KALIKUND HEIGHTS
by KALIKUND DEVELOPERS · Grant Road West, MumbaiAlso near Cumballa Hill, Girgaon, Mumbai Central
Possession date of KALIKUND HEIGHTS: 30 April 2027, moved from 28 February 2021 (70 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900017733, and currently active. Its completion date has moved from February 2021 to April 2027: 70 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about KALIKUND HEIGHTS?
How the possession date of KALIKUND HEIGHTS has moved
28 February 2021
Completion date given when the project was registered
28 February 2022
Extended at the builder's request (MahaRERA application EXT51900008873)
Reason the builder gave MahaRERA: “Two Non-co-operative Tenants had not vacated there premises. Had to apply to MHADA TO VACATE the tenants under Mhada Act 95(A).”
28 August 2023
Extended at the builder's request (MahaRERA application EXT51900012141)
Reason the builder gave MahaRERA: “Two Non-co-operative Tenants had not vacated there premises. Had to apply to MHADA TO VACATE the tenants under Mhada Act 95(A).”
31 December 2026
Extended at the builder's request (MahaRERA application EXT51900024373)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 53.85% allottees for purpose of extension of RERA registration period of the said project.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: KALIKUND HEIGHTS’s extension records on MahaRERA (P51900017733), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KALIKUND HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 5 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900017733
- Status
- Registered and active
- Builder
- KALIKUND DEVELOPERS
- Location
- Grant Road West, Mumbai · 400007
- Project type
- Others
- Registered on
- 11 Sep 2018
- Completion date at registration
- February 2021
- Latest completion date
- April 2027
- Delay so far
- 70 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 30
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 5
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of KALIKUND HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KALIKUND HEIGHTS WING A | 100% | 100% | 90% | 65% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KALIKUND HEIGHTS every month.
KALIKUND HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: KALIKUND HEIGHTS WING A (39 floors)
- Land: 1,853 sq m (about 0.5 acres) · sanctioned built-up 6,247 sq m
- Boundaries filed include: 30FT WIDE INTERNAL PRIVATE ROAD
The builder’s record and reviews
Kalikund Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 25 months); 1 still being built, 1 past the promised date (typically 58 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of KALIKUND HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KALIKUND HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KALIKUND HEIGHTS
What is the possession date of KALIKUND HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KALIKUND HEIGHTS in Grant Road West, Mumbai is 30 April 2027 — 70 months later than 28 February 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for KALIKUND HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KALIKUND HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2027, already 70 months later than the 28 February 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KALIKUND HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), KALIKUND HEIGHTS's builder applied to MahaRERA to extend the completion date 3 times: to 28 February 2022, giving the reason "Two Non-co-operative Tenants had not vacated there premises. Had to apply to MHADA TO VACATE the tenants under Mhada Act 95(A)."; to 28 August 2023, giving the reason "Two Non-co-operative Tenants had not vacated there premises. Had to apply to MHADA TO VACATE the tenants under Mhada Act 95(A)."; to 31 December 2026, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 53.85% allottees for purpose of extension of RERA registration period of the said project.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of KALIKUND HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KALIKUND HEIGHTS in Grant Road West, Mumbai is P51900017733.
Is KALIKUND HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KALIKUND HEIGHTS is registered as P51900017733 and its status is "Registered and active".
What is the construction status of KALIKUND HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), KALIKUND HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KALIKUND HEIGHTS WING A is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does KALIKUND HEIGHTS have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is KALIKUND HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), KALIKUND HEIGHTS is registered on MahaRERA as P51900017733, its completion date has moved 70 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KALIKUND HEIGHTS's possession date changes?
The latest dates are on KALIKUND HEIGHTS's MahaRERA page (P51900017733). GharKundli's Kundli Watch sends a free WhatsApp update on KALIKUND HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KALIKUND HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), KALIKUND HEIGHTS has one building filed: KALIKUND HEIGHTS WING A with 39 floors.
How big is the land of KALIKUND HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), KALIKUND HEIGHTS stands on 1,853 sq m of land (about 0.5 acres), with 6,247 sq m of sanctioned built-up area.
What is the track record of KALIKUND HEIGHTS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Kalikund Developers (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 25 months); 1 still being built, 1 past the promised date (typically 58 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of KALIKUND HEIGHTS?
Google Maps has reviews of KALIKUND HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KALIKUND HEIGHTS?
KALIKUND HEIGHTS by KALIKUND DEVELOPERS is in Grant Road West, Mumbai (pincode 400007), near Cumballa Hill, Girgaon, Mumbai Central, Maharashtra, and is registered on MahaRERA as P51900017733, per GharKundli's check of MahaRERA records. Its boundaries filed there include 30FT WIDE INTERNAL PRIVATE ROAD.
How many homes are in KALIKUND HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), KALIKUND HEIGHTS has 30 homes in 1 tower registered on MahaRERA.
When was KALIKUND HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KALIKUND HEIGHTS was registered on MahaRERA on 11 September 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on KALIKUND HEIGHTS?
5 court cases are listed for KALIKUND HEIGHTS on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of KALIKUND HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KALIKUND DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of KALIKUND HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in pincode 400007
- SHREE SAMMET SHIKHAR HEIGHTS
- FORTUNE AURA
- Marq
- SUGAN HEIGHTS
- Shapoorji Pallonji The Odyssey 1