BISMILLAH RESIDENCY
by NIRBAN INFRASTRUCTURE PVT LTD · J J, MumbaiAlso near Nagpada, Agripada, Byculla
Possession: BISMILLAH RESIDENCY is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900008056. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about BISMILLAH RESIDENCY?
How the possession date of BISMILLAH RESIDENCY has moved
31 July 2018
Completion date given when the project was registered
31 July 2019
Extended at the builder's request (MahaRERA application EXT51900000694)
Reason the builder gave MahaRERA:
“Due to the policy for construction was pending for approval, a delay has been caused. This delay is beyond our control. It is now the D.C. Regulations of 2034 is been notified and have came into effect, which will enable the Developers to p…” Read the full reason
“Due to the policy for construction was pending for approval, a delay has been caused. This delay is beyond our control. It is now the D.C. Regulations of 2034 is been notified and have came into effect, which will enable the Developers to proceed further. It is in these circumstances, an application is hereby made for extension of time for handing over the possession under RERA.”
Source: BISMILLAH RESIDENCY’s extension records on MahaRERA (P51900008056), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on BISMILLAH RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the July 2019 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- BISMILLAH RESIDENCY PHASE IIP51900020441 · possession 30 Dec 2021
- MahaRERA registration
- P51900008056
- Status
- Completed
- Builder
- NIRBAN INFRASTRUCTURE PVT LTD
- Location
- J J, Mumbai · 400008
- Project type
- Residential / Group Housing
- Registered on
- 18 Aug 2017
- Completion date at registration
- July 2018
- Latest completion date
- July 2019
- Delay so far
- 12 months
- Homes
- 57
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of BISMILLAH RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BISMILLAH RESIDENCY | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on BISMILLAH RESIDENCY every month.
BISMILLAH RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: BISMILLAH RESIDENCY (30 floors)
- Land: 835 sq m (about 0.2 acres) · sanctioned built-up 3,443 sq m
- Boundaries filed include: SIR J J ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Nirban Infrastructure (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 20 months); 6 still being built, 2 past the promised date (typically 10 months late). 2 complaints on MahaRERA across 2 projects.
Read Google reviews of BISMILLAH RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
BISMILLAH RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about BISMILLAH RESIDENCY
What is the possession date of BISMILLAH RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BISMILLAH RESIDENCY in J J, Mumbai is 31 July 2019 — 12 months later than 31 July 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for BISMILLAH RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date BISMILLAH RESIDENCY's builder has filed on MahaRERA, the official one, is 31 July 2019, already 12 months later than the 31 July 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of BISMILLAH RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated November 2026), BISMILLAH RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 31 July 2019, giving the reason "Due to the policy for construction was pending for approval, a delay has been caused. This delay is beyond our control. It is now the D.C. Regulations of 2034 is been notified and have came into effect, which will enable the Developers to proceed further. It is in these circumstances, an application is hereby made for extension of time for handing over the possession under RERA.".
What is the RERA number of BISMILLAH RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BISMILLAH RESIDENCY in J J, Mumbai is P51900008056.
Is BISMILLAH RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), BISMILLAH RESIDENCY is registered as P51900008056 and its status is "Completed".
What is the construction status of BISMILLAH RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), BISMILLAH RESIDENCY's status on MahaRERA is "Completed". As filed by the builder, slab work on BISMILLAH RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does BISMILLAH RESIDENCY have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is BISMILLAH RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), BISMILLAH RESIDENCY is registered on MahaRERA as P51900008056, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does BISMILLAH RESIDENCY have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: BISMILLAH RESIDENCY PHASE II (P51900020441, possession 30 Dec 2021). Check that your agreement names the registration of your own wing.
How can I get updates if BISMILLAH RESIDENCY's possession date changes?
The latest dates are on BISMILLAH RESIDENCY's MahaRERA page (P51900008056). GharKundli's Kundli Watch sends a free WhatsApp update on BISMILLAH RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does BISMILLAH RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), BISMILLAH RESIDENCY has one building filed: BISMILLAH RESIDENCY with 30 floors.
How big is the land of BISMILLAH RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), BISMILLAH RESIDENCY stands on 835 sq m of land (about 0.2 acres), with 3,443 sq m of sanctioned built-up area.
What is the track record of BISMILLAH RESIDENCY's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirban Infrastructure (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 20 months); 6 still being built, 2 past the promised date (typically 10 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of BISMILLAH RESIDENCY?
Google Maps has reviews of BISMILLAH RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is BISMILLAH RESIDENCY?
BISMILLAH RESIDENCY by NIRBAN INFRASTRUCTURE PVT LTD is in J J, Mumbai (pincode 400008), near Nagpada, Agripada, Byculla, Maharashtra, and is registered on MahaRERA as P51900008056, per GharKundli's check of MahaRERA records. Its boundaries filed there include SIR J J ROAD.
How many homes are in BISMILLAH RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), BISMILLAH RESIDENCY has 57 homes in 1 tower registered on MahaRERA.
When was BISMILLAH RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), BISMILLAH RESIDENCY was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on BISMILLAH RESIDENCY?
No court cases are listed for BISMILLAH RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of BISMILLAH RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NIRBAN INFRASTRUCTURE PVT LTD, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of BISMILLAH RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400008
- AZAD RESIDENCY
- Anzar Residency
- FUEGO
- BAUG E UMAR
- BISMILLAH ELITE
- ONE INDIA HEIGHTS
- BISMILLAH ARCADE 2
- 11 ASTORIA
Other projects by NIRBAN INFRASTRUCTURE PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.