by Nisar Properties Pvt. Ltd. · Kurla West, Mumbai 400070Also near Bhandup West, Parel, BycullaRegistered on MahaRERA as “Rajal Happy Home”

What’s in the report? →

Possession date of Nisar Rajal Happy Home (MahaRERA P51800079439): 30 April 2028. It has 40 homes (1 BHK, 2 BHK and 3 BHK, 234–762 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800079439, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800079439, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Nisar Rajal Happy Home?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Nisar Rajal Happy Home has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Nisar Rajal Happy Home’s extension records on MahaRERA (P51800079439), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Nisar Rajal Happy Home

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800079439
Status
Registered and active
Builder
Nisar Properties Pvt. Ltd.
Location
Kurla West, Mumbai · 400070
Project type
Residential / Group Housing
Registered on
6 Mar 2025
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
40
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Nisar Rajal Happy Home, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Rajal Happy Home0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Rajal Happy Home: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nisar Rajal Happy Home every 1–2 months.

Nisar Rajal Happy Home: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK638 – 76221
2 BHK633 – 76211
1 BHK234 – 4238
Shops161 – 3346

The builder’s record and reviews

Nisar Properties has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. 16 complaints on MahaRERA across 3 projects.

Read Google reviews of Nisar Rajal Happy Home →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Nisar Rajal Happy Home: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Nisar Rajal Happy Home

What is the possession date of Nisar Rajal Happy Home?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nisar Rajal Happy Home in Kurla West, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Nisar Rajal Happy Home?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Nisar Rajal Happy Home's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Nisar Rajal Happy Home?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Nisar Rajal Happy Home in Kurla West, Mumbai is P51800079439.

Is Nisar Rajal Happy Home registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Nisar Rajal Happy Home is registered as P51800079439 and its status is "Registered and active".

What is the current construction status of Nisar Rajal Happy Home? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Nisar Rajal Happy Home's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Rajal Happy Home is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Nisar Rajal Happy Home have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Nisar Rajal Happy Home safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Nisar Rajal Happy Home is registered on MahaRERA as P51800079439, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Nisar Rajal Happy Home?

Nisar Rajal Happy Home is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Nisar Rajal Happy Home are 234 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Nisar Rajal Happy Home?

For a flat in Nisar Rajal Happy Home (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Nisar Rajal Happy Home received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Nisar Rajal Happy Home is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Nisar Rajal Happy Home a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Nisar Rajal Happy Home is a redevelopment: 20 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Nisar Rajal Happy Home uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Nisar Rajal Happy Home was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Nisar Rajal Happy Home's possession date changes?

The latest dates are on Nisar Rajal Happy Home's MahaRERA page (P51800079439). GharKundli's Kundli Watch sends a free WhatsApp update on Nisar Rajal Happy Home every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Nisar Rajal Happy Home have?

According to GharKundli's check of MahaRERA records (updated October 2026), Nisar Rajal Happy Home has one building filed: Rajal Happy Home with 6 floors and 46 units.

What are the flat sizes (carpet area) in Nisar Rajal Happy Home?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Nisar Rajal Happy Home: 3 BHK: 638 to 762 sq ft carpet (21 homes); 2 BHK: 633 to 762 sq ft carpet (11 homes); 1 BHK: 234 to 423 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Nisar Rajal Happy Home have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 4 open car parking spaces for Nisar Rajal Happy Home.

How big is the land of Nisar Rajal Happy Home?

According to GharKundli's check of MahaRERA records (updated October 2026), Nisar Rajal Happy Home stands on 1,181 sq m of land (about 0.3 acres), with 2,706 sq m of sanctioned built-up area.

What is the track record of Nisar Rajal Happy Home's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Nisar Properties has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 3 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. 16 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Nisar Rajal Happy Home?

Google Maps has reviews of Nisar Rajal Happy Home written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Nisar Rajal Happy Home?

Nisar Rajal Happy Home by Nisar Properties Pvt. Ltd. is in Kurla West, Mumbai, pincode 400070 (near Bhandup West, Parel, Byculla), Maharashtra, and is registered on MahaRERA as P51800079439, per GharKundli's check of MahaRERA records. Its boundaries filed there include New Hall Road, Garden Green Belt. Its land is filed as 830B. GharKundli lists all 92 MahaRERA projects in Kurla West (400070).

How many flats are in Nisar Rajal Happy Home, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Nisar Rajal Happy Home has 40 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Nisar Rajal Happy Home registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Nisar Rajal Happy Home was registered on MahaRERA on 6 March 2025. GharKundli did not find a title report on the land on file there.

Does Nisar Rajal Happy Home have any legal issues or court cases?

No court cases are listed for Nisar Rajal Happy Home on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Nisar Rajal Happy Home?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Nisar Properties Pvt. Ltd., which has 6 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Kurla West (400070)

All 92 projects in Kurla West (400070) →

Other projects by Nisar Properties Pvt. Ltd.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.