Pratap Vista
by Parnakutir Real Estate Pvt Ltd (JPV) · Andheri East, MumbaiAlso near Andheri West, Mogra, Jogeshwari East
Possession date of Pratap Vista: 30 June 2028, moved from 31 December 2025 (30 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800034213, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Pratap Vista?
How the possession date of Pratap Vista has moved
31 December 2025
Completion date given when the project was registered
30 June 2028
Extended at the builder's request (MahaRERA application EA02032620071)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work”
Source: Pratap Vista’s extension records on MahaRERA (P51800034213), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Pratap Vista
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the June 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800034213
- Status
- Registered and active
- Builder
- Parnakutir Real Estate Pvt Ltd
- Location
- Andheri East, Mumbai · 400069
- Project type
- Residential / Group Housing
- Registered on
- 25 Mar 2022
- Completion date at registration
- December 2025
- Latest completion date
- June 2028
- Delay so far
- 30 months
- Homes
- 18
- Sold or booked
- 75%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Pratap Vista, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Pratap Vista | 100% | 10% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Pratap Vista: covers 11 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pratap Vista every month.
Pratap Vista: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 353 – 423 | 14 |
| Shops | 164 – 200 | 4 |
| 2 BHK | 568 – 599 | 3 |
| Multi Purpose Room | 132 | 1 |
- Buildings: Pratap Vista (11 floors, 22 units)
- Land: 688 sq m (about 0.2 acres) · sanctioned built-up 794 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
JPV Realtors (a group of 6 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 5 finished, all within the promised date; 7 still being built, 4 past the promised date (typically 8 months late). 4 complaints on MahaRERA across 3 projects.
Read Google reviews of Pratap Vista →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Pratap Vista: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Pratap Vista
What is the possession date of Pratap Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Pratap Vista in Andheri East, Mumbai is 30 June 2028 — 30 months later than 31 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Pratap Vista?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Pratap Vista's builder has filed on MahaRERA, the official one, is 30 June 2028, already 30 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Pratap Vista extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Vista's builder applied to MahaRERA to extend the completion date once: to 30 June 2028, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work".
What is the RERA number of Pratap Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Pratap Vista in Andheri East, Mumbai is P51800034213.
Is Pratap Vista registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Vista is registered as P51800034213 and its status is "Registered and active".
What is the construction status of Pratap Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Vista's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Pratap Vista is 10% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Pratap Vista have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Pratap Vista safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Vista is registered on MahaRERA as P51800034213, its completion date has moved 30 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Pratap Vista's possession date changes?
The latest dates are on Pratap Vista's MahaRERA page (P51800034213). GharKundli's Kundli Watch sends a free WhatsApp update on Pratap Vista every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Pratap Vista have?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Vista has one building filed: Pratap Vista with 11 floors and 22 units.
What are the flat sizes (carpet area) in Pratap Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Pratap Vista: 1 BHK: 353 to 423 sq ft carpet (14 homes); 2 BHK: 568 to 599 sq ft carpet (3 homes); Multi Purpose Room: 132 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Pratap Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Vista stands on 688 sq m of land (about 0.2 acres), with 794 sq m of sanctioned built-up area.
What is the track record of Pratap Vista's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), JPV Realtors (a group of 6 linked companies) has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 5 finished, all within the promised date; 7 still being built, 4 past the promised date (typically 8 months late). 4 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Pratap Vista?
Google Maps has reviews of Pratap Vista written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Pratap Vista?
Pratap Vista by Parnakutir Real Estate Pvt Ltd (JPV) is in Andheri East, Mumbai (pincode 400069), near Andheri West, Mogra, Jogeshwari East, Maharashtra, and is registered on MahaRERA as P51800034213, per GharKundli's check of MahaRERA records.
How many homes are in Pratap Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Vista has 18 homes in 1 tower registered on MahaRERA, and 75% of them are sold or booked.
When was Pratap Vista registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pratap Vista was registered on MahaRERA on 25 March 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on Pratap Vista?
1 court case is listed for Pratap Vista on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Pratap Vista?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Parnakutir Real Estate Pvt Ltd, the company JPV files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Pratap Vista
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400069
- THE KOLLAGE
- Commercial Project Andheri
- Parleshwar Aangan
- AARHAM
- Sajay Business Hub
- Sankirt Jasmine
- Mass Marquise
- Shri Shankarpuri
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.