Registered on MahaRERA under P51800048947. Status: Completed. Its completion date has moved from December 2024 to June 2026, 18 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
- MahaRERA registration
- P51800048947
- Status
- Completed
- Builder
- ASTRUM REALITY PRIVATE LIMITED
- Location
- Borivali East, Mumbai · 400066
- Project type
- Residential / Group Housing
- Registered on
- 24 Jan 2023
- Completion date at registration
- December 2024
- Latest completion date
- June 2026
- Delay so far
- 18 months
- Homes
- 60
- Sold or booked
- 68%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
GharKundli’s full report on ASTRUM ANNEX
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Kundli Watch
ASTRUM ANNEX: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about ASTRUM ANNEX
Is ASTRUM ANNEX registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ASTRUM ANNEX is registered as P51800048947 and its status is "Completed".
Where is ASTRUM ANNEX?
ASTRUM ANNEX by ASTRUM REALITY PRIVATE LIMITED is in Borivali East, Mumbai (pincode 400066), Maharashtra, and is registered on MahaRERA as P51800048947, per GharKundli's check of MahaRERA records.
When is possession of ASTRUM ANNEX due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ASTRUM ANNEX in Borivali East, Mumbai is 30 June 2026 — 18 months later than 31 December 2024, the date given at registration.
Does ASTRUM ANNEX have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of ASTRUM ANNEX?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ASTRUM REALITY PRIVATE LIMITED.
Other projects in pincode 400066
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.