71P
by LIVING HABITATS PRIVATE LIMITED · Borivali East, MumbaiAlso near Borivali West
Possession date of 71P: 30 April 2027, moved from 30 September 2025 (15 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800051382, and currently active. Its completion date has moved from September 2025 to April 2027: 15 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about 71P?
How the possession date of 71P has moved
30 September 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA08082502342)
Reason the builder gave MahaRERA:
“We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the fol…” Read the full reason
“We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay: 1. Structural Redesign or Change in Planning Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safety and quality. 2. Delay in Statutory Clearances/Utility Approvals The redesigning and r…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: 71P’s extension records on MahaRERA (P51800051382), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on 71P
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 7 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800051382
- Status
- Registered and active
- Builder
- LIVING HABITATS PRIVATE LIMITED
- Location
- Borivali East, Mumbai · 400066
- Project type
- Others
- Registered on
- 8 Jun 2023
- Completion date at registration
- September 2025
- Latest completion date
- April 2027
- Delay so far
- 15 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 60
- Sold or booked
- 62%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 7
- Title report on file
- Not found
Construction progress of 71P, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 71P | 100% | 41% | 0% | 25% |
Commencement certificate (CC), as filed on MahaRERA
- 71P: covers plinth level
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 71P every month.
71P: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 535 – 8,430 | 41 |
| 3 BHK | 961 – 10,345 | 15 |
| Shops | 458 – 950 | 3 |
| 4 BHK | 1,510 | 1 |
- Buildings: 71P (12 floors, 60 units)
- Land: 1,505 sq m (about 0.4 acres) · sanctioned built-up 2,304 sq m
- Boundaries filed include: HARIBHAI PATEL ROAD 60FT
The builder’s record and reviews
Urna Evolved Living has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 9 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of 71P →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
71P: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about 71P
What is the possession date of 71P?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 71P in Borivali East, Mumbai is 30 April 2027 — 15 months later than 30 September 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for 71P?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 71P's builder has filed on MahaRERA, the official one, is 30 April 2027, already 15 months later than the 30 September 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of 71P extended?
According to GharKundli's check of MahaRERA records (updated October 2026), 71P's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay: 1. Structural Redesign or Change in Planning Based on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safety and quality. 2. Delay in Statutory Clearances/Utility Approvals The redesigning and r…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of 71P?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 71P in Borivali East, Mumbai is P51800051382.
Is 71P registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 71P is registered as P51800051382 and its status is "Registered and active".
What is the construction status of 71P?
According to GharKundli's check of MahaRERA records (updated October 2026), 71P's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 71P is 41% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does 71P have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is 71P safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), 71P is registered on MahaRERA as P51800051382, its completion date has moved 15 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if 71P's possession date changes?
The latest dates are on 71P's MahaRERA page (P51800051382). GharKundli's Kundli Watch sends a free WhatsApp update on 71P every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does 71P have?
According to GharKundli's check of MahaRERA records (updated October 2026), 71P has one building filed: 71P with 12 floors and 60 units.
What are the flat sizes (carpet area) in 71P?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for 71P: 2 BHK: 535 to 8430 sq ft carpet (41 homes); 3 BHK: 961 to 10345 sq ft carpet (15 homes); Shops: 458 to 950 sq ft carpet (3 homes); 4 BHK: 1510 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of 71P?
According to GharKundli's check of MahaRERA records (updated October 2026), 71P stands on 1,505 sq m of land (about 0.4 acres), with 2,304 sq m of sanctioned built-up area.
What is the track record of 71P's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Urna Evolved Living has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 9 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of 71P?
Google Maps has reviews of 71P written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is 71P?
71P by LIVING HABITATS PRIVATE LIMITED is in Borivali East, Mumbai (pincode 400066), near Borivali West, Maharashtra, and is registered on MahaRERA as P51800051382, per GharKundli's check of MahaRERA records. Its boundaries filed there include HARIBHAI PATEL ROAD 60FT.
How many homes are in 71P?
According to GharKundli's check of MahaRERA records (updated October 2026), 71P has 60 homes in 1 tower registered on MahaRERA, and 62% of them are sold or booked.
When was 71P registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 71P was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on 71P?
7 court cases are listed for 71P on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of 71P?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LIVING HABITATS PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of 71P
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400066
- Rustomjee Summit
- RAJENDRA NAGAR SWAGAT CHSL
- RAJENDRA NAGAR OMSAI CO-OPERATIVE HOUSING SOCIETY LIMITED
- MEGH MAHAL CHSL
- PARSHURAM HEIGHTS
- DTG ASHFORD
- H. Rishabraj AER
- Paras Darshan
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.