location
Malad East, Mumbai · 400097
Project type
Others
Registered on
19 Jan 2023
Completion date at registration
December 2024
Latest completion date
June 2027
Delay so far
30 months
Homes
20
Sold or booked
90%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Right Hill Star, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Hill Star100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Hill Star: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Right Hill Star every 1–2 months.

Right Hill Star: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK351 – 37912
2 BHK506 – 5317
1 Room Kitchen2651
  • Buildings: Hill Star (16 floors, 20 units)
  • Car parking: 18 covered
  • Land: 493 sq m (about 0.1 acres) · sanctioned built-up 1,494 sq m
  • Boundaries filed include: Scheme Road
  • Land, as filed: 446
  • Map: Get directions

The builder’s record and reviews

Right Channel Construction (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 26 months); 4 still being built, 4 past the promised date (typically 91 months late); 2 lapsed. 27 complaints on MahaRERA across 4 projects.

Read Google reviews of Right Hill Star →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Right Hill Star: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Right Hill Star

What is the possession date of Right Hill Star?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Right Hill Star in Malad East, Mumbai is 30 June 2027 — 30 months later than 31 December 2024, the date given at registration.

The date has already moved 30 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Right Hill Star?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Right Hill Star's builder has filed on MahaRERA, the official one, is 30 June 2027, already 30 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Right Hill Star extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Right Hill Star's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "Due to shortage of construction material specially RMC and Steel construction activity is running beyond scheduled time So; to complete the building we may take another 9-12 months’ time period"; to 30 June 2027, giving the reason "We have already completed entire RCC structure, Internal & External Plaster, Floorings within flats, Doors & Windows, Sanitary & Electrical Fittings, Staircases, Lifts Wells and Lobbies, Overhead and Underground Water tank, External plumbing i.e. most of the finishing work of the building has been completed but due to road construction work undergoing nearby, the site was affected for 3 to 4 months due to which, the work could not got completed as per timelines. Though Installations of lifts, firefighting equipment’s work are completed to about 95%. So, to complete the remaining work of bui…".

What is the RERA number of Right Hill Star?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Right Hill Star in Malad East, Mumbai is P51800048810.

Is Right Hill Star registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Right Hill Star is registered as P51800048810 and its status is "Registered and active".

What is the current construction status of Right Hill Star? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Right Hill Star's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Hill Star is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Right Hill Star have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Right Hill Star safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Right Hill Star is registered on MahaRERA as P51800048810, its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Right Hill Star?

Right Hill Star is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Right Hill Star are 265 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Right Hill Star?

For a flat in Right Hill Star (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Right Hill Star received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Right Hill Star is still under construction, with 30 June 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Right Hill Star a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Right Hill Star's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.

Has Right Hill Star uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Right Hill Star was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Right Hill Star's possession date changes?

The latest dates are on Right Hill Star's MahaRERA page (P51800048810). GharKundli's Kundli Watch sends a free WhatsApp update on Right Hill Star every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Right Hill Star have?

According to GharKundli's check of MahaRERA records (updated October 2026), Right Hill Star has one building filed: Hill Star with 16 floors and 20 units.

What are the flat sizes (carpet area) in Right Hill Star?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Right Hill Star: 1 BHK: 351 to 379 sq ft carpet (12 homes); 2 BHK: 506 to 531 sq ft carpet (7 homes); 1 Room Kitchen: 265 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Right Hill Star have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 18 covered car parking spaces for Right Hill Star.

How big is the land of Right Hill Star?

According to GharKundli's check of MahaRERA records (updated October 2026), Right Hill Star stands on 493 sq m of land (about 0.1 acres), with 1,494 sq m of sanctioned built-up area.

What is the track record of Right Hill Star's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Right Channel Construction (a group of 3 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 26 months); 4 still being built, 4 past the promised date (typically 91 months late); 2 lapsed. 27 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Right Hill Star?

Google Maps has reviews of Right Hill Star written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Right Hill Star?

Right Hill Star by Right Channel Buildcon LLP is in Malad East, Mumbai, pincode 400097 (near Malad West Dely, Motilal Nagar), Maharashtra, and is registered on MahaRERA as P51800048810, per GharKundli's check of MahaRERA records. Its boundaries filed there include Scheme Road. Its land is filed as 446. GharKundli lists all 195 MahaRERA projects in Malad East (400097).

How many flats are in Right Hill Star, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Right Hill Star has 20 homes in 1 tower registered on MahaRERA, and 90% of them are sold or booked.

When was Right Hill Star registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Right Hill Star was registered on MahaRERA on 19 January 2023. GharKundli did not find a title report on the land on file there.

Does Right Hill Star have any legal issues or court cases?

No court cases are listed for Right Hill Star on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Right Hill Star?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Right Channel Buildcon LLP.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Malad East (400097)

All 195 projects in Malad East (400097) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.