SIDDHI YOG
by SIDDHITECH DEVELOPERS PRIVATE LIMITED · Mahim, MumbaiAlso near Dadar West, Shivaji Park, Matunga
Possession date of SIDDHI YOG: 31 December 2025, moved from 30 December 2023 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51900017229. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about SIDDHI YOG?
How the possession date of SIDDHI YOG has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51900018130)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”30 June 2025
Extended at the builder's request (MahaRERA application EXT51900025658)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The major reason for the delay is the stop-work order issued by MHADA dated 11th October 2023, which halted the project temporarily. We are plea…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The major reason for the delay is the stop-work order issued by MHADA dated 11th October 2023, which halted the project temporarily. We are pleased to inform you that this order has now been withdrawn, as evidenced by the withdrawal order issued on 2nd December 2024, which is attached herewith for your reference. In addition to the above, the project experienced challenges related to procurement, unforeseen site conditions, coordination issues, and temporary financial constraints. Despite these s…”31 December 2025
Extended at the builder's request (MahaRERA application EA30062501849)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2025”
Source: SIDDHI YOG’s extension records on MahaRERA (P51900017229), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SIDDHI YOG
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900017229
- Status
- Lapsed (registration period ended)
- Builder
- SIDDHITECH DEVELOPERS PRIVATE LIMITED
- Location
- Mahim, Mumbai · 400016
- Project type
- Others
- Registered on
- 24 Jul 2018
- Completion date at registration
- December 2023
- Latest completion date
- December 2025
- Delay so far
- 24 months
- Homes
- 16
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Appeals at the tribunal
- 3
- Title report on file
- Not found
Construction progress of SIDDHI YOG, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SIDDHI YOG | 100% | 80% | 80% | 85% |
Commencement certificate (CC), as filed on MahaRERA
- SIDDHI YOG: covers 17 floors
Latest CC order on MahaRERA: dated 10/10/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SIDDHI YOG every month.
SIDDHI YOG: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 441 | 8 |
| 3 BHK | 1,431 – 1,442 | 8 |
- Buildings: SIDDHI YOG (23 floors, 16 units)
- Land: 625 sq m (about 0.2 acres)
- Boundaries filed include: SHITALADEVI TEMPLE ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SIDDHI YOG →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SIDDHI YOG: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SIDDHI YOG
What is the possession date of SIDDHI YOG?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SIDDHI YOG in Mahim, Mumbai is 31 December 2025 — 24 months later than 30 December 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for SIDDHI YOG?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SIDDHI YOG's builder has filed on MahaRERA, the official one, is 31 December 2025, already 24 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SIDDHI YOG extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHI YOG's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 30 June 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The major reason for the delay is the stop-work order issued by MHADA dated 11th October 2023, which halted the project temporarily. We are pleased to inform you that this order has now been withdrawn, as evidenced by the withdrawal order issued on 2nd December 2024, which is attached herewith for your reference. In addition to the above, the project experienced challenges related to procurement, unforeseen site conditions, coordination issues, and temporary financial constraints. Despite these s…"; to 31 December 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2025".
What is the RERA number of SIDDHI YOG?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SIDDHI YOG in Mahim, Mumbai is P51900017229.
Is SIDDHI YOG registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHI YOG is registered as P51900017229 and its status is "Lapsed (registration period ended)".
What is the construction status of SIDDHI YOG?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHI YOG's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SIDDHI YOG is 80% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does SIDDHI YOG have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SIDDHI YOG safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHI YOG is registered on MahaRERA as P51900017229, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SIDDHI YOG's possession date changes?
The latest dates are on SIDDHI YOG's MahaRERA page (P51900017229). GharKundli's Kundli Watch sends a free WhatsApp update on SIDDHI YOG every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SIDDHI YOG have?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHI YOG has one building filed: SIDDHI YOG with 23 floors and 16 units.
What are the flat sizes (carpet area) in SIDDHI YOG?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SIDDHI YOG: 1 BHK: 441 sq ft carpet (8 homes); 3 BHK: 1431 to 1442 sq ft carpet (8 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SIDDHI YOG?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHI YOG stands on 625 sq m of land (about 0.2 acres).
Where can I read reviews of SIDDHI YOG?
Google Maps has reviews of SIDDHI YOG written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SIDDHI YOG?
SIDDHI YOG by SIDDHITECH DEVELOPERS PRIVATE LIMITED is in Mahim, Mumbai (pincode 400016), near Dadar West, Shivaji Park, Matunga, Maharashtra, and is registered on MahaRERA as P51900017229, per GharKundli's check of MahaRERA records. Its boundaries filed there include SHITALADEVI TEMPLE ROAD.
How many homes are in SIDDHI YOG?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHI YOG has 16 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was SIDDHI YOG registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SIDDHI YOG was registered on MahaRERA on 24 July 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on SIDDHI YOG?
No court cases are listed for SIDDHI YOG on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SIDDHI YOG?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SIDDHITECH DEVELOPERS PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of SIDDHI YOG
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400016
All 83 projects in Mahim (400016) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.