Poddar Venus

by PODDAR REALTY INDIA PRIVATE LIMITED · Jogeshwari East, Mumbai 400060Also near Seepz, Jogeshwari West, Chakala MIDCRegistered on MahaRERA as “VENUS”

What’s in the report? →

Possession date of Poddar Venus (MahaRERA P51800053403): 30 September 2025, moved from 31 March 2025 (6 months later), and it has already passed. It has 40 homes (1 BHK, 322–434 sq ft carpet), 65% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800053403. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P51800053403, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (September 2025) has passed.

What do you want to know about Poddar Venus?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Poddar Venus has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 30 September 2025

    Extended at the builder's request (MahaRERA application EXT51800027946)

    Reason the builder gave MahaRERA: “We are in process of obtaining Occupation Certificate which will take 3 to 4 months time”

Source: Poddar Venus’s extension records on MahaRERA (P51800053403), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Poddar Venus

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800053403
Status
Lapsed (registration period ended)
Builder
PODDAR REALTY INDIA PRIVATE LIMITED
Location
Jogeshwari East, Mumbai · 400060
Project type
Residential / Group Housing
Registered on
31 Oct 2023
Completion date at registration
March 2025
Latest completion date
September 2025
Delay so far
6 months
Homes
40
Sold or booked
65%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Poddar Venus, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VENUS100%100%100%0%

Commencement certificate (CC), as filed on MahaRERA

Latest CC order on MahaRERA: dated 23/10/2023.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Poddar Venus every 1–2 months.

Poddar Venus: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK322 – 43440
  • Buildings: VENUS (11 floors)
  • Land: 510 sq m (about 0.1 acres) · sanctioned built-up 1,511 sq m
  • Land, as filed: 260/A/2
  • Map: Get directions

The builder’s record and reviews

Poddar Infracon (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 2 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Poddar Venus →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Poddar Venus: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Poddar Venus

What is the possession date of Poddar Venus?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Poddar Venus in Jogeshwari East, Mumbai is 30 September 2025 — 6 months later than 31 March 2025, the date given at registration. That date has already passed.

The date has already moved 6 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Poddar Venus?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Poddar Venus's builder has filed on MahaRERA, the official one, is 30 September 2025, already 6 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Poddar Venus extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Poddar Venus's builder applied to MahaRERA to extend the completion date once: to 30 September 2025, giving the reason "We are in process of obtaining Occupation Certificate which will take 3 to 4 months time".

What is the RERA number of Poddar Venus?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Poddar Venus in Jogeshwari East, Mumbai is P51800053403.

Is Poddar Venus registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Poddar Venus is registered as P51800053403 and its status is "Lapsed (registration period ended)".

What is the current construction status of Poddar Venus? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Poddar Venus's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on VENUS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Poddar Venus have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Poddar Venus safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Poddar Venus is registered on MahaRERA as P51800053403, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Poddar Venus?

Poddar Venus isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Poddar Venus are 322 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Poddar Venus?

For a flat in Poddar Venus (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Poddar Venus received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Poddar Venus isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 September 2025 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Poddar Venus?

According to GharKundli's check of MahaRERA records (updated October 2026), Poddar Venus's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 September 2025) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is Poddar Venus a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Poddar Venus is a redevelopment: 20 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Poddar Venus uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Poddar Venus was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Poddar Venus's possession date changes?

The latest dates are on Poddar Venus's MahaRERA page (P51800053403). GharKundli's Kundli Watch sends a free WhatsApp update on Poddar Venus every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Poddar Venus have?

According to GharKundli's check of MahaRERA records (updated October 2026), Poddar Venus has one building filed: VENUS with 11 floors.

What are the flat sizes (carpet area) in Poddar Venus?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Poddar Venus: 1 BHK: 322 to 434 sq ft carpet (40 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Poddar Venus?

According to GharKundli's check of MahaRERA records (updated October 2026), Poddar Venus stands on 510 sq m of land (about 0.1 acres), with 1,511 sq m of sanctioned built-up area.

What is the track record of Poddar Venus's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Poddar Infracon (a group of 3 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 2 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Poddar Venus?

Google Maps has reviews of Poddar Venus written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Poddar Venus?

Poddar Venus by PODDAR REALTY INDIA PRIVATE LIMITED is in Jogeshwari East, Mumbai, pincode 400060 (near Seepz, Jogeshwari West, Chakala MIDC), Maharashtra, and is registered on MahaRERA as P51800053403, per GharKundli's check of MahaRERA records. Its land is filed as 260/A/2. GharKundli lists all 97 MahaRERA projects in Jogeshwari East (400060).

How many flats are in Poddar Venus, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Poddar Venus has 40 homes in 1 tower registered on MahaRERA, and 65% of them are sold or booked.

When was Poddar Venus registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Poddar Venus was registered on MahaRERA on 31 October 2023. GharKundli did not find a title report on the land on file there.

Does Poddar Venus have any legal issues or court cases?

No court cases are listed for Poddar Venus on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Poddar Venus?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PODDAR REALTY INDIA PRIVATE LIMITED.

Other projects in Jogeshwari East (400060)

All 97 projects in Jogeshwari East (400060) →