Xenus Phase 1

by Rodium Properties division of Rodium Realty Ltd. · Matunga, MumbaiAlso near Mahim, Wadala West, Dadar East

Possession: Xenus Phase 1 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51900015095. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Xenus Phase 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Xenus Phase 1 has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51900012530)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. W”
  3. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51900018720)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 57.14% allottees for purpose of extension of RERA registration period of the said project.”
  4. 16 October 2024

    Extended at the builder's request (MahaRERA application EXT51900027283)

    Reason the builder gave MahaRERA:
    “We, M/s. Rodium Properties Division Of Rodium Realty Ltd, hereby declare the following with respect to the project Xenus Phase 1 bearing registration number. P51900015095 registered under MahaRERA. The delay in the completion of the real es…” Read the full reason“We, M/s. Rodium Properties Division Of Rodium Realty Ltd, hereby declare the following with respect to the project Xenus Phase 1 bearing registration number. P51900015095 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 16th October 2024 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the…”

Source: Xenus Phase 1’s extension records on MahaRERA (P51900015095), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Xenus Phase 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the October 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51900015095
Status
Completed
Builder
Rodium Properties division of Rodium Realty Ltd.
Location
Matunga, Mumbai · 400019
Project type
Residential / Group Housing
Registered on
24 Jan 2018
Completion date at registration
December 2022
Latest completion date
October 2024
Delay so far
22 months
Homes
26
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Xenus Phase 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Xenus Phase 1100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Xenus Phase 1 every month.

Xenus Phase 1: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Rodium Properties Division Of Rodium Realty has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 9 months). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Xenus Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Xenus Phase 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Xenus Phase 1

What is the possession date of Xenus Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Xenus Phase 1 in Matunga, Mumbai is 16 October 2024 — 22 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Xenus Phase 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Xenus Phase 1's builder has filed on MahaRERA, the official one, is 16 October 2024, already 22 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Xenus Phase 1 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Xenus Phase 1's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. W"; to 30 June 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 57.14% allottees for purpose of extension of RERA registration period of the said project."; to 16 October 2024, giving the reason "We, M/s. Rodium Properties Division Of Rodium Realty Ltd, hereby declare the following with respect to the project Xenus Phase 1 bearing registration number. P51900015095 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 16th October 2024 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the…".

What is the RERA number of Xenus Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Xenus Phase 1 in Matunga, Mumbai is P51900015095.

Is Xenus Phase 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Xenus Phase 1 is registered as P51900015095 and its status is "Completed".

What is the construction status of Xenus Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Xenus Phase 1's status on MahaRERA is "Completed". As filed by the builder, slab work on Xenus Phase 1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Xenus Phase 1 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Xenus Phase 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Xenus Phase 1 is registered on MahaRERA as P51900015095, its MahaRERA status is "Completed", its completion date has moved 22 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Xenus Phase 1's possession date changes?

The latest dates are on Xenus Phase 1's MahaRERA page (P51900015095). GharKundli's Kundli Watch sends a free WhatsApp update on Xenus Phase 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Xenus Phase 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Xenus Phase 1 has one building filed: Xenus Phase 1 with 23 floors.

How big is the land of Xenus Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Xenus Phase 1 stands on 864 sq m of land (about 0.2 acres), with 2,643 sq m of sanctioned built-up area.

What is the track record of Xenus Phase 1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Rodium Properties Division Of Rodium Realty has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 9 months). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Xenus Phase 1?

Google Maps has reviews of Xenus Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Xenus Phase 1?

Xenus Phase 1 by Rodium Properties division of Rodium Realty Ltd. is in Matunga, Mumbai (pincode 400019), near Mahim, Wadala West, Dadar East, Maharashtra, and is registered on MahaRERA as P51900015095, per GharKundli's check of MahaRERA records.

How many homes are in Xenus Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Xenus Phase 1 has 26 homes in 1 tower registered on MahaRERA.

When was Xenus Phase 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Xenus Phase 1 was registered on MahaRERA on 24 January 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Xenus Phase 1?

No court cases are listed for Xenus Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Xenus Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Rodium Properties division of Rodium Realty Ltd., which has 1 other project registered on MahaRERA.

Other projects in pincode 400019

All 104 projects in Matunga (400019) →

Other projects by Rodium Properties division of Rodium Realty Ltd.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.