by HFI INDUSTRIES · Jogeshwari, MumbaiAlso near Vesava, Andheri Railway Station

Possession date of AKSA TOWER: 30 January 2027, moved from 31 March 2025 (18 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800055503, and currently active. Its completion date has moved from March 2025 to January 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AKSA TOWER?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AKSA TOWER has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 30 November 2025

    Extended at the builder's request (MahaRERA application EXT51800024787)

    Reason the builder gave MahaRERA: “We are making the application to Extend the completion date of our above project Under Section 6 of Real Estate (Regulations and Development) Act, 2016 upto 30/11/2025”
  3. 30 September 2026

    Extended at the builder's request (MahaRERA application EA12112518311)

    Reason the builder gave MahaRERA:
    “We are in the process of obtaining the requisite No Objection Certificates (NOCs) necessary for the issuance of the Occupation Certificate (OC). We anticipate receiving the OC well before 30th August 2026. The on-site work has been complete…” Read the full reason“We are in the process of obtaining the requisite No Objection Certificates (NOCs) necessary for the issuance of the Occupation Certificate (OC). We anticipate receiving the OC well before 30th August 2026. The on-site work has been completed up to approximately 85% overall.”
  4. 30 January 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: AKSA TOWER’s extension records on MahaRERA (P51800055503), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AKSA TOWER

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the January 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800055503
Status
Registered and active
Builder
HFI INDUSTRIES
Location
Jogeshwari, Mumbai · 400102
Project type
Residential / Group Housing
Registered on
2 Apr 2024
Completion date at registration
March 2025
Latest completion date
January 2027
Delay so far
18 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
65
Sold or booked
25%
Towers
1
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found

Construction progress of AKSA TOWER, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING 3F100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING 3F: covers 17 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AKSA TOWER every month.

AKSA TOWER: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK599 – 63264
4 BHK1,2131
  • Buildings: BUILDING 3F (18 floors, 65 units)
  • Land: 6,512 sq m (about 1.6 acres) · sanctioned built-up 4,226 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of AKSA TOWER →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AKSA TOWER: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AKSA TOWER

What is the possession date of AKSA TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AKSA TOWER in Jogeshwari, Mumbai is 30 January 2027 — 18 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for AKSA TOWER?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AKSA TOWER's builder has filed on MahaRERA, the official one, is 30 January 2027, already 18 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AKSA TOWER extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSA TOWER's builder applied to MahaRERA to extend the completion date 2 times: to 30 November 2025, giving the reason "We are making the application to Extend the completion date of our above project Under Section 6 of Real Estate (Regulations and Development) Act, 2016 upto 30/11/2025"; to 30 September 2026, giving the reason "We are in the process of obtaining the requisite No Objection Certificates (NOCs) necessary for the issuance of the Occupation Certificate (OC). We anticipate receiving the OC well before 30th August 2026. The on-site work has been completed up to approximately 85% overall.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of AKSA TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AKSA TOWER in Jogeshwari, Mumbai is P51800055503.

Is AKSA TOWER registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSA TOWER is registered as P51800055503 and its status is "Registered and active".

What is the construction status of AKSA TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSA TOWER's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING 3F is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does AKSA TOWER have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AKSA TOWER safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSA TOWER is registered on MahaRERA as P51800055503, its completion date has moved 18 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AKSA TOWER's possession date changes?

The latest dates are on AKSA TOWER's MahaRERA page (P51800055503). GharKundli's Kundli Watch sends a free WhatsApp update on AKSA TOWER every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AKSA TOWER have?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSA TOWER has one building filed: BUILDING 3F with 18 floors and 65 units.

What are the flat sizes (carpet area) in AKSA TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for AKSA TOWER: 2 BHK: 599 to 632 sq ft carpet (64 homes); 4 BHK: 1213 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of AKSA TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSA TOWER stands on 6,512 sq m of land (about 1.6 acres), with 4,226 sq m of sanctioned built-up area.

Where can I read reviews of AKSA TOWER?

Google Maps has reviews of AKSA TOWER written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AKSA TOWER?

AKSA TOWER by HFI INDUSTRIES is in Jogeshwari, Mumbai (pincode 400102), near Vesava, Andheri Railway Station, Maharashtra, and is registered on MahaRERA as P51800055503, per GharKundli's check of MahaRERA records.

How many homes are in AKSA TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSA TOWER has 65 homes in 1 tower registered on MahaRERA, and 25% of them are sold or booked.

When was AKSA TOWER registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AKSA TOWER was registered on MahaRERA on 2 April 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on AKSA TOWER?

1 court case is listed for AKSA TOWER on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of AKSA TOWER?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HFI INDUSTRIES.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400102

All 115 projects in Jogeshwari West (400102) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.