MINT
by TULSIANI SUMER ASSOCIATES · J.B. Nagar, MumbaiAlso near Andheri East, Andheri West, D.N.Nagar
Possession date of MINT: 25 November 2026, moved from 30 June 2026 (5 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800053816, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MINT?
How the possession date of MINT has moved
30 June 2026
Completion date given when the project was registered
25 November 2026
Extended at the builder's request (MahaRERA application EA25082622386)
Reason the builder gave MahaRERA: “OC Recived”
Source: MINT’s extension records on MahaRERA (P51800053816), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MINT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800053816
- Status
- Registered and active
- Builder
- TULSIANI SUMER ASSOCIATES
- Location
- J.B. Nagar, Mumbai · 400059
- Project type
- Commercial
- Registered on
- 1 Dec 2023
- Completion date at registration
- June 2026
- Latest completion date
- November 2026
- Delay so far
- 5 months
- Homes
- 0
- Sold or booked
- 18%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of MINT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING NO 3 WING A | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- BUILDING NO 3 WING A: covers upto top of 10th floor of Wing `A'
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MINT every month.
MINT: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 1,412 – 22,391 | 121 |
- Buildings: BUILDING NO 3 WING A (14 floors, 121 units)
- Land: 5,756 sq m (about 1.4 acres) · sanctioned built-up 23,711 sq m
- Boundaries filed include: ADANI ELECTRICITY RECEIVING STATION, MCGM GARDEN
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Sumer Corporation (a group of 4 linked companies) has 5 projects on MahaRERA since 2019, this one included. Of the 5 GharKundli has checked: 4 still being built, 4 past the promised date (typically 12 months late); 1 lapsed. 31 complaints on MahaRERA across 2 projects.
Read Google reviews of MINT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MINT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MINT
What is the possession date of MINT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MINT in J.B. Nagar, Mumbai is 25 November 2026 — 5 months later than 30 June 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for MINT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MINT's builder has filed on MahaRERA, the official one, is 25 November 2026, already 5 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MINT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MINT's builder applied to MahaRERA to extend the completion date once: to 25 November 2026, giving the reason "OC Recived".
What is the RERA number of MINT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MINT in J.B. Nagar, Mumbai is P51800053816.
Is MINT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MINT is registered as P51800053816 and its status is "Registered and active".
What is the construction status of MINT?
According to GharKundli's check of MahaRERA records (updated October 2026), MINT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING NO 3 WING A is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does MINT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is MINT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MINT is registered on MahaRERA as P51800053816, its completion date has moved 5 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MINT's possession date changes?
The latest dates are on MINT's MahaRERA page (P51800053816). GharKundli's Kundli Watch sends a free WhatsApp update on MINT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MINT have?
According to GharKundli's check of MahaRERA records (updated October 2026), MINT has one building filed: BUILDING NO 3 WING A with 14 floors and 121 units.
How big is the land of MINT?
According to GharKundli's check of MahaRERA records (updated October 2026), MINT stands on 5,756 sq m of land (about 1.4 acres), with 23,711 sq m of sanctioned built-up area.
What is the track record of MINT's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sumer Corporation (a group of 4 linked companies) has 5 projects on MahaRERA since 2019, this one included. Of the 5 GharKundli has checked: 4 still being built, 4 past the promised date (typically 12 months late); 1 lapsed. 31 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MINT?
Google Maps has reviews of MINT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MINT?
MINT by TULSIANI SUMER ASSOCIATES is in J.B. Nagar, Mumbai (pincode 400059), near Andheri East, Andheri West, D.N.Nagar, Maharashtra, and is registered on MahaRERA as P51800053816, per GharKundli's check of MahaRERA records. Its boundaries filed there include ADANI ELECTRICITY RECEIVING STATION, MCGM GARDEN.
How many homes are in MINT?
According to GharKundli's check of MahaRERA records (updated October 2026), MINT has 0 homes in 1 tower registered on MahaRERA, and 18% of them are sold or booked.
When was MINT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MINT was registered on MahaRERA on 1 December 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on MINT?
No court cases are listed for MINT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of MINT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is TULSIANI SUMER ASSOCIATES.
Check it yourself on MahaRERA
- How to check the possession date of MINT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in pincode 400059
- LUMA TOWERS A & B
- Trade Square 4th to 7th Floor
- MUBARAK MANZIL CHSL
- Gateway Residences
- LEELA BUSINESS PARK - II
- Privilon
- AQUINA
- SUDARSAN SATYANIVAS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.