ONE JOGESHWARI
by UNIQUE DEVELOPERS · Jogeshwari West, MumbaiAlso near Vesava
Possession date of ONE JOGESHWARI: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800051003, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about ONE JOGESHWARI?
How the possession date of ONE JOGESHWARI has moved
31 December 2026
Completion date given when the project was registered
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ONE JOGESHWARI’s extension records on MahaRERA (P51800051003), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ONE JOGESHWARI
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800051003
- Status
- Registered and active
- Builder
- UNIQUE DEVELOPERS
- Location
- Jogeshwari West, Mumbai · 400102
- Project type
- Residential / Group Housing
- Registered on
- 19 May 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 176
- Sold or booked
- 46%
- Towers
- 1
- Complaints on MahaRERA
- 5
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 8
Construction progress of ONE JOGESHWARI, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 2 | 100% | 100% | 95% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 2: covers plinth level
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ONE JOGESHWARI every month.
ONE JOGESHWARI: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING NO 2 (29 floors, 176 units)
- Car parking: 41 covered
- Land: 1,950 sq m (about 0.5 acres) · sanctioned built-up 5,254 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of ONE JOGESHWARI →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ONE JOGESHWARI: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ONE JOGESHWARI
What is the possession date of ONE JOGESHWARI?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ONE JOGESHWARI in Jogeshwari West, Mumbai is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ONE JOGESHWARI?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ONE JOGESHWARI's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of ONE JOGESHWARI?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ONE JOGESHWARI in Jogeshwari West, Mumbai is P51800051003.
Is ONE JOGESHWARI registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE JOGESHWARI is registered as P51800051003 and its status is "Registered and active".
What is the construction status of ONE JOGESHWARI?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE JOGESHWARI's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING NO 2 is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does ONE JOGESHWARI have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ONE JOGESHWARI safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE JOGESHWARI is registered on MahaRERA as P51800051003, its completion date has not been moved by the builder and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ONE JOGESHWARI's possession date changes?
The latest dates are on ONE JOGESHWARI's MahaRERA page (P51800051003). GharKundli's Kundli Watch sends a free WhatsApp update on ONE JOGESHWARI every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ONE JOGESHWARI have?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE JOGESHWARI has one building filed: BUILDING NO 2 with 29 floors and 176 units.
How much parking does ONE JOGESHWARI have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 41 covered car parking spaces for ONE JOGESHWARI.
How big is the land of ONE JOGESHWARI?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE JOGESHWARI stands on 1,950 sq m of land (about 0.5 acres), with 5,254 sq m of sanctioned built-up area.
Where can I read reviews of ONE JOGESHWARI?
Google Maps has reviews of ONE JOGESHWARI written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ONE JOGESHWARI?
ONE JOGESHWARI by UNIQUE DEVELOPERS is in Jogeshwari West, Mumbai (pincode 400102), near Vesava, Maharashtra, and is registered on MahaRERA as P51800051003, per GharKundli's check of MahaRERA records.
How many homes are in ONE JOGESHWARI?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE JOGESHWARI has 176 homes in 1 tower registered on MahaRERA, and 46% of them are sold or booked.
When was ONE JOGESHWARI registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), ONE JOGESHWARI was registered on MahaRERA on 19 May 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on ONE JOGESHWARI?
No court cases are listed for ONE JOGESHWARI on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of ONE JOGESHWARI?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is UNIQUE DEVELOPERS, which has 8 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ONE JOGESHWARI
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400102
- A. H. Heights
- Arkan
- 24 Karat
- ESQUINA PRIVATE RESIDENCE
- Live Well Chs Ltd
- Infra - Azura Height
- Gurukrupa Ekam
- Lotus Sky Plaza
Other projects by UNIQUE DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.