by Pinal Realty LLP · Mulund West, Mumbai 400080Also near Mulund East, Bhandup West, Off DmartRegistered on MahaRERA as “Pramukh Krupa Phase One”
What’s in the report? →Possession date of Pinal Pramukh Krupa Phase One (MahaRERA P51800051702): 31 March 2026, moved from 31 March 2025 (12 months later), and it has already passed. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800051702. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800051702, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (March 2026) has passed.
What do you want to know about Pinal Pramukh Krupa Phase One?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Pinal Pramukh Krupa Phase One has moved
31 March 2025
Completion date given when the project was registered
31 March 2026
Extended at the builder's request (MahaRERA application EXT51800027967)
Reason the builder gave MahaRERA:
“We, Pinal Realty LLP, the promoter of the project Pramukh Krupa Phase One (Registration No. P51800051702) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the delay in th…” Read the full reason
“We, Pinal Realty LLP, the promoter of the project Pramukh Krupa Phase One (Registration No. P51800051702) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension…”
Source: Pinal Pramukh Krupa Phase One’s extension records on MahaRERA (P51800051702), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Pinal Pramukh Krupa Phase One
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800051702
- Status
- Lapsed (registration period ended)
- Builder
- Pinal Realty LLP
- Location
- Mulund West, Mumbai · 400080
- Project type
- Commercial
- Registered on
- 27 Jun 2023
- Completion date at registration
- March 2025
- Latest completion date
- March 2026
- Delay so far
- 12 months
- Homes
- 0
- Sold or booked
- 71%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Pinal Pramukh Krupa Phase One, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| C Wing | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- C Wing: covers 8(Lower Basement +Upper Basement +Ground +5 Upper Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pinal Pramukh Krupa Phase One every 1–2 months.
Pinal Pramukh Krupa Phase One: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Shops | 180 – 1,287 | 15 |
| Office Space | 475 – 1,583 | 7 |
| Other | 6,129 | 1 |
- Buildings: C Wing (10 floors, 23 units)
- Land: 1,666 sq m (about 0.4 acres) · sanctioned built-up 6,209 sq m
- Boundaries filed include: Ganesh Gawade Road
- Land, as filed: C.T.S. No. 1138, 1138/1 to 22
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Pinal Realty (a group of 2 linked companies) has 7 projects on MahaRERA since 2019, this one included. Of the 7 GharKundli has checked: 5 still being built, 1 past the promised date (typically 20 months late); 2 lapsed. 5 complaints on MahaRERA across 2 projects.
Read Google reviews of Pinal Pramukh Krupa Phase One →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Pinal Pramukh Krupa Phase One: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Pinal Pramukh Krupa Phase One
What is the possession date of Pinal Pramukh Krupa Phase One?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Pinal Pramukh Krupa Phase One in Mulund West, Mumbai is 31 March 2026 — 12 months later than 31 March 2025, the date given at registration. That date has already passed.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Pinal Pramukh Krupa Phase One?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Pinal Pramukh Krupa Phase One's builder has filed on MahaRERA, the official one, is 31 March 2026, already 12 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Pinal Pramukh Krupa Phase One extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Pramukh Krupa Phase One's builder applied to MahaRERA to extend the completion date once: to 31 March 2026, giving the reason "We, Pinal Realty LLP, the promoter of the project Pramukh Krupa Phase One (Registration No. P51800051702) under MahaRERA, hereby submit our request for an extension of time for the completion of the project. We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension…".
What is the RERA number of Pinal Pramukh Krupa Phase One?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Pinal Pramukh Krupa Phase One in Mulund West, Mumbai is P51800051702.
Is Pinal Pramukh Krupa Phase One registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Pramukh Krupa Phase One is registered as P51800051702 and its status is "Lapsed (registration period ended)".
What is the current construction status of Pinal Pramukh Krupa Phase One? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Pramukh Krupa Phase One's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on C Wing is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Pinal Pramukh Krupa Phase One have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Pinal Pramukh Krupa Phase One safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Pramukh Krupa Phase One is registered on MahaRERA as P51800051702, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Pinal Pramukh Krupa Phase One?
Pinal Pramukh Krupa Phase One isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Pinal Pramukh Krupa Phase One?
For a flat in Pinal Pramukh Krupa Phase One (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Pinal Pramukh Krupa Phase One received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Pramukh Krupa Phase One isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 March 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Pinal Pramukh Krupa Phase One?
According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Pramukh Krupa Phase One's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 March 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Is Pinal Pramukh Krupa Phase One a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Pramukh Krupa Phase One is a redevelopment: 16 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Pinal Pramukh Krupa Phase One uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Pinal Pramukh Krupa Phase One was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Pinal Pramukh Krupa Phase One's possession date changes?
The latest dates are on Pinal Pramukh Krupa Phase One's MahaRERA page (P51800051702). GharKundli's Kundli Watch sends a free WhatsApp update on Pinal Pramukh Krupa Phase One every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Pinal Pramukh Krupa Phase One have?
According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Pramukh Krupa Phase One has one building filed: C Wing with 10 floors and 23 units.
How big is the land of Pinal Pramukh Krupa Phase One?
According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Pramukh Krupa Phase One stands on 1,666 sq m of land (about 0.4 acres), with 6,209 sq m of sanctioned built-up area.
What is the track record of Pinal Pramukh Krupa Phase One's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Realty (a group of 2 linked companies) has 7 projects on MahaRERA since 2019, this one included. Of the 7 GharKundli has checked: 5 still being built, 1 past the promised date (typically 20 months late); 2 lapsed. 5 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Pinal Pramukh Krupa Phase One?
Google Maps has reviews of Pinal Pramukh Krupa Phase One written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Pinal Pramukh Krupa Phase One?
Pinal Pramukh Krupa Phase One by Pinal Realty LLP is in Mulund West, Mumbai, pincode 400080 (near Mulund East, Bhandup West, Off Dmart), Maharashtra, and is registered on MahaRERA as P51800051702, per GharKundli's check of MahaRERA records. Its boundaries filed there include Ganesh Gawade Road. Its land is filed as C.T.S. No. 1138, 1138/1 to 22. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).
How many flats are in Pinal Pramukh Krupa Phase One, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Pramukh Krupa Phase One has 0 homes in 1 tower registered on MahaRERA, and 71% of them are sold or booked.
When was Pinal Pramukh Krupa Phase One registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pinal Pramukh Krupa Phase One was registered on MahaRERA on 27 June 2023. GharKundli did not find a title report on the land on file there.
Does Pinal Pramukh Krupa Phase One have any legal issues or court cases?
No court cases are listed for Pinal Pramukh Krupa Phase One on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Pinal Pramukh Krupa Phase One?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pinal Realty LLP, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Pinal Pramukh Krupa Phase One
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Mulund West (400080)
- Malhar Guide
- Arihant Royale
- The Sanctuary - Tower 5
- Keshavpada
- Dhanraj Tower
- Mulund Mahavirdham Co. Op. Housing Soc. LTD.
- Madhuvan Nivanta
- Shraddha Paradise Enclave
Other projects by Pinal Realty LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.