by OMKAR ENGINEERS AND CONTRACTORS · Borivali East, MumbaiAlso near Borivali West, Dahisar, Mandapeshwar
Possession date of DIWALI DARSHAN: 1 February 2027, moved from 31 January 2026 (13 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800080143, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about DIWALI DARSHAN?
How the possession date of DIWALI DARSHAN has moved
31 January 2026
Completion date given when the project was registered
1 February 2027
Extended at the builder's request (MahaRERA application EA19032620285)
Reason the builder gave MahaRERA:
“Subject: Submission of Technical Reasons for Delay in Completion of the Project - Diwali Darshan CHSL, Maha RERA Reg. No P51800080143 Respected Sir, We, Narendra Shah, are the promoters of the real estate project known as "Diwali Darshan CH…” Read the full reason
“Subject: Submission of Technical Reasons for Delay in Completion of the Project - Diwali Darshan CHSL, Maha RERA Reg. No P51800080143 Respected Sir, We, Narendra Shah, are the promoters of the real estate project known as "Diwali Darshan CHSL" bearing Maha RERA Registration No. P51800080143 The project completion has been delayed due to unforeseen technical challenges encountered during execution, additional structural work, impacting timelines. Further, delays in procurement of key materials and extended monsoon conditions caused interruptions in construction activities. Additionally, time…”
Source: DIWALI DARSHAN’s extension records on MahaRERA (P51800080143), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DIWALI DARSHAN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 1 court case, and how it ended
- Construction pace against the February 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800080143
- Status
- Registered and active
- Builder
- OMKAR ENGINEERS AND CONTRACTORS
- Location
- Borivali East, Mumbai · 400066
- Project type
- Residential / Group Housing
- Registered on
- 30 Apr 2025
- Completion date at registration
- January 2026
- Latest completion date
- February 2027
- Delay so far
- 13 months
- Homes
- 39
- Sold or booked
- 7%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of DIWALI DARSHAN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DIWALI DARSHAN | 100% | 81.25% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- DIWALI DARSHAN: covers o 1ST TO 2ND COMMERCIAL FLOOR + 3RD TO 5TH PODIUM FLOOR + SERVICE FLOOR + 6TH TO 15 UPPER FLOORS.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DIWALI DARSHAN every month.
DIWALI DARSHAN: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 1,970 – 5,943 | 19 |
| Office Space | 991 – 22,776 | 18 |
| Shops | 1,244 – 2,713 | 14 |
| 2 BHK | 2,334 – 7,114 | 14 |
| 1 Room Kitchen | 2,518 – 4,010 | 5 |
| 3 BHK | 11,361 | 1 |
- Buildings: DIWALI DARSHAN (19 floors, 71 units)
- Car parking: 33 covered
- Land: 877 sq m (about 0.2 acres) · sanctioned built-up 2,761 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of DIWALI DARSHAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DIWALI DARSHAN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DIWALI DARSHAN
What is the possession date of DIWALI DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DIWALI DARSHAN in Borivali East, Mumbai is 1 February 2027 — 13 months later than 31 January 2026, the date given at registration.
Is the builder's possession date different from the MahaRERA date for DIWALI DARSHAN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DIWALI DARSHAN's builder has filed on MahaRERA, the official one, is 1 February 2027, already 13 months later than the 31 January 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of DIWALI DARSHAN extended?
According to GharKundli's check of MahaRERA records (updated October 2026), DIWALI DARSHAN's builder applied to MahaRERA to extend the completion date once: to 1 February 2027, giving the reason "Subject: Submission of Technical Reasons for Delay in Completion of the Project - Diwali Darshan CHSL, Maha RERA Reg. No P51800080143 Respected Sir, We, Narendra Shah, are the promoters of the real estate project known as "Diwali Darshan CHSL" bearing Maha RERA Registration No. P51800080143 The project completion has been delayed due to unforeseen technical challenges encountered during execution, additional structural work, impacting timelines. Further, delays in procurement of key materials and extended monsoon conditions caused interruptions in construction activities. Additionally, time…".
What is the RERA number of DIWALI DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DIWALI DARSHAN in Borivali East, Mumbai is P51800080143.
Is DIWALI DARSHAN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DIWALI DARSHAN is registered as P51800080143 and its status is "Registered and active".
What is the construction status of DIWALI DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), DIWALI DARSHAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on DIWALI DARSHAN is 81.25% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does DIWALI DARSHAN have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is DIWALI DARSHAN safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), DIWALI DARSHAN is registered on MahaRERA as P51800080143, its completion date has moved 13 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DIWALI DARSHAN's possession date changes?
The latest dates are on DIWALI DARSHAN's MahaRERA page (P51800080143). GharKundli's Kundli Watch sends a free WhatsApp update on DIWALI DARSHAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DIWALI DARSHAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), DIWALI DARSHAN has one building filed: DIWALI DARSHAN with 19 floors and 71 units.
What are the flat sizes (carpet area) in DIWALI DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for DIWALI DARSHAN: 1 BHK: 1970 to 5943 sq ft carpet (19 homes); 2 BHK: 2334 to 7114 sq ft carpet (14 homes); 1 Room Kitchen: 2518 to 4010 sq ft carpet (5 homes); 3 BHK: 11361 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does DIWALI DARSHAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 33 covered car parking spaces for DIWALI DARSHAN.
How big is the land of DIWALI DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), DIWALI DARSHAN stands on 877 sq m of land (about 0.2 acres), with 2,761 sq m of sanctioned built-up area.
Where can I read reviews of DIWALI DARSHAN?
Google Maps has reviews of DIWALI DARSHAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DIWALI DARSHAN?
DIWALI DARSHAN by OMKAR ENGINEERS AND CONTRACTORS is in Borivali East, Mumbai (pincode 400066), near Borivali West, Dahisar, Mandapeshwar, Maharashtra, and is registered on MahaRERA as P51800080143, per GharKundli's check of MahaRERA records.
How many homes are in DIWALI DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), DIWALI DARSHAN has 39 homes in 1 tower registered on MahaRERA, and 7% of them are sold or booked.
When was DIWALI DARSHAN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DIWALI DARSHAN was registered on MahaRERA on 30 April 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on DIWALI DARSHAN?
1 court case is listed for DIWALI DARSHAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of DIWALI DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is OMKAR ENGINEERS AND CONTRACTORS.
Check it yourself on MahaRERA
- How to check the possession date of DIWALI DARSHAN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400066
- Rustomjee Summit
- RAJENDRA NAGAR SWAGAT CHSL
- RAJENDRA NAGAR OMSAI CO-OPERATIVE HOUSING SOCIETY LIMITED
- MEGH MAHAL CHSL
- PARSHURAM HEIGHTS
- DTG ASHFORD
- H. Rishabraj AER
- Paras Darshan
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.