Nirban Bismillah Space Residency

by NIRBAN INFRASTRUCTURE PVT LTD · Byculla Division, Mumbai 400008Also near Nagpada, Agripada, MazgaonRegistered on MahaRERA as “BISMILLAH SPACE RESIDENCY”

What’s in the report? →

Possession date of Nirban Bismillah Space Residency (MahaRERA P51900054797): 30 April 2028. It has 158 homes (1 BHK, 2 BHK and 3 BHK, 403–666 sq ft carpet), 13% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900054797, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51900054797, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Nirban Bismillah Space Residency?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Nirban Bismillah Space Residency has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Nirban Bismillah Space Residency’s extension records on MahaRERA (P51900054797), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Nirban Bismillah Space Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900054797
Status
Registered and active
Builder
NIRBAN INFRASTRUCTURE PVT LTD
Location
Byculla Division, Mumbai · 400008
Project type
Residential / Group Housing
Registered on
12 Feb 2024
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
158
Sold or booked
13%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Nirban Bismillah Space Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NIRBAN SPACE RESIDENCY100%89.47%60%50%

Commencement certificate (CC), as filed on MahaRERA

  • NIRBAN SPACE RESIDENCY: covers 35 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nirban Bismillah Space Residency every 1–2 months.

Nirban Bismillah Space Residency: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK403 – 500135
2 BHK66622
Shops18 – 38914
3 BHK6661

The builder’s record and reviews

Nirban Infrastructure (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 20 months); 6 still being built, 2 past the promised date (typically 10 months late). 2 complaints on MahaRERA across 2 projects.

Read Google reviews of Nirban Bismillah Space Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Nirban Bismillah Space Residency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Nirban Bismillah Space Residency

What is the possession date of Nirban Bismillah Space Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nirban Bismillah Space Residency in Byculla Division, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Nirban Bismillah Space Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Nirban Bismillah Space Residency's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Nirban Bismillah Space Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Nirban Bismillah Space Residency in Byculla Division, Mumbai is P51900054797.

Is Nirban Bismillah Space Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirban Bismillah Space Residency is registered as P51900054797 and its status is "Registered and active".

What is the current construction status of Nirban Bismillah Space Residency? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirban Bismillah Space Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NIRBAN SPACE RESIDENCY is 89.47% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.

Does Nirban Bismillah Space Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Nirban Bismillah Space Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirban Bismillah Space Residency is registered on MahaRERA as P51900054797, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Nirban Bismillah Space Residency?

Nirban Bismillah Space Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Nirban Bismillah Space Residency are 403 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Nirban Bismillah Space Residency?

For a flat in Nirban Bismillah Space Residency (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Nirban Bismillah Space Residency received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Nirban Bismillah Space Residency is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Nirban Bismillah Space Residency a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirban Bismillah Space Residency is a redevelopment: 94 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Nirban Bismillah Space Residency uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Nirban Bismillah Space Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Nirban Bismillah Space Residency's possession date changes?

The latest dates are on Nirban Bismillah Space Residency's MahaRERA page (P51900054797). GharKundli's Kundli Watch sends a free WhatsApp update on Nirban Bismillah Space Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Nirban Bismillah Space Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirban Bismillah Space Residency has one building filed: NIRBAN SPACE RESIDENCY with 44 floors and 172 units.

What are the flat sizes (carpet area) in Nirban Bismillah Space Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Nirban Bismillah Space Residency: 1 BHK: 403 to 500 sq ft carpet (135 homes); 2 BHK: 666 sq ft carpet (22 homes); 3 BHK: 666 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Nirban Bismillah Space Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirban Bismillah Space Residency stands on 626 sq m of land (about 0.2 acres), with 8,278 sq m of sanctioned built-up area.

What is the track record of Nirban Bismillah Space Residency's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirban Infrastructure (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 20 months); 6 still being built, 2 past the promised date (typically 10 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Nirban Bismillah Space Residency?

Google Maps has reviews of Nirban Bismillah Space Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Nirban Bismillah Space Residency?

Nirban Bismillah Space Residency by NIRBAN INFRASTRUCTURE PVT LTD is in Byculla Division, Mumbai, pincode 400008 (near Nagpada, Agripada, Mazgaon), Maharashtra, and is registered on MahaRERA as P51900054797, per GharKundli's check of MahaRERA records. Its boundaries filed there include Ditimkar Road. Its land is filed as 1349 & 1348. GharKundli lists all 75 MahaRERA projects in Mumbai Central (400008).

How many flats are in Nirban Bismillah Space Residency, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirban Bismillah Space Residency has 158 homes in 1 tower registered on MahaRERA, and 13% of them are sold or booked.

When was Nirban Bismillah Space Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Nirban Bismillah Space Residency was registered on MahaRERA on 12 February 2024. GharKundli did not find a title report on the land on file there.

Does Nirban Bismillah Space Residency have any legal issues or court cases?

No court cases are listed for Nirban Bismillah Space Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Nirban Bismillah Space Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NIRBAN INFRASTRUCTURE PVT LTD, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai City →

Other projects in Ward E

All 75 projects in Mumbai Central (400008) →

Other projects by NIRBAN INFRASTRUCTURE PVT LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.