Skyline Sky Heights
by Skyline Developers · Andheri East, Mumbai 400069Also near Jogeshwari East, Andheri West, MograRegistered on MahaRERA as “Sky Heights”
What’s in the report? →Possession date of Skyline Sky Heights (MahaRERA P51800078955): 30 April 2029. It has 68 homes (1 BHK, 350–374 sq ft carpet), 49% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800078955, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for P51800078955, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Skyline Sky Heights?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Skyline Sky Heights has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Skyline Sky Heights’s extension records on MahaRERA (P51800078955), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Skyline Sky Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800078955
- Status
- Registered and active
- Builder
- Skyline Developers
- Location
- Andheri East, Mumbai · 400069
- Project type
- Residential / Group Housing
- Registered on
- 24 Jan 2025
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 68
- Sold or booked
- 49%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 14
Construction progress of Skyline Sky Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sale Wing B | 100% | 15% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Sale Wing B: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Skyline Sky Heights every 1–2 months.
Skyline Sky Heights: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 350 – 374 | 68 |
| Other | 215 – 701 | 2 |
- Buildings: Sale Wing B (17 floors, 70 units)
- Car parking: 33 covered
- Land: 1,003 sq m (about 0.2 acres) · sanctioned built-up 2,544 sq m
- Land, as filed: CTS No 84, 84/1 to 12 (Pt) of Village Mogra
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Skyline Sky Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Skyline Sky Heights: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Skyline Sky Heights
What is the possession date of Skyline Sky Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Skyline Sky Heights in Andheri East, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Skyline Sky Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Skyline Sky Heights's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Skyline Sky Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Skyline Sky Heights in Andheri East, Mumbai is P51800078955.
Is Skyline Sky Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Sky Heights is registered as P51800078955 and its status is "Registered and active".
What is the current construction status of Skyline Sky Heights? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Sky Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Sale Wing B is 15% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Skyline Sky Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Skyline Sky Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Sky Heights is registered on MahaRERA as P51800078955, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Skyline Sky Heights?
Skyline Sky Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Skyline Sky Heights are 350 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Skyline Sky Heights?
For a flat in Skyline Sky Heights (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Skyline Sky Heights received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Sky Heights is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Skyline Sky Heights uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Skyline Sky Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Skyline Sky Heights's possession date changes?
The latest dates are on Skyline Sky Heights's MahaRERA page (P51800078955). GharKundli's Kundli Watch sends a free WhatsApp update on Skyline Sky Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Skyline Sky Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Sky Heights has one building filed: Sale Wing B with 17 floors and 70 units.
What are the flat sizes (carpet area) in Skyline Sky Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Skyline Sky Heights: 1 BHK: 350 to 374 sq ft carpet (68 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Skyline Sky Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 33 covered car parking spaces for Skyline Sky Heights.
How big is the land of Skyline Sky Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Sky Heights stands on 1,003 sq m of land (about 0.2 acres), with 2,544 sq m of sanctioned built-up area.
What are the reviews of Skyline Sky Heights?
Google Maps has reviews of Skyline Sky Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Skyline Sky Heights?
Skyline Sky Heights by Skyline Developers is in Andheri East, Mumbai, pincode 400069 (near Jogeshwari East, Andheri West, Mogra), Maharashtra, and is registered on MahaRERA as P51800078955, per GharKundli's check of MahaRERA records. Its land is filed as CTS No 84, 84/1 to 12 (Pt) of Village Mogra. GharKundli lists all 96 MahaRERA projects in Andheri East (400069).
How many flats are in Skyline Sky Heights, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Sky Heights has 68 homes in 1 tower registered on MahaRERA, and 49% of them are sold or booked.
When was Skyline Sky Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Skyline Sky Heights was registered on MahaRERA on 24 January 2025. GharKundli did not find a title report on the land on file there.
Does Skyline Sky Heights have any legal issues or court cases?
No court cases are listed for Skyline Sky Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Skyline Sky Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Skyline Developers, which has 14 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Skyline Sky Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in Andheri East (400069)
- Sankirt Jasmine
- Sajay Business Hub
- Nityanand Nagar Vibhag IV Cooperative Housing Society Limited
- Commercial Project Andheri
- Aarham
- Shri Shankarpuri
- Mass Marquise
- Parleshwar Aangan
Other projects by Skyline Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.