HORIZON TOWER

by HORIZON REALTY · Dadar West, MumbaiAlso near Chembur, Kurla East, Sion Chunabhatti

Possession: HORIZON TOWER is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900009490. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about HORIZON TOWER?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of HORIZON TOWER has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51900001250)

    Reason the builder gave MahaRERA:
    “The Project has been delayed due to Force Majure and conditions laid down by MCGM from time to time which were bad in Law and due to the mistakes and inordinate delay in granting permissions. The MCGM sanctioned the Applicants proposal in 2…” Read the full reason“The Project has been delayed due to Force Majure and conditions laid down by MCGM from time to time which were bad in Law and due to the mistakes and inordinate delay in granting permissions. The MCGM sanctioned the Applicants proposal in 2007 and also made the Applicant pay a a premium for deficiency in the width of the access road. The Applicant was in turn informed by the MCGM that the occupation certificate will be granted only on removal of the encroachment on the abutting DP road. The MCGM also restricted utilization of part FSI. The Applicant inspite of completing the building were u…”
  3. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51900005219)

    Reason the builder gave MahaRERA:
    “The Applicants obtained fresh online D.P. Remarks on 19th December 2018 for CTS No 125/4 & CTS No 1850. To the utter dismay of the Applicants the MCGM inspite of the Applicants making a representation on 6th June 2016 did not call them for…” Read the full reason“The Applicants obtained fresh online D.P. Remarks on 19th December 2018 for CTS No 125/4 & CTS No 1850. To the utter dismay of the Applicants the MCGM inspite of the Applicants making a representation on 6th June 2016 did not call them for a hearing and has in turn shown that the CTS No 125/4 which had a sanctioned building with a part occupation upto 4th floor on a plot area of 1229.40 sq. mtrs as 734.47 sq. mtrs and the remaining part of the plot i.e. 494.93 sq. mtrs has now been marked as C.T.S. No 1850 and shown as R.G. The Applicant have with immediate effect addressed a letter of obje…”
  4. 30 October 2020

    Revised completion date on MahaRERA

Source: HORIZON TOWER’s extension records on MahaRERA (P51900009490), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on HORIZON TOWER

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900009490
Status
Completed
Builder
HORIZON REALTY
Location
Dadar West, Mumbai · 400022
Project type
Residential / Group Housing
Registered on
22 Aug 2017
Completion date at registration
December 2018
Latest completion date
October 2020
Delay so far
22 months
Homes
59
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of HORIZON TOWER, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
HORIZON TOWER100%100%70%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on HORIZON TOWER every month.

HORIZON TOWER: buildings, flats and land, as filed on MahaRERA

  • Buildings: HORIZON TOWER (21 floors)
  • Land: 1,594 sq m (about 0.4 acres) · sanctioned built-up 2,129 sq m · recreational space 1,594 sq m
  • Boundaries filed include: South Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of HORIZON TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

HORIZON TOWER: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HORIZON TOWER

What is the possession date of HORIZON TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for HORIZON TOWER in Dadar West, Mumbai is 30 October 2020 — 22 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for HORIZON TOWER?

Builders and listing sites often quote an earlier "target" date for handover. The completion date HORIZON TOWER's builder has filed on MahaRERA, the official one, is 30 October 2020, already 22 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of HORIZON TOWER extended?

According to GharKundli's check of MahaRERA records (updated November 2026), HORIZON TOWER's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2020, giving the reason "The Project has been delayed due to Force Majure and conditions laid down by MCGM from time to time which were bad in Law and due to the mistakes and inordinate delay in granting permissions. The MCGM sanctioned the Applicants proposal in 2007 and also made the Applicant pay a a premium for deficiency in the width of the access road. The Applicant was in turn informed by the MCGM that the occupation certificate will be granted only on removal of the encroachment on the abutting DP road. The MCGM also restricted utilization of part FSI. The Applicant inspite of completing the building were u…"; to 30 April 2020, giving the reason "The Applicants obtained fresh online D.P. Remarks on 19th December 2018 for CTS No 125/4 & CTS No 1850. To the utter dismay of the Applicants the MCGM inspite of the Applicants making a representation on 6th June 2016 did not call them for a hearing and has in turn shown that the CTS No 125/4 which had a sanctioned building with a part occupation upto 4th floor on a plot area of 1229.40 sq. mtrs as 734.47 sq. mtrs and the remaining part of the plot i.e. 494.93 sq. mtrs has now been marked as C.T.S. No 1850 and shown as R.G. The Applicant have with immediate effect addressed a letter of obje…".

What is the RERA number of HORIZON TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of HORIZON TOWER in Dadar West, Mumbai is P51900009490.

Is HORIZON TOWER registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), HORIZON TOWER is registered as P51900009490 and its status is "Completed".

What is the construction status of HORIZON TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), HORIZON TOWER's status on MahaRERA is "Completed". As filed by the builder, slab work on HORIZON TOWER is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does HORIZON TOWER have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is HORIZON TOWER safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), HORIZON TOWER is registered on MahaRERA as P51900009490, its MahaRERA status is "Completed", its completion date has moved 22 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if HORIZON TOWER's possession date changes?

The latest dates are on HORIZON TOWER's MahaRERA page (P51900009490). GharKundli's Kundli Watch sends a free WhatsApp update on HORIZON TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does HORIZON TOWER have?

According to GharKundli's check of MahaRERA records (updated November 2026), HORIZON TOWER has one building filed: HORIZON TOWER with 21 floors.

How big is the land of HORIZON TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), HORIZON TOWER stands on 1,594 sq m of land (about 0.4 acres), with 2,129 sq m of sanctioned built-up area and 1,594 sq m of recreational open space.

Where can I read reviews of HORIZON TOWER?

Google Maps has reviews of HORIZON TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is HORIZON TOWER?

HORIZON TOWER by HORIZON REALTY is in Dadar West, Mumbai (pincode 400022), near Chembur, Kurla East, Sion Chunabhatti, Maharashtra, and is registered on MahaRERA as P51900009490, per GharKundli's check of MahaRERA records. Its boundaries filed there include South Road.

How many homes are in HORIZON TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), HORIZON TOWER has 59 homes in 1 tower registered on MahaRERA.

When was HORIZON TOWER registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), HORIZON TOWER was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on HORIZON TOWER?

No court cases are listed for HORIZON TOWER on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of HORIZON TOWER?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is HORIZON REALTY, which has 1 other project registered on MahaRERA.