Southfield Gravity E Wing
by SOUTHFIELD BUILDCON LLP · Bhandup East, Mumbai 400042Also near Bhandup West, Nahur East, Mulund WestRegistered on MahaRERA as “GRAVITY E WING”
What’s in the report? →Possession date of Southfield Gravity E Wing (MahaRERA P51800078273): 30 April 2029. It has 4 homes (1 BHK, 325–518 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800078273, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800078273, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Southfield Gravity E Wing?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Southfield Gravity E Wing has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Southfield Gravity E Wing’s extension records on MahaRERA (P51800078273), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Southfield Gravity E Wing
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800078273
- Status
- Registered and active
- Builder
- SOUTHFIELD BUILDCON LLP
- Location
- Bhandup East, Mumbai · 400042
- Project type
- Residential / Group Housing
- Registered on
- 4 Dec 2024
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 4
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Southfield Gravity E Wing, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| E-WING | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- E-WING: covers 3 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Southfield Gravity E Wing every 1–2 months.
Southfield Gravity E Wing: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 325 – 518 | 4 |
- Buildings: E-WING (3 floors, 4 units)
- Land: 5,195 sq m (about 1.3 acres) · sanctioned built-up 171 sq m
- Boundaries filed include: 9 MTR TERMINAL ACCESS ROAD
- Land, as filed: 732,737
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Southfield Infra LLP AND HR Infra (a group of 5 linked companies) has 7 projects on MahaRERA since 2018, this one included. Of the 7 GharKundli has checked: 7 still being built, 4 past the promised date (typically 20 months late). 2 complaints on MahaRERA across 2 projects.
Read Google reviews of Southfield Gravity E Wing →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Southfield Gravity E Wing: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Southfield Gravity E Wing
What is the possession date of Southfield Gravity E Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Southfield Gravity E Wing in Bhandup East, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Southfield Gravity E Wing?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Southfield Gravity E Wing's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Southfield Gravity E Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Southfield Gravity E Wing in Bhandup East, Mumbai is P51800078273.
Is Southfield Gravity E Wing registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Southfield Gravity E Wing is registered as P51800078273 and its status is "Registered and active".
What is the current construction status of Southfield Gravity E Wing? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Southfield Gravity E Wing's status on MahaRERA is "Registered and active". As filed by the builder, slab work on E-WING is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Southfield Gravity E Wing have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Southfield Gravity E Wing safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Southfield Gravity E Wing is registered on MahaRERA as P51800078273, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Southfield Gravity E Wing?
Southfield Gravity E Wing is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Southfield Gravity E Wing are 325 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Southfield Gravity E Wing?
For a flat in Southfield Gravity E Wing (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Southfield Gravity E Wing received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Southfield Gravity E Wing is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Southfield Gravity E Wing a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Southfield Gravity E Wing's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.
Has Southfield Gravity E Wing uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Southfield Gravity E Wing was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Southfield Gravity E Wing's possession date changes?
The latest dates are on Southfield Gravity E Wing's MahaRERA page (P51800078273). GharKundli's Kundli Watch sends a free WhatsApp update on Southfield Gravity E Wing every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Southfield Gravity E Wing have?
According to GharKundli's check of MahaRERA records (updated October 2026), Southfield Gravity E Wing has one building filed: E-WING with 3 floors and 4 units.
What are the flat sizes (carpet area) in Southfield Gravity E Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Southfield Gravity E Wing: 1 BHK: 325 to 518 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Southfield Gravity E Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), Southfield Gravity E Wing stands on 5,195 sq m of land (about 1.3 acres), with 171 sq m of sanctioned built-up area.
What is the track record of Southfield Gravity E Wing's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Southfield Infra LLP AND HR Infra (a group of 5 linked companies) has 7 projects on MahaRERA since 2018, this one included. Of the 7 GharKundli has checked: 7 still being built, 4 past the promised date (typically 20 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Southfield Gravity E Wing?
Google Maps has reviews of Southfield Gravity E Wing written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Southfield Gravity E Wing?
Southfield Gravity E Wing by SOUTHFIELD BUILDCON LLP is in Bhandup East, Mumbai, pincode 400042 (near Bhandup West, Nahur East, Mulund West), Maharashtra, and is registered on MahaRERA as P51800078273, per GharKundli's check of MahaRERA records. Its boundaries filed there include 9 MTR TERMINAL ACCESS ROAD. Its land is filed as 732,737. GharKundli lists all 74 MahaRERA projects in Kanjurmarg East (400042).
How many flats are in Southfield Gravity E Wing, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Southfield Gravity E Wing has 4 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Southfield Gravity E Wing registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Southfield Gravity E Wing was registered on MahaRERA on 4 December 2024. GharKundli did not find a title report on the land on file there.
Does Southfield Gravity E Wing have any legal issues or court cases?
No court cases are listed for Southfield Gravity E Wing on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Southfield Gravity E Wing?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SOUTHFIELD BUILDCON LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Southfield Gravity E Wing
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in Kanjurmarg East (400042)
- Rajshree Ashish Co-operative Housing Society Limited
- Runwal Avenue Wing - M
- Bhandup Siddhivinayak CHS Ltd
- Shivmangal Residency
- Satre Happynest
- Runwal Bliss - Wing F
- Southfield Gravity
- Sudhanshu Heights
Other projects by SOUTHFIELD BUILDCON LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.