Trade Square 4th to 7th Floor
by ATUL PROPERTIES · Andheri East, MumbaiAlso near Sakinaka, Saki Naka, Ballard Estate
Possession date of Trade Square 4th to 7th Floor: 30 September 2026, moved from 30 March 2025 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800020821. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (September 2026) has passed.
What do you want to know about Trade Square 4th to 7th Floor?
How the possession date of Trade Square 4th to 7th Floor has moved
30 March 2025
Completion date given when the project was registered
30 September 2026
Extended at the builder's request (MahaRERA application EA01072621652)
Reason the builder gave MahaRERA: “OC recived”
Source: Trade Square 4th to 7th Floor’s extension records on MahaRERA (P51800020821), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Trade Square 4th to 7th Floor
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 9 court cases, and how it ended
- Construction pace against the September 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800020821
- Status
- Lapsed (registration period ended)
- Builder
- ATUL PROPERTIES
- Location
- Andheri East, Mumbai · 400059
- Project type
- Commercial
- Registered on
- 10 May 2019
- Completion date at registration
- March 2025
- Latest completion date
- September 2026
- Delay so far
- 18 months
- Homes
- 0
- Sold or booked
- 43%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 9
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of Trade Square 4th to 7th Floor, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A 4th to 7th Floor | 0% | 100% | 100% | 100% |
| Wing B 4th to 7th Floor | 0% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Wing A 4th to 7th Floor: covers GROUND + 7TH FLOOR
- Wing B 4th to 7th Floor: covers GROUND + 7TH FLOOR
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Trade Square 4th to 7th Floor every month.
Trade Square 4th to 7th Floor: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 561 – 2,040 | 35 |
- Buildings: Wing A 4th to 7th Floor (6 floors, 20 units) · Wing B 4th to 7th Floor (6 floors, 15 units)
- Land: 4,755 sq m (about 1.2 acres) · sanctioned built-up 4,773 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Atul Projects (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, none past the promised date yet; 3 lapsed. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of Trade Square 4th to 7th Floor →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Trade Square 4th to 7th Floor: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Trade Square 4th to 7th Floor
What is the possession date of Trade Square 4th to 7th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Trade Square 4th to 7th Floor in Andheri East, Mumbai is 30 September 2026 — 18 months later than 30 March 2025, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Trade Square 4th to 7th Floor?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Trade Square 4th to 7th Floor's builder has filed on MahaRERA, the official one, is 30 September 2026, already 18 months later than the 30 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Trade Square 4th to 7th Floor extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Trade Square 4th to 7th Floor's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "OC recived".
What is the RERA number of Trade Square 4th to 7th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Trade Square 4th to 7th Floor in Andheri East, Mumbai is P51800020821.
Is Trade Square 4th to 7th Floor registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Trade Square 4th to 7th Floor is registered as P51800020821 and its status is "Lapsed (registration period ended)".
What is the construction status of Trade Square 4th to 7th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), Trade Square 4th to 7th Floor's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Trade Square 4th to 7th Floor have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Trade Square 4th to 7th Floor safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Trade Square 4th to 7th Floor is registered on MahaRERA as P51800020821, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Trade Square 4th to 7th Floor's possession date changes?
The latest dates are on Trade Square 4th to 7th Floor's MahaRERA page (P51800020821). GharKundli's Kundli Watch sends a free WhatsApp update on Trade Square 4th to 7th Floor every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Trade Square 4th to 7th Floor have?
According to GharKundli's check of MahaRERA records (updated October 2026), Trade Square 4th to 7th Floor has 2 buildings filed: Wing A 4th to 7th Floor with 6 floors and 20 units; Wing B 4th to 7th Floor with 6 floors and 15 units.
How big is the land of Trade Square 4th to 7th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), Trade Square 4th to 7th Floor stands on 4,755 sq m of land (about 1.2 acres), with 4,773 sq m of sanctioned built-up area.
What is the track record of Trade Square 4th to 7th Floor's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Atul Projects (a group of 4 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, all within the promised date; 2 still being built, none past the promised date yet; 3 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Trade Square 4th to 7th Floor?
Google Maps has reviews of Trade Square 4th to 7th Floor written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Trade Square 4th to 7th Floor?
Trade Square 4th to 7th Floor by ATUL PROPERTIES is in Andheri East, Mumbai (pincode 400059), near Sakinaka, Saki Naka, Ballard Estate, Maharashtra, and is registered on MahaRERA as P51800020821, per GharKundli's check of MahaRERA records.
How many homes are in Trade Square 4th to 7th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), Trade Square 4th to 7th Floor has 0 homes in 2 towers registered on MahaRERA, and 43% of them are sold or booked.
When was Trade Square 4th to 7th Floor registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Trade Square 4th to 7th Floor was registered on MahaRERA on 10 May 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on Trade Square 4th to 7th Floor?
9 court cases are listed for Trade Square 4th to 7th Floor on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Trade Square 4th to 7th Floor?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ATUL PROPERTIES.
Check it yourself on MahaRERA
- How to check the possession date of Trade Square 4th to 7th Floor
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Andheri East
- Privilon
- AQUINA
- Nityanand Nagar Vibhag IV Cooperative Housing Society Limited
- I Wing Samarth Enclave Andheri Chhaya CHS
- Pratap Vista
- Swapna Sudha CHS LTD
- Stellar Heights
- TRILIVE MAROL TOWER B
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.