Raheja SkyPolis - 1

by Radha Krishna Properties Private Limited · near inorbit mall, Mumbai 400064

What’s in the report? →

Possession date of Raheja SkyPolis - 1 (MahaRERA P51800076650): 30 April 2035. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800076650, and currently active. Its completion date is now April 2035, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800076650, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Raheja SkyPolis - 1?

5 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Raheja SkyPolis - 1 has moved

  1. 31 December 2034

    Completion date given when the project was registered

  2. 30 April 2035

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Raheja SkyPolis - 1’s extension records on MahaRERA (P51800076650), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Raheja SkyPolis - 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 5 court cases, and how it ended
  • Construction pace against the April 2035 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800076650
Status
Registered and active
Builder
Radha Krishna Properties Private Limited
Location
near inorbit mall, Mumbai · 400064
Project type
Residential / Group Housing
Registered on
20 Jun 2024
Completion date at registration
December 2034
Latest completion date
April 2035
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
0
Court cases listed
5
Title report on file
Not found

Construction progress of Raheja SkyPolis - 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Raheja SkyPolis-1 / null0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Raheja SkyPolis - 1 every 1–2 months.

Raheja SkyPolis - 1: buildings, flats and land, as filed on MahaRERA

  • Land: 80,650 sq m (about 19.9 acres) · sanctioned built-up 711 sq m
  • Land, as filed: 1406-A/14
  • Map: Get directions

The builder’s record and reviews

Raheja Universal (a group of 2 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 2 finished, all within the promised date; 17 still being built, none past the promised date yet. 18 complaints on MahaRERA across 7 projects.

Read Google reviews of Raheja SkyPolis - 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Raheja SkyPolis - 1: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Raheja SkyPolis - 1

What is the possession date of Raheja SkyPolis - 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Raheja SkyPolis - 1 in near inorbit mall, Mumbai is 30 April 2035, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Raheja SkyPolis - 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Raheja SkyPolis - 1's builder has filed on MahaRERA, the official one, is 30 April 2035, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Raheja SkyPolis - 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Raheja SkyPolis - 1 in near inorbit mall, Mumbai is P51800076650.

Is Raheja SkyPolis - 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja SkyPolis - 1 is registered as P51800076650 and its status is "Registered and active".

What is the current construction status of Raheja SkyPolis - 1? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja SkyPolis - 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Raheja SkyPolis-1 / null is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Raheja SkyPolis - 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Raheja SkyPolis - 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja SkyPolis - 1 is registered on MahaRERA as P51800076650, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Raheja SkyPolis - 1?

Raheja SkyPolis - 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Raheja SkyPolis - 1?

For a flat in Raheja SkyPolis - 1 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Raheja SkyPolis - 1 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Raheja SkyPolis - 1 is still under construction, with 30 April 2035 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Raheja SkyPolis - 1 a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja SkyPolis - 1's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Raheja SkyPolis - 1 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Raheja SkyPolis - 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Raheja SkyPolis - 1's possession date changes?

The latest dates are on Raheja SkyPolis - 1's MahaRERA page (P51800076650). GharKundli's Kundli Watch sends a free WhatsApp update on Raheja SkyPolis - 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Raheja SkyPolis - 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja SkyPolis - 1 stands on 80,650 sq m of land (about 19.9 acres), with 711 sq m of sanctioned built-up area.

What is the track record of Raheja SkyPolis - 1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja Universal (a group of 2 linked companies) has 19 projects on MahaRERA since 2017, this one included. Of the 19 GharKundli has checked: 2 finished, all within the promised date; 17 still being built, none past the promised date yet. 18 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Raheja SkyPolis - 1?

Google Maps has reviews of Raheja SkyPolis - 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Raheja SkyPolis - 1?

Raheja SkyPolis - 1 by Radha Krishna Properties Private Limited is in near inorbit mall, Mumbai, pincode 400064, Maharashtra, and is registered on MahaRERA as P51800076650, per GharKundli's check of MahaRERA records. Its land is filed as 1406-A/14. GharKundli lists all 301 MahaRERA projects in Malad West (400064).

When was Raheja SkyPolis - 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Raheja SkyPolis - 1 was registered on MahaRERA on 20 June 2024. GharKundli did not find a title report on the land on file there.

Does Raheja SkyPolis - 1 have any legal issues or court cases?

5 court cases are listed for Raheja SkyPolis - 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what each case is about →

Who is the builder / developer of Raheja SkyPolis - 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Radha Krishna Properties Private Limited.

Other projects in Borivali

All 301 projects in Malad West (400064) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.