Skip to content
GharKundli

Khandwani Mehrabad

by KHANDWANI EXPORT PVT LTD · Mahim, Mumbai 400016Also near Dharavi, Matunga, Bhawani ShankarRegistered on MahaRERA as “MEHRABAD”

What’s in the report? →

Possession date of Khandwani Mehrabad (MahaRERA P51900008625): 31 December 2025, moved from 30 December 2022 (36 months later), and it has already passed. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900008625. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51900008625, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about Khandwani Mehrabad?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Khandwani Mehrabad has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 September 2024

    Extended at the builder's request (MahaRERA application EXT51900017897)

    Reason the builder gave MahaRERA: “We have currently completed the RCC work and will be applying for the occupancy certificate. We shall expect the Occupancy certificate before 30.09.2024”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51900027570)

    Reason the builder gave MahaRERA: “DUE TO TRENCHING PERMISSION NOC DELAYED FOR PERMANENT WATER CONNECTION AND BEST ELECTRIC CONNECTION THE PROJECT WAS NOT ABLE TO GET COMPLETED IN TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENTION FOR 31-12-2025”

Source: Khandwani Mehrabad’s extension records on MahaRERA (P51900008625), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Khandwani Mehrabad

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900008625
Status
Lapsed (registration period ended)
Builder
KHANDWANI EXPORT PVT LTD
Location
Mahim, Mumbai · 400016
Project type
Residential / Group Housing
Registered on
19 Aug 2017
Completion date at registration
December 2022
Latest completion date
December 2025
Delay so far
36 months
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Khandwani Mehrabad, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MEHRABAD100%100%90%92%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Khandwani Mehrabad every 1–2 months.

Khandwani Mehrabad: buildings, flats and land, as filed on MahaRERA

  • Buildings: MEHRABAD (24 floors)
  • Land: 615 sq m (about 0.2 acres) · sanctioned built-up 2,492 sq m
  • Land, as filed: 936
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Khandwani Mehrabad →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Khandwani Mehrabad: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Khandwani Mehrabad

What is the possession date of Khandwani Mehrabad?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Khandwani Mehrabad in Mahim, Mumbai is 31 December 2025 — 36 months later than 30 December 2022, the date given at registration. That date has already passed.

The date has already moved 36 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Khandwani Mehrabad?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Khandwani Mehrabad's builder has filed on MahaRERA, the official one, is 31 December 2025, already 36 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Khandwani Mehrabad extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Khandwani Mehrabad's builder applied to MahaRERA to extend the completion date 2 times: to 30 September 2024, giving the reason "We have currently completed the RCC work and will be applying for the occupancy certificate. We shall expect the Occupancy certificate before 30.09.2024"; to 31 December 2025, giving the reason "DUE TO TRENCHING PERMISSION NOC DELAYED FOR PERMANENT WATER CONNECTION AND BEST ELECTRIC CONNECTION THE PROJECT WAS NOT ABLE TO GET COMPLETED IN TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENTION FOR 31-12-2025".

What is the RERA number of Khandwani Mehrabad?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Khandwani Mehrabad in Mahim, Mumbai is P51900008625.

Is Khandwani Mehrabad registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Khandwani Mehrabad is registered as P51900008625 and its status is "Lapsed (registration period ended)".

What is the current construction status of Khandwani Mehrabad? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Khandwani Mehrabad's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MEHRABAD is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does Khandwani Mehrabad have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Khandwani Mehrabad safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Khandwani Mehrabad is registered on MahaRERA as P51900008625, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Khandwani Mehrabad?

Khandwani Mehrabad isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Khandwani Mehrabad?

For a flat in Khandwani Mehrabad (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Khandwani Mehrabad received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Khandwani Mehrabad isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Khandwani Mehrabad?

According to GharKundli's check of MahaRERA records (updated October 2026), Khandwani Mehrabad's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Khandwani Mehrabad uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Khandwani Mehrabad was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Khandwani Mehrabad's possession date changes?

The latest dates are on Khandwani Mehrabad's MahaRERA page (P51900008625). GharKundli's Kundli Watch sends a free WhatsApp update on Khandwani Mehrabad every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Khandwani Mehrabad have?

According to GharKundli's check of MahaRERA records (updated October 2026), Khandwani Mehrabad has one building filed: MEHRABAD with 24 floors.

How big is the land of Khandwani Mehrabad?

According to GharKundli's check of MahaRERA records (updated October 2026), Khandwani Mehrabad stands on 615 sq m of land (about 0.2 acres), with 2,492 sq m of sanctioned built-up area.

What are the reviews of Khandwani Mehrabad?

Google Maps has reviews of Khandwani Mehrabad written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Khandwani Mehrabad?

Khandwani Mehrabad by KHANDWANI EXPORT PVT LTD is in Mahim, Mumbai, pincode 400016 (near Dharavi, Matunga, Bhawani Shankar), Maharashtra, and is registered on MahaRERA as P51900008625, per GharKundli's check of MahaRERA records. Its land is filed as 936. GharKundli lists all 84 MahaRERA projects in Mahim (400016).

When was Khandwani Mehrabad registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Khandwani Mehrabad was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.

Does Khandwani Mehrabad have any legal issues or court cases?

No court cases are listed for Khandwani Mehrabad on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Khandwani Mehrabad?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KHANDWANI EXPORT PVT LTD.

Other projects in Mahim (400016)

All 84 projects in Mahim (400016) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.