Crescent Western Trade Center - Goregaon
by BP INFRA REALTORS LLP · Malad East, Mumbai 400097Also near Goregaon East, Kurar, Dindoshi
What’s in the report? →Possession date of Crescent Western Trade Center - Goregaon (MahaRERA P51800077923): 30 April 2028. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800077923, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800077923, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Crescent Western Trade Center - Goregaon?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Crescent Western Trade Center - Goregaon has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Crescent Western Trade Center - Goregaon’s extension records on MahaRERA (P51800077923), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Crescent Western Trade Center - Goregaon
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800077923
- Status
- Registered and active
- Builder
- BP INFRA REALTORS LLP
- Location
- Malad East, Mumbai · 400097
- Project type
- Commercial
- Registered on
- 13 Nov 2024
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 19%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Crescent Western Trade Center - Goregaon, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CRESCENT WESTERN TRADE CENTER - GOREGAON COMMERCIAL BUILDING | 100% | 57% | 10% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- CRESCENT WESTERN TRADE CENTER - GOREGAON COMMERCIAL BUILDING: covers Basement + Ground floor (pt.) for Shops + 1st (pt.) upper floor for Shops and (pt.) podium + 2nd to 6th Podium + 7th to 16th [pt] upper floors Office No. 1 & 5
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Crescent Western Trade Center - Goregaon every 1–2 months.
Crescent Western Trade Center - Goregaon: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 461 – 601 | 94 |
| Shops | 397 – 517 | 8 |
- Buildings: CRESCENT WESTERN TRADE CENTER - GOREGAON COMMERCIAL BUILDING (23 floors, 102 units)
- Car parking: 144 covered
- Land: 2,229 sq m (about 0.6 acres) · sanctioned built-up 5,583 sq m · recreational space 152 sq m
- Boundaries filed include: BMC GARDEN
- Land, as filed: 104D
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Crescent Western Trade Center - Goregaon →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Crescent Western Trade Center - Goregaon: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Crescent Western Trade Center - Goregaon
What is the possession date of Crescent Western Trade Center - Goregaon?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Crescent Western Trade Center - Goregaon in Malad East, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Crescent Western Trade Center - Goregaon?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Crescent Western Trade Center - Goregaon's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Crescent Western Trade Center - Goregaon?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Crescent Western Trade Center - Goregaon in Malad East, Mumbai is P51800077923.
Is Crescent Western Trade Center - Goregaon registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Western Trade Center - Goregaon is registered as P51800077923 and its status is "Registered and active".
What is the current construction status of Crescent Western Trade Center - Goregaon? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Western Trade Center - Goregaon's status on MahaRERA is "Registered and active". As filed by the builder, slab work on CRESCENT WESTERN TRADE CENTER - GOREGAON COMMERCIAL BUILDING is 57% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.
Does Crescent Western Trade Center - Goregaon have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Crescent Western Trade Center - Goregaon safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Western Trade Center - Goregaon is registered on MahaRERA as P51800077923, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Crescent Western Trade Center - Goregaon?
Crescent Western Trade Center - Goregaon is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Crescent Western Trade Center - Goregaon?
For a flat in Crescent Western Trade Center - Goregaon (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Crescent Western Trade Center - Goregaon received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Western Trade Center - Goregaon is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Crescent Western Trade Center - Goregaon a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Western Trade Center - Goregaon's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.
Has Crescent Western Trade Center - Goregaon uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Crescent Western Trade Center - Goregaon was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Crescent Western Trade Center - Goregaon's possession date changes?
The latest dates are on Crescent Western Trade Center - Goregaon's MahaRERA page (P51800077923). GharKundli's Kundli Watch sends a free WhatsApp update on Crescent Western Trade Center - Goregaon every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Crescent Western Trade Center - Goregaon have?
According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Western Trade Center - Goregaon has one building filed: CRESCENT WESTERN TRADE CENTER - GOREGAON COMMERCIAL BUILDING with 23 floors and 102 units.
How much parking does Crescent Western Trade Center - Goregaon have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 144 covered car parking spaces for Crescent Western Trade Center - Goregaon.
How big is the land of Crescent Western Trade Center - Goregaon?
According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Western Trade Center - Goregaon stands on 2,229 sq m of land (about 0.6 acres), with 5,583 sq m of sanctioned built-up area and 152 sq m of recreational open space.
What are the reviews of Crescent Western Trade Center - Goregaon?
Google Maps has reviews of Crescent Western Trade Center - Goregaon written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Crescent Western Trade Center - Goregaon?
Crescent Western Trade Center - Goregaon by BP INFRA REALTORS LLP is in Malad East, Mumbai, pincode 400097 (near Goregaon East, Kurar, Dindoshi), Maharashtra, and is registered on MahaRERA as P51800077923, per GharKundli's check of MahaRERA records. Its boundaries filed there include BMC GARDEN. Its land is filed as 104D. GharKundli lists all 195 MahaRERA projects in Malad East (400097).
How many flats are in Crescent Western Trade Center - Goregaon, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Western Trade Center - Goregaon has 0 homes in 1 tower registered on MahaRERA, and 19% of them are sold or booked.
When was Crescent Western Trade Center - Goregaon registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Crescent Western Trade Center - Goregaon was registered on MahaRERA on 13 November 2024. GharKundli did not find a title report on the land on file there.
Does Crescent Western Trade Center - Goregaon have any legal issues or court cases?
No court cases are listed for Crescent Western Trade Center - Goregaon on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Crescent Western Trade Center - Goregaon?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BP INFRA REALTORS LLP.
Check it yourself on MahaRERA
- How to check the possession date of Crescent Western Trade Center - Goregaon
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Malad East (400097)
- L&T Realty Ahana Tower A
- Aarambh Phase III by group Satellite
- L&T Realty Ahana Tower B
- Pearl Solitaire
- Namo Whispering Bliss
- Upper East 97
- Nivetia Heights
- Vardhan Royale
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.