by Agastya Infra · Vikhroli East, Mumbai

Registered on MahaRERA under P51800079411, and currently active. Its completion date has moved from August 2027 to December 2027, 4 months later.

Source: GharKundli’s check of MahaRERA records, October 2026.

GharKundli’s full report on High Pavilion

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800079411
Status
Registered and active
Builder
Agastya Infra
Location
Vikhroli East, Mumbai · 400083
Project type
Residential / Group Housing
Registered on
4 Mar 2025
Completion date at registration
August 2027
Latest completion date
December 2027
Delay so far
4 months
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Kundli Watch

High Pavilion: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about High Pavilion

Is High Pavilion registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), High Pavilion is registered as P51800079411 and its status is "Registered and active".

Where is High Pavilion?

High Pavilion by Agastya Infra is in Vikhroli East, Mumbai (pincode 400083), Maharashtra, and is registered on MahaRERA as P51800079411, per GharKundli's check of MahaRERA records.

When is possession of High Pavilion due?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for High Pavilion in Vikhroli East, Mumbai is 30 December 2027 — 4 months later than 30 August 2027, the date given at registration.

Does High Pavilion have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Who is the builder of High Pavilion?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Agastya Infra, which has 3 other projects registered on MahaRERA.

Other projects in pincode 400083

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.