Skip to content
GharKundli

Meera Upvan Co-operative Housing Society Limited

by YOGIRAJ BUILDERS AND DEVELOPERS · Borivali East, Mumbai 400066Also near Borivali West, Mandapeshwar, Dahisar

What’s in the report? →

Possession date of Meera Upvan Co-operative Housing Society Limited (MahaRERA P51800080078): 30 April 2028. It has 23 homes (1 BHK and 2 BHK, 435–805 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800080078, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800080078, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Meera Upvan Co-operative Housing Society Limited?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Meera Upvan Co-operative Housing Society Limited has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Meera Upvan Co-operative Housing Society Limited’s extension records on MahaRERA (P51800080078), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Meera Upvan Co-operative Housing Society Limited

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800080078
Status
Registered and active
Builder
YOGIRAJ BUILDERS AND DEVELOPERS
Location
Borivali East, Mumbai · 400066
Project type
Residential / Group Housing
Registered on
23 Apr 2025
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
23
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Meera Upvan Co-operative Housing Society Limited, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MEERA UPVAN CHS LIMITED100%95%11%0%

Commencement certificate (CC), as filed on MahaRERA

  • MEERA UPVAN CHS LIMITED: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Meera Upvan Co-operative Housing Society Limited every 1–2 months.

Meera Upvan Co-operative Housing Society Limited: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK435 – 51812
2 BHK565 – 80511
Shops101 – 4769
Office Space271 – 2,5356
  • Buildings: MEERA UPVAN CHS LIMITED (14 floors, 38 units)
  • Car parking: 45 covered
  • Land: 1,070 sq m (about 0.3 acres) · sanctioned built-up 2,312 sq m
  • Boundaries filed include: Wide Main Kasturba Road
  • Land, as filed: 29A
  • Map: Get directions

The builder’s record and reviews

Yogiraj Builders AND Developers has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 2 months); 2 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Meera Upvan Co-operative Housing Society Limited →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Meera Upvan Co-operative Housing Society Limited: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Meera Upvan Co-operative Housing Society Limited

What is the possession date of Meera Upvan Co-operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Meera Upvan Co-operative Housing Society Limited in Borivali East, Mumbai is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Meera Upvan Co-operative Housing Society Limited?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Meera Upvan Co-operative Housing Society Limited's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Meera Upvan Co-operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Meera Upvan Co-operative Housing Society Limited in Borivali East, Mumbai is P51800080078.

Is Meera Upvan Co-operative Housing Society Limited registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Meera Upvan Co-operative Housing Society Limited is registered as P51800080078 and its status is "Registered and active".

What is the current construction status of Meera Upvan Co-operative Housing Society Limited? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Meera Upvan Co-operative Housing Society Limited's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MEERA UPVAN CHS LIMITED is 95% done and internal work 11%. GharKundli's full report compares construction progress with the deadline.

Does Meera Upvan Co-operative Housing Society Limited have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Meera Upvan Co-operative Housing Society Limited safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Meera Upvan Co-operative Housing Society Limited is registered on MahaRERA as P51800080078, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Meera Upvan Co-operative Housing Society Limited?

Meera Upvan Co-operative Housing Society Limited is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Meera Upvan Co-operative Housing Society Limited are 435 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Meera Upvan Co-operative Housing Society Limited?

For a flat in Meera Upvan Co-operative Housing Society Limited (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Meera Upvan Co-operative Housing Society Limited received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Meera Upvan Co-operative Housing Society Limited is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Meera Upvan Co-operative Housing Society Limited a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Meera Upvan Co-operative Housing Society Limited is a redevelopment: 18 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Meera Upvan Co-operative Housing Society Limited uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Meera Upvan Co-operative Housing Society Limited was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Meera Upvan Co-operative Housing Society Limited's possession date changes?

The latest dates are on Meera Upvan Co-operative Housing Society Limited's MahaRERA page (P51800080078). GharKundli's Kundli Watch sends a free WhatsApp update on Meera Upvan Co-operative Housing Society Limited every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Meera Upvan Co-operative Housing Society Limited have?

According to GharKundli's check of MahaRERA records (updated October 2026), Meera Upvan Co-operative Housing Society Limited has one building filed: MEERA UPVAN CHS LIMITED with 14 floors and 38 units.

What are the flat sizes (carpet area) in Meera Upvan Co-operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Meera Upvan Co-operative Housing Society Limited: 1 BHK: 435 to 518 sq ft carpet (12 homes); 2 BHK: 565 to 805 sq ft carpet (11 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Meera Upvan Co-operative Housing Society Limited have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 45 covered car parking spaces for Meera Upvan Co-operative Housing Society Limited.

How big is the land of Meera Upvan Co-operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), Meera Upvan Co-operative Housing Society Limited stands on 1,070 sq m of land (about 0.3 acres), with 2,312 sq m of sanctioned built-up area.

What is the track record of Meera Upvan Co-operative Housing Society Limited's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Yogiraj Builders AND Developers has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 2 months); 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Meera Upvan Co-operative Housing Society Limited?

Google Maps has reviews of Meera Upvan Co-operative Housing Society Limited written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Meera Upvan Co-operative Housing Society Limited?

Meera Upvan Co-operative Housing Society Limited by YOGIRAJ BUILDERS AND DEVELOPERS is in Borivali East, Mumbai, pincode 400066 (near Borivali West, Mandapeshwar, Dahisar), Maharashtra, and is registered on MahaRERA as P51800080078, per GharKundli's check of MahaRERA records. Its boundaries filed there include Wide Main Kasturba Road. Its land is filed as 29A. GharKundli lists all 228 MahaRERA projects in Borivali East (400066).

How many flats are in Meera Upvan Co-operative Housing Society Limited, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Meera Upvan Co-operative Housing Society Limited has 23 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Meera Upvan Co-operative Housing Society Limited registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Meera Upvan Co-operative Housing Society Limited was registered on MahaRERA on 23 April 2025. GharKundli did not find a title report on the land on file there.

Does Meera Upvan Co-operative Housing Society Limited have any legal issues or court cases?

No court cases are listed for Meera Upvan Co-operative Housing Society Limited on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Meera Upvan Co-operative Housing Society Limited?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is YOGIRAJ BUILDERS AND DEVELOPERS, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Borivali East (400066)

All 228 projects in Borivali East (400066) →

Other projects by YOGIRAJ BUILDERS AND DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.