Possession date of Armee Noori Horizon (MahaRERA P51800077125): 30 April 2030. It has 98 homes (1 BHK and 2 BHK, 421–650 sq ft carpet), 2% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800077125, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800077125, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Armee Noori Horizon?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Armee Noori Horizon has moved

  1. 31 December 2029

    Completion date given when the project was registered

  2. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Armee Noori Horizon’s extension records on MahaRERA (P51800077125), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Armee Noori Horizon

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800077125
Status
Registered and active
Builder
ARMEE ENTERPRISES
Location
Daya Amerse Chawls, Bandra West, Mumbai · 400050
Project type
Residential / Group Housing
Registered on
23 Jul 2024
Completion date at registration
December 2029
Latest completion date
April 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
98
Sold or booked
2%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Armee Noori Horizon, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NOORI HORIZON0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • NOORI HORIZON: covers 0 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Armee Noori Horizon every 1–2 months.

Armee Noori Horizon: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK421 – 50365
2 BHK576 – 65033
Other2,2291
  • Buildings: NOORI HORIZON (16 floors, 99 units)
  • Car parking: 117 covered
  • Land: 1,200 sq m (about 0.3 acres) · sanctioned built-up 5,445 sq m · recreational space 199 sq m
  • Boundaries filed include: Sanotsh Nagar, 9 MTR - Bazar Road
  • Land, as filed: A/246, A/247, A/248, A/249(pt.), A/251(pt.), A/252, A/253, A/264, A/265
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Armee Noori Horizon →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Armee Noori Horizon: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Armee Noori Horizon

What is the possession date of Armee Noori Horizon?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Armee Noori Horizon in Daya Amerse Chawls, Bandra West, Mumbai is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Armee Noori Horizon?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Armee Noori Horizon's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Armee Noori Horizon?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Armee Noori Horizon in Daya Amerse Chawls, Bandra West, Mumbai is P51800077125.

Is Armee Noori Horizon registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Armee Noori Horizon is registered as P51800077125 and its status is "Registered and active".

What is the current construction status of Armee Noori Horizon? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Armee Noori Horizon's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NOORI HORIZON is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Armee Noori Horizon have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Armee Noori Horizon safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Armee Noori Horizon is registered on MahaRERA as P51800077125, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Armee Noori Horizon?

Armee Noori Horizon is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Armee Noori Horizon are 421 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Armee Noori Horizon?

For a flat in Armee Noori Horizon (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Armee Noori Horizon received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Armee Noori Horizon is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Armee Noori Horizon uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Armee Noori Horizon was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Armee Noori Horizon's possession date changes?

The latest dates are on Armee Noori Horizon's MahaRERA page (P51800077125). GharKundli's Kundli Watch sends a free WhatsApp update on Armee Noori Horizon every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Armee Noori Horizon have?

According to GharKundli's check of MahaRERA records (updated October 2026), Armee Noori Horizon has one building filed: NOORI HORIZON with 16 floors and 99 units.

What are the flat sizes (carpet area) in Armee Noori Horizon?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Armee Noori Horizon: 1 BHK: 421 to 503 sq ft carpet (65 homes); 2 BHK: 576 to 650 sq ft carpet (33 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Armee Noori Horizon have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 117 covered car parking spaces for Armee Noori Horizon.

How big is the land of Armee Noori Horizon?

According to GharKundli's check of MahaRERA records (updated October 2026), Armee Noori Horizon stands on 1,200 sq m of land (about 0.3 acres), with 5,445 sq m of sanctioned built-up area and 199 sq m of recreational open space.

What are the reviews of Armee Noori Horizon?

Google Maps has reviews of Armee Noori Horizon written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Armee Noori Horizon?

Armee Noori Horizon by ARMEE ENTERPRISES is in Daya Amerse Chawls, Bandra West, Mumbai, pincode 400050 (near Bandra East, Khar West, Santacruz West), Maharashtra, and is registered on MahaRERA as P51800077125, per GharKundli's check of MahaRERA records. Its boundaries filed there include Sanotsh Nagar, 9 MTR - Bazar Road. Its land is filed as A/246, A/247, A/248, A/249(pt.), A/251(pt.), A/252, A/253, A/264, A/265. GharKundli lists all 168 MahaRERA projects in Bandra West (400050).

How many flats are in Armee Noori Horizon, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Armee Noori Horizon has 98 homes in 1 tower registered on MahaRERA, and 2% of them are sold or booked.

When was Armee Noori Horizon registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Armee Noori Horizon was registered on MahaRERA on 23 July 2024. GharKundli did not find a title report on the land on file there.

Does Armee Noori Horizon have any legal issues or court cases?

No court cases are listed for Armee Noori Horizon on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Armee Noori Horizon?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARMEE ENTERPRISES.

All projects with possession due in 2030 in Mumbai Suburban →

Other projects in Bandra West (400050)

All 168 projects in Bandra West (400050) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.