Ashiyana Apartment CHSL Ltd
by Pearl Infra · Malad East, Mumbai 400097Also near Malad West Dely, Motilal Nagar
What’s in the report? →Possession date of Ashiyana Apartment CHSL Ltd (MahaRERA P51800054430): 30 January 2028, moved from 30 September 2026 (12 months later). It has 28 homes (1 Room Kitchen, 1 BHK and 2 BHK, 169–770 sq ft carpet), 9% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800054430, and currently active. Its completion date has moved from September 2026 to January 2028: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800054430, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Ashiyana Apartment CHSL Ltd?
2 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Ashiyana Apartment CHSL Ltd has moved
30 September 2026
Completion date given when the project was registered
30 September 2027
Extended at the builder's request (MahaRERA application EA06082502313)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, and site challenges. Despite these setbacks, we are workin…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30-09-2027, to complete the project and fulfil all regulatory requirements.”30 January 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Ashiyana Apartment CHSL Ltd’s extension records on MahaRERA (P51800054430), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ashiyana Apartment CHSL Ltd
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 court cases, and how it ended
- Construction pace against the January 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800054430
- Status
- Registered and active
- Builder
- Pearl Infra
- Location
- Malad East, Mumbai · 400097
- Project type
- Residential / Group Housing
- Registered on
- 19 Jan 2024
- Completion date at registration
- September 2026
- Latest completion date
- January 2028
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 28
- Sold or booked
- 9%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Ashiyana Apartment CHSL Ltd, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Ashiyana Apartment CHSL Ltd | 100% | 65% | 15% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Ashiyana Apartment CHSL Ltd: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ashiyana Apartment CHSL Ltd every 1–2 months.
Ashiyana Apartment CHSL Ltd: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 453 – 587 | 25 |
| 1 Room Kitchen | 169 | 1 |
| 1 BHK | 391 | 1 |
| 3 BHK | 770 | 1 |
- Buildings: Ashiyana Apartment CHSL Ltd (9 floors, 28 units)
- Car parking: 30 covered
- Land: 919 sq m (about 0.2 acres) · sanctioned built-up 1,485 sq m
- Land, as filed: 97A/27
- Map: Get directions
The builder’s record and reviews
Pearl Infra has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Ashiyana Apartment CHSL Ltd →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ashiyana Apartment CHSL Ltd: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Ashiyana Apartment CHSL Ltd
What is the possession date of Ashiyana Apartment CHSL Ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ashiyana Apartment CHSL Ltd in Malad East, Mumbai is 30 January 2028 — 12 months later than 30 September 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Ashiyana Apartment CHSL Ltd?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ashiyana Apartment CHSL Ltd's builder has filed on MahaRERA, the official one, is 30 January 2028, already 12 months later than the 30 September 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Ashiyana Apartment CHSL Ltd extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Ashiyana Apartment CHSL Ltd's builder applied to MahaRERA to extend the completion date once: to 30 September 2027, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 30-09-2027, to complete the project and fulfil all regulatory requirements.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Ashiyana Apartment CHSL Ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ashiyana Apartment CHSL Ltd in Malad East, Mumbai is P51800054430.
Is Ashiyana Apartment CHSL Ltd registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ashiyana Apartment CHSL Ltd is registered as P51800054430 and its status is "Registered and active".
What is the current construction status of Ashiyana Apartment CHSL Ltd? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Ashiyana Apartment CHSL Ltd's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Ashiyana Apartment CHSL Ltd is 65% done and internal work 15%. GharKundli's full report compares construction progress with the deadline.
Does Ashiyana Apartment CHSL Ltd have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Ashiyana Apartment CHSL Ltd safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Ashiyana Apartment CHSL Ltd is registered on MahaRERA as P51800054430, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Ashiyana Apartment CHSL Ltd?
Ashiyana Apartment CHSL Ltd is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Ashiyana Apartment CHSL Ltd are 169 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Ashiyana Apartment CHSL Ltd?
For a flat in Ashiyana Apartment CHSL Ltd (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Ashiyana Apartment CHSL Ltd received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ashiyana Apartment CHSL Ltd is still under construction, with 30 January 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Ashiyana Apartment CHSL Ltd a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Ashiyana Apartment CHSL Ltd is a redevelopment: 17 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Ashiyana Apartment CHSL Ltd uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ashiyana Apartment CHSL Ltd was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Ashiyana Apartment CHSL Ltd's possession date changes?
The latest dates are on Ashiyana Apartment CHSL Ltd's MahaRERA page (P51800054430). GharKundli's Kundli Watch sends a free WhatsApp update on Ashiyana Apartment CHSL Ltd every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ashiyana Apartment CHSL Ltd have?
According to GharKundli's check of MahaRERA records (updated October 2026), Ashiyana Apartment CHSL Ltd has one building filed: Ashiyana Apartment CHSL Ltd with 9 floors and 28 units.
What are the flat sizes (carpet area) in Ashiyana Apartment CHSL Ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ashiyana Apartment CHSL Ltd: 2 BHK: 453 to 587 sq ft carpet (25 homes); 1 Room Kitchen: 169 sq ft carpet (1 homes); 1 BHK: 391 sq ft carpet (1 homes); 3 BHK: 770 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Ashiyana Apartment CHSL Ltd have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 30 covered car parking spaces for Ashiyana Apartment CHSL Ltd.
How big is the land of Ashiyana Apartment CHSL Ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), Ashiyana Apartment CHSL Ltd stands on 919 sq m of land (about 0.2 acres), with 1,485 sq m of sanctioned built-up area.
What is the track record of Ashiyana Apartment CHSL Ltd's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Pearl Infra has 2 projects on MahaRERA since 2024, this one included. Of the 2 GharKundli has checked: 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Ashiyana Apartment CHSL Ltd?
Google Maps has reviews of Ashiyana Apartment CHSL Ltd written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Ashiyana Apartment CHSL Ltd?
Ashiyana Apartment CHSL Ltd by Pearl Infra is in Malad East, Mumbai, pincode 400097 (near Malad West Dely, Motilal Nagar), Maharashtra, and is registered on MahaRERA as P51800054430, per GharKundli's check of MahaRERA records. Its land is filed as 97A/27. GharKundli lists all 195 MahaRERA projects in Malad East (400097).
How many flats are in Ashiyana Apartment CHSL Ltd, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Ashiyana Apartment CHSL Ltd has 28 homes in 1 tower registered on MahaRERA, and 9% of them are sold or booked.
When was Ashiyana Apartment CHSL Ltd registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ashiyana Apartment CHSL Ltd was registered on MahaRERA on 19 January 2024. GharKundli did not find a title report on the land on file there.
Does Ashiyana Apartment CHSL Ltd have any legal issues or court cases?
2 court cases are listed for Ashiyana Apartment CHSL Ltd on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of Ashiyana Apartment CHSL Ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Pearl Infra, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Ashiyana Apartment CHSL Ltd
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Malad East (400097)
- Aarambh Phase III by group Satellite
- L&T Realty Ahana Tower B
- Namo Whispering Bliss
- Upper East 97
- Nivetia Heights
- Vardhan Royale
- L&T Realty Ahana Tower A
- Pearl Solitaire
Other projects by Pearl Infra
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.