by Hridyaa Infraprojects LLP · Borivali East, Mumbai 400066Also near Borivali West, Rajendra Nagar, Daulat NagarRegistered on MahaRERA as “Arvind Niwas”

What’s in the report? →

Possession date of Hridyaa Arvind Niwas (MahaRERA P51800052356): 30 October 2026, moved from 30 June 2025 (12 months later), and it has already passed. It has 35 homes (1 BHK and 2 BHK, 319–668 sq ft carpet), 35% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800052356, and currently active. Its completion date has moved from June 2025 to October 2026: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800052356, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about Hridyaa Arvind Niwas?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Hridyaa Arvind Niwas has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EA06092502522)

    Reason the builder gave MahaRERA:
    “We, Hridyaa Infraprojects Llp, hereby declare the following with respect to the project “Arvind Niwas” bearing registration number P51800052356 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have…” Read the full reason“We, Hridyaa Infraprojects Llp, hereby declare the following with respect to the project “Arvind Niwas” bearing registration number P51800052356 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for the Occupation Cer…”
  3. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Hridyaa Arvind Niwas’s extension records on MahaRERA (P51800052356), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Hridyaa Arvind Niwas

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800052356
Status
Registered and active
Builder
Hridyaa Infraprojects LLP
Location
Borivali East, Mumbai · 400066
Project type
Others
Registered on
21 Aug 2023
Completion date at registration
June 2025
Latest completion date
October 2026
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
35
Sold or booked
35%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Hridyaa Arvind Niwas, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Arvind Niwas100%100%100%20%

Commencement certificate (CC), as filed on MahaRERA

  • Arvind Niwas: covers G+10

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hridyaa Arvind Niwas every 1–2 months.

Hridyaa Arvind Niwas: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK319 – 48127
2 BHK592 – 6688
Other215 – 3195
Shops166 – 2262
  • Buildings: Arvind Niwas (11 floors, 42 units)
  • Car parking: 9 covered
  • Land: 378 sq m (about 0.1 acres) · sanctioned built-up 1,226 sq m
  • Boundaries filed include: Kasturba Road No 05
  • Land, as filed: FP NO. 71J of TPS II CTS No 457, 457/1 to 457/4
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Hridyaa Arvind Niwas →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Hridyaa Arvind Niwas: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Hridyaa Arvind Niwas

What is the possession date of Hridyaa Arvind Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Hridyaa Arvind Niwas in Borivali East, Mumbai is 30 October 2026 — 12 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Hridyaa Arvind Niwas?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Hridyaa Arvind Niwas's builder has filed on MahaRERA, the official one, is 30 October 2026, already 12 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Hridyaa Arvind Niwas extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Hridyaa Arvind Niwas's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "We, Hridyaa Infraprojects Llp, hereby declare the following with respect to the project “Arvind Niwas” bearing registration number P51800052356 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for the Occupation Cer…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Hridyaa Arvind Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Hridyaa Arvind Niwas in Borivali East, Mumbai is P51800052356.

Is Hridyaa Arvind Niwas registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Hridyaa Arvind Niwas is registered as P51800052356 and its status is "Registered and active".

What is the current construction status of Hridyaa Arvind Niwas? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Hridyaa Arvind Niwas's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Arvind Niwas is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Hridyaa Arvind Niwas have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Hridyaa Arvind Niwas safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Hridyaa Arvind Niwas is registered on MahaRERA as P51800052356, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Hridyaa Arvind Niwas?

Hridyaa Arvind Niwas is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Hridyaa Arvind Niwas are 319 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Hridyaa Arvind Niwas?

For a flat in Hridyaa Arvind Niwas (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Hridyaa Arvind Niwas received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Hridyaa Arvind Niwas is still under construction, with 30 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Hridyaa Arvind Niwas a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Hridyaa Arvind Niwas is a redevelopment: 16 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Hridyaa Arvind Niwas uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Hridyaa Arvind Niwas was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Hridyaa Arvind Niwas's possession date changes?

The latest dates are on Hridyaa Arvind Niwas's MahaRERA page (P51800052356). GharKundli's Kundli Watch sends a free WhatsApp update on Hridyaa Arvind Niwas every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Hridyaa Arvind Niwas have?

According to GharKundli's check of MahaRERA records (updated October 2026), Hridyaa Arvind Niwas has one building filed: Arvind Niwas with 11 floors and 42 units.

What are the flat sizes (carpet area) in Hridyaa Arvind Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Hridyaa Arvind Niwas: 1 BHK: 319 to 481 sq ft carpet (27 homes); 2 BHK: 592 to 668 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Hridyaa Arvind Niwas have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 9 covered car parking spaces for Hridyaa Arvind Niwas.

How big is the land of Hridyaa Arvind Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), Hridyaa Arvind Niwas stands on 378 sq m of land (about 0.1 acres), with 1,226 sq m of sanctioned built-up area.

What are the reviews of Hridyaa Arvind Niwas?

Google Maps has reviews of Hridyaa Arvind Niwas written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Hridyaa Arvind Niwas?

Hridyaa Arvind Niwas by Hridyaa Infraprojects LLP is in Borivali East, Mumbai, pincode 400066 (near Borivali West, Rajendra Nagar, Daulat Nagar), Maharashtra, and is registered on MahaRERA as P51800052356, per GharKundli's check of MahaRERA records. Its boundaries filed there include Kasturba Road No 05. Its land is filed as FP NO. 71J of TPS II CTS No 457, 457/1 to 457/4. GharKundli lists all 228 MahaRERA projects in Borivali East (400066).

How many flats are in Hridyaa Arvind Niwas, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Hridyaa Arvind Niwas has 35 homes in 1 tower registered on MahaRERA, and 35% of them are sold or booked.

When was Hridyaa Arvind Niwas registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Hridyaa Arvind Niwas was registered on MahaRERA on 21 August 2023. GharKundli did not find a title report on the land on file there.

Does Hridyaa Arvind Niwas have any legal issues or court cases?

No court cases are listed for Hridyaa Arvind Niwas on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Hridyaa Arvind Niwas?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Hridyaa Infraprojects LLP.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Borivali East (400066)

All 228 projects in Borivali East (400066) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.