Ojas Milestone
by Ojas Corporation · Kurla West, Mumbai 400070Also near Bhandup west, RajawadiRegistered on MahaRERA as “Milestone”
What’s in the report? →Possession date of Ojas Milestone (MahaRERA P51800078128): 30 August 2028. It has 40 homes (1 BHK, 2 BHK and 3 BHK, 474–1691 sq ft carpet), 62% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800078128, and currently active. Its completion date is now August 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800078128, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Ojas Milestone?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Ojas Milestone has moved
30 April 2028
Completion date given when the project was registered
30 August 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Ojas Milestone’s extension records on MahaRERA (P51800078128), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ojas Milestone
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800078128
- Status
- Registered and active
- Builder
- Ojas Corporation
- Location
- Kurla West, Mumbai · 400070
- Project type
- Others
- Registered on
- 25 Nov 2024
- Completion date at registration
- April 2028
- Latest completion date
- August 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 40
- Sold or booked
- 62%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Ojas Milestone, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Milestone | 100% | 100% | 60% | 10% |
Commencement certificate (CC), as filed on MahaRERA
- Milestone: covers 18 (Ground + 17 Upper Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ojas Milestone every 1–2 months.
Ojas Milestone: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 474 – 477 | 17 |
| 2 BHK | 713 – 734 | 15 |
| 3 BHK | 957 – 997 | 7 |
| Shops | 189 – 455 | 7 |
| 4 BHK | 1,691 | 1 |
- Buildings: Milestone (11 floors, 47 units)
- Land: 751 sq m (about 0.2 acres) · sanctioned built-up 2,533 sq m
- Land, as filed: 135
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Ojas Corporation (a group of 2 linked companies) has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Ojas Milestone →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ojas Milestone: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Ojas Milestone
What is the possession date of Ojas Milestone?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ojas Milestone in Kurla West, Mumbai is 30 August 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Ojas Milestone?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ojas Milestone's builder has filed on MahaRERA, the official one, is 30 August 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Ojas Milestone?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ojas Milestone in Kurla West, Mumbai is P51800078128.
Is Ojas Milestone registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ojas Milestone is registered as P51800078128 and its status is "Registered and active".
What is the current construction status of Ojas Milestone? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Ojas Milestone's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Milestone is 100% done and internal work 60%. GharKundli's full report compares construction progress with the deadline.
Does Ojas Milestone have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Ojas Milestone safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Ojas Milestone is registered on MahaRERA as P51800078128, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Ojas Milestone?
Ojas Milestone is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Ojas Milestone are 474 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Ojas Milestone?
For a flat in Ojas Milestone (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Ojas Milestone received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ojas Milestone is still under construction, with 30 August 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Ojas Milestone a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Ojas Milestone is a redevelopment: 21 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Ojas Milestone uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ojas Milestone was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Ojas Milestone's possession date changes?
The latest dates are on Ojas Milestone's MahaRERA page (P51800078128). GharKundli's Kundli Watch sends a free WhatsApp update on Ojas Milestone every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ojas Milestone have?
According to GharKundli's check of MahaRERA records (updated October 2026), Ojas Milestone has one building filed: Milestone with 11 floors and 47 units.
What are the flat sizes (carpet area) in Ojas Milestone?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ojas Milestone: 1 BHK: 474 to 477 sq ft carpet (17 homes); 2 BHK: 713 to 734 sq ft carpet (15 homes); 3 BHK: 957 to 997 sq ft carpet (7 homes); 4 BHK: 1691 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Ojas Milestone?
According to GharKundli's check of MahaRERA records (updated October 2026), Ojas Milestone stands on 751 sq m of land (about 0.2 acres), with 2,533 sq m of sanctioned built-up area.
What is the track record of Ojas Milestone's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ojas Corporation (a group of 2 linked companies) has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Ojas Milestone?
Google Maps has reviews of Ojas Milestone written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Ojas Milestone?
Ojas Milestone by Ojas Corporation is in Kurla West, Mumbai, pincode 400070 (near Bhandup west, Rajawadi), Maharashtra, and is registered on MahaRERA as P51800078128, per GharKundli's check of MahaRERA records. Its land is filed as 135. GharKundli lists all 92 MahaRERA projects in Kurla West (400070).
How many flats are in Ojas Milestone, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Ojas Milestone has 40 homes in 1 tower registered on MahaRERA, and 62% of them are sold or booked.
When was Ojas Milestone registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ojas Milestone was registered on MahaRERA on 25 November 2024. GharKundli did not find a title report on the land on file there.
Does Ojas Milestone have any legal issues or court cases?
No court cases are listed for Ojas Milestone on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Ojas Milestone?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ojas Corporation, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Ojas Milestone
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in Kurla West (400070)
- Sai Chamunda
- Twin Galaxy
- Deraiya Luxurio
- Jai Shreeram Prasanna CHSL
- Dadamiya’s Man'souza Height
- Kalyan Kutir Co-operative Housing Society Limited
- Taiba Residency
- Anupam Villa CHSL
Other projects by Ojas Corporation
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.