Mahavir Park Grandezza
by SHREE MAHAVIR ESTATES · Andheri West, Mumbai 400053Also near Vesava, Andheri Railway Station, JuhuRegistered on MahaRERA as “PARK GRANDEZZA”
What’s in the report? →Possession date of Mahavir Park Grandezza (MahaRERA P51800066462): 15 June 2034. It has 140 homes (3 BHK, 1090–1243 sq ft carpet), 34% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800066462, and currently active. Its completion date is now June 2034, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800066462, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Mahavir Park Grandezza?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Mahavir Park Grandezza has moved
15 February 2034
Completion date given when the project was registered
15 June 2034
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Mahavir Park Grandezza’s extension records on MahaRERA (P51800066462), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mahavir Park Grandezza
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2034 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800066462
- Status
- Registered and active
- Builder
- SHREE MAHAVIR ESTATES
- Location
- Andheri West, Mumbai · 400053
- Project type
- Residential / Group Housing
- Registered on
- 11 Jun 2024
- Completion date at registration
- February 2034
- Latest completion date
- June 2034
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 140
- Sold or booked
- 34%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of Mahavir Park Grandezza, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING A | 25% | 10% | 0% | 0% |
| Wing B | 25% | 10% | 0% | 0% |
| Wing C | 25% | 10% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- WING A: covers PLINTH LEVEL
- Wing B: covers PLINTH LEVEL
- Wing C: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mahavir Park Grandezza every 1–2 months.
Mahavir Park Grandezza: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 1,090 – 1,243 | 140 |
- Buildings: WING A (11 floors, 53 units) · Wing B (11 floors, 34 units) · Wing C (9 floors, 53 units)
- Land: 2,360 sq m (about 0.6 acres) · sanctioned built-up 6,362 sq m
- Boundaries filed include: PRIMARY SCHOOL
- Land, as filed: 195(pt)
- Map: Get directions
The builder’s record and reviews
Shree Mahavir Estates (a group of 7 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 7 finished, 4 within the promised date and 3 needed more time (typically 12 months); 9 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Mahavir Park Grandezza →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mahavir Park Grandezza: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Mahavir Park Grandezza
What is the possession date of Mahavir Park Grandezza?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mahavir Park Grandezza in Andheri West, Mumbai is 15 June 2034, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Mahavir Park Grandezza?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mahavir Park Grandezza's builder has filed on MahaRERA, the official one, is 15 June 2034, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Mahavir Park Grandezza?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mahavir Park Grandezza in Andheri West, Mumbai is P51800066462.
Is Mahavir Park Grandezza registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Park Grandezza is registered as P51800066462 and its status is "Registered and active".
What is the current construction status of Mahavir Park Grandezza? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Park Grandezza's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 10% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Mahavir Park Grandezza have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Mahavir Park Grandezza safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Park Grandezza is registered on MahaRERA as P51800066462, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Mahavir Park Grandezza?
Mahavir Park Grandezza is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Mahavir Park Grandezza start at 1090 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Mahavir Park Grandezza?
For a flat in Mahavir Park Grandezza (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Mahavir Park Grandezza received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Park Grandezza is still under construction, with 15 June 2034 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Mahavir Park Grandezza a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Park Grandezza is a redevelopment: 40 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Mahavir Park Grandezza uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Mahavir Park Grandezza was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Mahavir Park Grandezza's possession date changes?
The latest dates are on Mahavir Park Grandezza's MahaRERA page (P51800066462). GharKundli's Kundli Watch sends a free WhatsApp update on Mahavir Park Grandezza every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mahavir Park Grandezza have?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Park Grandezza has 3 buildings filed: WING A with 11 floors and 53 units; Wing B with 11 floors and 34 units; Wing C with 9 floors and 53 units.
What are the flat sizes (carpet area) in Mahavir Park Grandezza?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Mahavir Park Grandezza: 3 BHK: 1090 to 1243 sq ft carpet (140 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Mahavir Park Grandezza?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Park Grandezza stands on 2,360 sq m of land (about 0.6 acres), with 6,362 sq m of sanctioned built-up area.
What is the track record of Mahavir Park Grandezza's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Mahavir Estates (a group of 7 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 7 finished, 4 within the promised date and 3 needed more time (typically 12 months); 9 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Mahavir Park Grandezza?
Google Maps has reviews of Mahavir Park Grandezza written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Mahavir Park Grandezza?
Mahavir Park Grandezza by SHREE MAHAVIR ESTATES is in Andheri West, Mumbai, pincode 400053 (near Vesava, Andheri Railway Station, Juhu), Maharashtra, and is registered on MahaRERA as P51800066462, per GharKundli's check of MahaRERA records. Its boundaries filed there include PRIMARY SCHOOL. Its land is filed as 195(pt). GharKundli lists all 162 MahaRERA projects in Andheri West (400053).
How many flats are in Mahavir Park Grandezza, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Park Grandezza has 140 homes in 3 towers registered on MahaRERA, and 34% of them are sold or booked.
When was Mahavir Park Grandezza registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Park Grandezza was registered on MahaRERA on 11 June 2024. GharKundli did not find a title report on the land on file there.
Does Mahavir Park Grandezza have any legal issues or court cases?
No court cases are listed for Mahavir Park Grandezza on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Mahavir Park Grandezza?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE MAHAVIR ESTATES, which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Mahavir Park Grandezza
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Andheri West (400053)
- Parinee i
- Naman Fifty Eight
- Fame Garden
- Amaha Sunflower
- Gayatri Enclave
- Tru Gardenia
- Esto Arkis
- Sunbeam Heights
Other projects by SHREE MAHAVIR ESTATES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.