Trilive Marol Tower B
by I-STAY HOUSING PRIVATE LIMITED (Starwing) · Andheri East, Mumbai 400059
What’s in the report? →Possession date of Trilive Marol Tower B (MahaRERA P51800053082): 31 December 2028, moved from 31 December 2027 (12 months later). It has 294 homes (Other, 183–219 sq ft carpet), 100% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800053082, and currently active.
Source: MahaRERA website — records for P51800053082, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Trilive Marol Tower B?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Trilive Marol Tower B has moved
31 December 2027
Completion date given when the project was registered
31 December 2028
Extended at the builder's request (MahaRERA application EA12122518653)
Reason the builder gave MahaRERA:
“We Would like to request you that the Project TRILIVE MAROL TOWER B which is located at CTS NO. 47, 48, 51/A, 52, 53/A, 1702 at Marol, Andheri, Mumbai Suburban, PIN 400093. having its Registration No P51800053082 was mentioned to be complet…” Read the full reason
“We Would like to request you that the Project TRILIVE MAROL TOWER B which is located at CTS NO. 47, 48, 51/A, 52, 53/A, 1702 at Marol, Andheri, Mumbai Suburban, PIN 400093. having its Registration No P51800053082 was mentioned to be completed on 31/12/2027. "Due to the open space constraints at the construction site of the Trilive Marol Tower B which is in turn slowing down the vehicular movements carrying the construction materials resulting in delay in the construction progress of Trilive Marol Tower B, hence an extension owing to the aforesaid is hereby sought by the Promoter". The proje…”
Source: Trilive Marol Tower B’s extension records on MahaRERA (P51800053082), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Trilive Marol Tower B
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- TRILIVE MAROL TOWER AP51800079406 · possession 30 Oct 2028
- MahaRERA registration
- P51800053082
- Status
- Registered and active
- Builder
- I-STAY HOUSING PRIVATE LIMITED
- Location
- Andheri East, Mumbai · 400059
- Project type
- Residential / Group Housing
- Registered on
- 16 Oct 2023
- Completion date at registration
- December 2027
- Latest completion date
- December 2028
- Delay so far
- 12 months
- Homes
- 294
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 6
Construction progress of Trilive Marol Tower B, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| I-STAY TOWER J STUDIO | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- I-STAY TOWER J STUDIO: covers Ground + 21 Floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Trilive Marol Tower B every 1–2 months.
Trilive Marol Tower B: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Other | 183 – 219 | 294 |
- Buildings: I-STAY TOWER J STUDIO (23 floors, 294 units)
- Land: 7,917 sq m (about 2.0 acres) · sanctioned built-up 42 sq m
- Boundaries filed include: SEVEN HILL HOSPITAL
- Land, as filed: CTS NO 47, 48, 51/A, 52, 53/A, 1702 OF VILLAGE MAROL
- Map: Get directions
The builder’s record and reviews
Starwing Developers (a group of 3 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 3 finished, all within the promised date; 10 still being built, 1 past the promised date; 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Trilive Marol Tower B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Trilive Marol Tower B: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Trilive Marol Tower B
What is the possession date of Trilive Marol Tower B?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Trilive Marol Tower B in Andheri East, Mumbai is 31 December 2028 — 12 months later than 31 December 2027, the date given at registration.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Trilive Marol Tower B?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Trilive Marol Tower B's builder has filed on MahaRERA, the official one, is 31 December 2028, already 12 months later than the 31 December 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Trilive Marol Tower B extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Trilive Marol Tower B's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "We Would like to request you that the Project TRILIVE MAROL TOWER B which is located at CTS NO. 47, 48, 51/A, 52, 53/A, 1702 at Marol, Andheri, Mumbai Suburban, PIN 400093. having its Registration No P51800053082 was mentioned to be completed on 31/12/2027. "Due to the open space constraints at the construction site of the Trilive Marol Tower B which is in turn slowing down the vehicular movements carrying the construction materials resulting in delay in the construction progress of Trilive Marol Tower B, hence an extension owing to the aforesaid is hereby sought by the Promoter". The proje…".
What is the RERA number of Trilive Marol Tower B?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Trilive Marol Tower B in Andheri East, Mumbai is P51800053082.
Is Trilive Marol Tower B registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Trilive Marol Tower B is registered as P51800053082 and its status is "Registered and active".
What is the current construction status of Trilive Marol Tower B? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Trilive Marol Tower B's status on MahaRERA is "Registered and active". As filed by the builder, slab work on I-STAY TOWER J STUDIO is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Trilive Marol Tower B have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Trilive Marol Tower B safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Trilive Marol Tower B is registered on MahaRERA as P51800053082, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Trilive Marol Tower B?
Trilive Marol Tower B is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Trilive Marol Tower B are 183 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Trilive Marol Tower B?
For a flat in Trilive Marol Tower B (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Trilive Marol Tower B received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Trilive Marol Tower B is still under construction, with 31 December 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Trilive Marol Tower B uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Trilive Marol Tower B was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Trilive Marol Tower B have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: TRILIVE MAROL TOWER A (P51800079406, possession 30 Oct 2028). Check that your agreement names the registration of your own wing.
How can I get updates if Trilive Marol Tower B's possession date changes?
The latest dates are on Trilive Marol Tower B's MahaRERA page (P51800053082). GharKundli's Kundli Watch sends a free WhatsApp update on Trilive Marol Tower B every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Trilive Marol Tower B have?
According to GharKundli's check of MahaRERA records (updated October 2026), Trilive Marol Tower B has one building filed: I-STAY TOWER J STUDIO with 23 floors and 294 units.
What are the flat sizes (carpet area) in Trilive Marol Tower B?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Trilive Marol Tower B: Other: 183 to 219 sq ft carpet (294 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Trilive Marol Tower B?
According to GharKundli's check of MahaRERA records (updated October 2026), Trilive Marol Tower B stands on 7,917 sq m of land (about 2.0 acres), with 42 sq m of sanctioned built-up area.
What is the track record of Trilive Marol Tower B's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Starwing Developers (a group of 3 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 3 finished, all within the promised date; 10 still being built, 1 past the promised date; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Trilive Marol Tower B?
Google Maps has reviews of Trilive Marol Tower B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Trilive Marol Tower B?
Trilive Marol Tower B by I-STAY HOUSING PRIVATE LIMITED (Starwing) is in Andheri East, Mumbai, pincode 400059, Maharashtra, and is registered on MahaRERA as P51800053082, per GharKundli's check of MahaRERA records. Its boundaries filed there include SEVEN HILL HOSPITAL. Its land is filed as CTS NO 47, 48, 51/A, 52, 53/A, 1702 OF VILLAGE MAROL. GharKundli lists all 108 MahaRERA projects in Andheri East (400059).
How many flats are in Trilive Marol Tower B, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Trilive Marol Tower B has 294 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Trilive Marol Tower B registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Trilive Marol Tower B was registered on MahaRERA on 16 October 2023. GharKundli did not find a title report on the land on file there.
Does Trilive Marol Tower B have any legal issues or court cases?
No court cases are listed for Trilive Marol Tower B on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Trilive Marol Tower B?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is I-STAY HOUSING PRIVATE LIMITED, the company Starwing files this project under, which has 6 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Trilive Marol Tower B
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Andheri East (400059)
- Privilon
- Aquina
- Trade Square 4th to 7th Floor
- Nityanand Nagar Vibhag IV Cooperative Housing Society Limited
- I Wing Samarth Enclave Andheri Chhaya CHS
- Swapna Sudha CHS LTD
- Pratap Vista
- Stellar Heights
Other projects by I-STAY HOUSING PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.