GharKundli

Ambit Vista

by Ambit Builders & Developers · Santacruz East, MumbaiAlso near Santacruz West, Vile Parle East, Vakola

Possession date of Ambit Vista: 30 April 2027, moved from 31 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800052265, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Ambit Vista?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Ambit Vista has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA05012619279)

    Reason the builder gave MahaRERA:
    “We had Registered the said Project under MahaRera on 9th August 2023 with the estimated date of completion being 31st December 2025. The completion date was based on Certain Assumptions of Construction Programs. The said Project consists of…” Read the full reason“We had Registered the said Project under MahaRera on 9th August 2023 with the estimated date of completion being 31st December 2025. The completion date was based on Certain Assumptions of Construction Programs. The said Project consists of One Rehab Building and Four Wings of Sale which are interconnected. Our Rehab wing is almost completed and application is being put up for obtaining Occupation Certificate. We have also completed RCC work of all wings and finishing work of 3 wings is in full swing. However during the Constructions of A wing the Retaining wall for Basement has been broken…”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Ambit Vista’s extension records on MahaRERA (P51800052265), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Ambit Vista

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800052265
Status
Registered and active
Builder
Ambit Builders & Developers
Location
Santacruz East, Mumbai · 400055
Project type
Residential / Group Housing
Registered on
9 Aug 2023
Completion date at registration
December 2025
Latest completion date
April 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
91
Sold or booked
76%
Towers
4
Complaints on MahaRERA
1
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of Ambit Vista, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A Wing100%100%57%0%
B Wing100%100%57%0%
C Wing100%100%90%0%
D Wing100%100%90%0%

Commencement certificate (CC), as filed on MahaRERA

  • A Wing: covers Plinth including Basement
  • B Wing: covers Plinth Including Basement
  • C Wing: covers Plinth including Basement
  • D Wing: covers Plinth including Basement

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ambit Vista every month.

Ambit Vista: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK530 – 73356
3 BHK900 – 1,04328
Shops156 – 32712
1 BHK3217
  • Buildings: A Wing (8 floors, 33 units) · B Wing (8 floors, 21 units) · C Wing (8 floors, 14 units) · D Wing (8 floors, 35 units)
  • Land: 2,540 sq m (about 0.6 acres) · sanctioned built-up 5,286 sq m
  • Boundaries filed include: Western Express Highway, Jawaharlal Nehru Marg, Western Railway Tracks
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Ambit Builders & Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 6 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Ambit Vista →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Ambit Vista: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Ambit Vista

What is the possession date of Ambit Vista?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ambit Vista in Santacruz East, Mumbai is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Ambit Vista?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Ambit Vista's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Ambit Vista extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Ambit Vista's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We had Registered the said Project under MahaRera on 9th August 2023 with the estimated date of completion being 31st December 2025. The completion date was based on Certain Assumptions of Construction Programs. The said Project consists of One Rehab Building and Four Wings of Sale which are interconnected. Our Rehab wing is almost completed and application is being put up for obtaining Occupation Certificate. We have also completed RCC work of all wings and finishing work of 3 wings is in full swing. However during the Constructions of A wing the Retaining wall for Basement has been broken…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Ambit Vista?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ambit Vista in Santacruz East, Mumbai is P51800052265.

Is Ambit Vista registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ambit Vista is registered as P51800052265 and its status is "Registered and active".

What is the construction status of Ambit Vista?

According to GharKundli's check of MahaRERA records (updated October 2026), Ambit Vista's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Ambit Vista have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Ambit Vista safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Ambit Vista is registered on MahaRERA as P51800052265, its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Ambit Vista's possession date changes?

The latest dates are on Ambit Vista's MahaRERA page (P51800052265). GharKundli's Kundli Watch sends a free WhatsApp update on Ambit Vista every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Ambit Vista have?

According to GharKundli's check of MahaRERA records (updated October 2026), Ambit Vista has 4 buildings filed: A Wing with 8 floors and 33 units; B Wing with 8 floors and 21 units; C Wing with 8 floors and 14 units; D Wing with 8 floors and 35 units.

What are the flat sizes (carpet area) in Ambit Vista?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ambit Vista: 2 BHK: 530 to 733 sq ft carpet (56 homes); 3 BHK: 900 to 1043 sq ft carpet (28 homes); 1 BHK: 321 sq ft carpet (7 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Ambit Vista?

According to GharKundli's check of MahaRERA records (updated October 2026), Ambit Vista stands on 2,540 sq m of land (about 0.6 acres), with 5,286 sq m of sanctioned built-up area.

What is the track record of Ambit Vista's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ambit Builders & Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 6 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Ambit Vista?

Google Maps has reviews of Ambit Vista written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Ambit Vista?

Ambit Vista by Ambit Builders & Developers is in Santacruz East, Mumbai (pincode 400055), near Santacruz West, Vile Parle East, Vakola, Maharashtra, and is registered on MahaRERA as P51800052265, per GharKundli's check of MahaRERA records. Its boundaries filed there include Western Express Highway, Jawaharlal Nehru Marg, Western Railway Tracks.

How many homes are in Ambit Vista?

According to GharKundli's check of MahaRERA records (updated October 2026), Ambit Vista has 91 homes in 4 towers registered on MahaRERA, and 76% of them are sold or booked.

When was Ambit Vista registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Ambit Vista was registered on MahaRERA on 9 August 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Ambit Vista?

No court cases are listed for Ambit Vista on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Ambit Vista?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ambit Builders & Developers.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400055

All 112 projects in Santacruz East (400055) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.