Gami and Jaydeep Ventura Commercial Hub
by M/S REAL INFRASTRUCTURE CO · Malad East, MumbaiAlso near Malad West Dely, Motilal Nagar
Possession date of Gami and Jaydeep Ventura Commercial Hub: 31 October 2026, moved from 31 December 2025 (10 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800052432, and currently active. 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (October 2026) has passed.
What do you want to know about Gami and Jaydeep Ventura Commercial Hub?
How the possession date of Gami and Jaydeep Ventura Commercial Hub has moved
31 December 2025
Completion date given when the project was registered
31 October 2026
Extended at the builder's request (MahaRERA application EA17022619888)
Reason the builder gave MahaRERA:
“We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the fol…” Read the full reason
“We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay:1. Structural Redesign or Change in PlanninBased on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safety and qualit2. Delay in Statutory Clearances/Utility ApprovalsALThe redesigning and revise…”
Source: Gami and Jaydeep Ventura Commercial Hub’s extension records on MahaRERA (P51800052432), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Gami and Jaydeep Ventura Commercial Hub
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints, and how it ended
- Construction pace against the October 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800052432
- Status
- Registered and active
- Builder
- M/S REAL INFRASTRUCTURE CO
- Location
- Malad East, Mumbai · 400097
- Project type
- Commercial
- Registered on
- 25 Aug 2023
- Completion date at registration
- December 2025
- Latest completion date
- October 2026
- Delay so far
- 10 months
- Homes
- 0
- Sold or booked
- 38%
- Towers
- 1
- Complaints on MahaRERA
- 5
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of Gami and Jaydeep Ventura Commercial Hub, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Gami and Jaydeep Ventura Commercial Hub | 100% | 100% | 97% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- Gami and Jaydeep Ventura Commercial Hub: covers C.C is further extended upto 4th floar for sale building No-3
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Gami and Jaydeep Ventura Commercial Hub every month.
Gami and Jaydeep Ventura Commercial Hub: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 115 – 2,196 | 283 |
| Shops | 185 – 745 | 22 |
- Buildings: Gami and Jaydeep Ventura Commercial Hub (16 floors, 305 units)
- Land: 2,613 sq m (about 0.6 acres) · sanctioned built-up 16,101 sq m
The builder’s record and reviews
Real Infrastructure has 5 projects on MahaRERA since 2022, this one included. Of the 5 GharKundli has checked: 4 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 6 complaints on MahaRERA across 2 projects.
Read Google reviews of Gami and Jaydeep Ventura Commercial Hub →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Gami and Jaydeep Ventura Commercial Hub: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Gami and Jaydeep Ventura Commercial Hub
What is the possession date of Gami and Jaydeep Ventura Commercial Hub?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Gami and Jaydeep Ventura Commercial Hub in Malad East, Mumbai is 31 October 2026 — 10 months later than 31 December 2025, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Gami and Jaydeep Ventura Commercial Hub?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Gami and Jaydeep Ventura Commercial Hub's builder has filed on MahaRERA, the official one, is 31 October 2026, already 10 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Gami and Jaydeep Ventura Commercial Hub extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami and Jaydeep Ventura Commercial Hub's builder applied to MahaRERA to extend the completion date once: to 31 October 2026, giving the reason "We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay:1. Structural Redesign or Change in PlanninBased on technical site evaluations and safety audits, certain aspects of the structural layout and MEP systems had to be redesigned to meet updated technical standards and ensure long-term safety and qualit2. Delay in Statutory Clearances/Utility ApprovalsALThe redesigning and revise…".
What is the RERA number of Gami and Jaydeep Ventura Commercial Hub?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Gami and Jaydeep Ventura Commercial Hub in Malad East, Mumbai is P51800052432.
Is Gami and Jaydeep Ventura Commercial Hub registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami and Jaydeep Ventura Commercial Hub is registered as P51800052432 and its status is "Registered and active".
What is the construction status of Gami and Jaydeep Ventura Commercial Hub?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami and Jaydeep Ventura Commercial Hub's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Gami and Jaydeep Ventura Commercial Hub is 100% done and internal work 97%. GharKundli's full report compares construction progress with the deadline.
Does Gami and Jaydeep Ventura Commercial Hub have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Gami and Jaydeep Ventura Commercial Hub safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami and Jaydeep Ventura Commercial Hub is registered on MahaRERA as P51800052432, its completion date has moved 10 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Gami and Jaydeep Ventura Commercial Hub's possession date changes?
The latest dates are on Gami and Jaydeep Ventura Commercial Hub's MahaRERA page (P51800052432). GharKundli's Kundli Watch sends a free WhatsApp update on Gami and Jaydeep Ventura Commercial Hub every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Gami and Jaydeep Ventura Commercial Hub have?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami and Jaydeep Ventura Commercial Hub has one building filed: Gami and Jaydeep Ventura Commercial Hub with 16 floors and 305 units.
How big is the land of Gami and Jaydeep Ventura Commercial Hub?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami and Jaydeep Ventura Commercial Hub stands on 2,613 sq m of land (about 0.6 acres), with 16,101 sq m of sanctioned built-up area.
What is the track record of Gami and Jaydeep Ventura Commercial Hub's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Real Infrastructure has 5 projects on MahaRERA since 2022, this one included. Of the 5 GharKundli has checked: 4 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Gami and Jaydeep Ventura Commercial Hub?
Google Maps has reviews of Gami and Jaydeep Ventura Commercial Hub written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Gami and Jaydeep Ventura Commercial Hub?
Gami and Jaydeep Ventura Commercial Hub by M/S REAL INFRASTRUCTURE CO is in Malad East, Mumbai (pincode 400097), near Malad West Dely, Motilal Nagar, Maharashtra, and is registered on MahaRERA as P51800052432, per GharKundli's check of MahaRERA records.
How many homes are in Gami and Jaydeep Ventura Commercial Hub?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami and Jaydeep Ventura Commercial Hub has 0 homes in 1 tower registered on MahaRERA, and 38% of them are sold or booked.
When was Gami and Jaydeep Ventura Commercial Hub registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Gami and Jaydeep Ventura Commercial Hub was registered on MahaRERA on 25 August 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Gami and Jaydeep Ventura Commercial Hub?
No court cases are listed for Gami and Jaydeep Ventura Commercial Hub on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Gami and Jaydeep Ventura Commercial Hub?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S REAL INFRASTRUCTURE CO, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Gami and Jaydeep Ventura Commercial Hub
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in pincode 400097
- Upper East 97
- Vardhan Royale
- Aarambh Phase III by group Satellite
- Nivetia Heights
- Pearl Solitaire
- L&T Realty Ahana Tower A
- L&T Realty Ahana Tower B
- NAMO WHISPERING BLISS
Other projects by M/S REAL INFRASTRUCTURE CO
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.