Skip to content
GharKundli

SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED

by SAMARPAN HOMES & DEVELOPERS · Borivali East, MumbaiAlso near Borivali West

Possession date of SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED: 31 December 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800079662, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 1 court case, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800079662
Status
Registered and active
Builder
SAMARPAN HOMES & DEVELOPERS
Location
Borivali East, Mumbai · 400066
Project type
Others
Registered on
20 Mar 2025
Completion date at registration
December 2027
Homes
44
Sold or booked
39%
Towers
1
Complaints on MahaRERA
1
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
13

Construction progress of SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SWANAND CO-OPERATIVE HOUSING SOCIETY LTD100%70%40%0%

Commencement certificate (CC), as filed on MahaRERA

  • SWANAND CO-OPERATIVE HOUSING SOCIETY LTD: covers C. C. is now granted for the work upto plinth level

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED every month.

SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Shops148 – 1,53916
1 BHK296 – 47516
2 BHK475 – 69714
3 BHK672 – 88514
  • Buildings: SWANAND CO-OPERATIVE HOUSING SOCIETY LTD (20 floors, 60 units)
  • Land: 1,085 sq m (about 0.3 acres) · sanctioned built-up 2,732 sq m
  • Boundaries filed include: Dattapada Road

The builder’s record and reviews

Samarpan Homes & Developers (a group of 2 linked companies) has 17 projects on MahaRERA since 2020, this one included. Of the 17 GharKundli has checked: 6 finished, 5 within the promised date and 1 needed more time (typically 1 months); 11 still being built, 1 past the promised date (typically 3 months late). 4 complaints on MahaRERA across 4 projects.

Read Google reviews of SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED

What is the possession date of SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED in Borivali East, Mumbai is 31 December 2027.

Is the builder's possession date different from the MahaRERA date for SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED's builder has filed on MahaRERA, the official one, is 31 December 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED in Borivali East, Mumbai is P51800079662.

Is SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED is registered as P51800079662 and its status is "Registered and active".

What is the construction status of SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED?

According to GharKundli's check of MahaRERA records (updated October 2026), SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SWANAND CO-OPERATIVE HOUSING SOCIETY LTD is 70% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.

Does SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED is registered on MahaRERA as P51800079662, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED's possession date changes?

The latest dates are on SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED's MahaRERA page (P51800079662). GharKundli's Kundli Watch sends a free WhatsApp update on SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED have?

According to GharKundli's check of MahaRERA records (updated October 2026), SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED has one building filed: SWANAND CO-OPERATIVE HOUSING SOCIETY LTD with 20 floors and 60 units.

What are the flat sizes (carpet area) in SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED: 1 BHK: 296 to 475 sq ft carpet (16 homes); 2 BHK: 475 to 697 sq ft carpet (14 homes); 3 BHK: 672 to 885 sq ft carpet (14 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED?

According to GharKundli's check of MahaRERA records (updated October 2026), SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED stands on 1,085 sq m of land (about 0.3 acres), with 2,732 sq m of sanctioned built-up area.

What is the track record of SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Samarpan Homes & Developers (a group of 2 linked companies) has 17 projects on MahaRERA since 2020, this one included. Of the 17 GharKundli has checked: 6 finished, 5 within the promised date and 1 needed more time (typically 1 months); 11 still being built, 1 past the promised date (typically 3 months late). 4 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED?

Google Maps has reviews of SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED?

SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED by SAMARPAN HOMES & DEVELOPERS is in Borivali East, Mumbai (pincode 400066), near Borivali West, Maharashtra, and is registered on MahaRERA as P51800079662, per GharKundli's check of MahaRERA records. Its boundaries filed there include Dattapada Road.

How many homes are in SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED?

According to GharKundli's check of MahaRERA records (updated October 2026), SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED has 44 homes in 1 tower registered on MahaRERA, and 39% of them are sold or booked.

When was SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED was registered on MahaRERA on 20 March 2025. GharKundli did not find a title report on the land on file there.

Are there court cases on SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED?

1 court case is listed for SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of SWANAND CO-OPERATIVE HOUSING SOCIETY LIMITED?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAMARPAN HOMES & DEVELOPERS, which has 13 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400066

All 228 projects in Borivali East (400066) →

Other projects by SAMARPAN HOMES & DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.