The Westpark Phase-1
by WESTPARK DEVELOPERS PRIVATE LIMITED · Oshiwara-Jogeshwari West, Mumbai 400102Also near Andheri West, Goregaon West, Adarsh Nagar
What’s in the report? →Possession date of The Westpark Phase-1 (MahaRERA PR1181012500079): 30 October 2032. It has 416 homes (3 BHK, 4 BHK and 5 BHK, 245–2278 sq ft carpet), 98% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1181012500079, and currently active. Its completion date is now October 2032, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PR1181012500079, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about The Westpark Phase-1?
31 court cases MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of The Westpark Phase-1 has moved
30 June 2032
Completion date given when the project was registered
30 October 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: The Westpark Phase-1’s extension records on MahaRERA (PR1181012500079), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on The Westpark Phase-1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 31 court cases, and how it ended
- Construction pace against the October 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1181012500079
- Status
- Registered and active
- Builder
- WESTPARK DEVELOPERS PRIVATE LIMITED
- Location
- Oshiwara-Jogeshwari West, Mumbai · 400102
- Project type
- Residential / Group Housing
- Registered on
- 16 Jun 2025
- Completion date at registration
- June 2032
- Latest completion date
- October 2032
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 416
- Sold or booked
- 98%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 31
- Title report on file
- Not found
Construction progress of The Westpark Phase-1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Tower 2 | 100% | 0% | 0% | 0% |
| Tower 3 | 100% | 0% | 0% | 0% |
| Tower 4 | 100% | 0% | 0% | 0% |
| Tower 5 | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Tower 2: covers Plinth
- Tower 3: covers Plinth
- Tower 4: covers Plinth
- Tower 5: covers Plinth
Latest CC order on MahaRERA: dated 27/05/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Westpark Phase-1 every 1–2 months.
The Westpark Phase-1: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 1,048 – 1,368 | 394 |
| 4 BHK | 1,246 – 2,278 | 13 |
| Other | 245 – 478 | 5 |
| 5 BHK | 1,825 | 4 |
- Buildings: Tower 2 (44 floors, 67 units) · Tower 3 (44 floors, 139 units) · Tower 4 (44 floors, 103 units) · Tower 5 (44 floors, 107 units)
- Car parking: 844 covered
- Land: 40,609 sq m (about 10.0 acres) · sanctioned built-up 57,510 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of The Westpark Phase-1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
The Westpark Phase-1: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about The Westpark Phase-1
What is the possession date of The Westpark Phase-1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Westpark Phase-1 in Oshiwara-Jogeshwari West, Mumbai is 30 October 2032, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for The Westpark Phase-1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date The Westpark Phase-1's builder has filed on MahaRERA, the official one, is 30 October 2032, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of The Westpark Phase-1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Westpark Phase-1 in Oshiwara-Jogeshwari West, Mumbai is PR1181012500079.
Is The Westpark Phase-1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), The Westpark Phase-1 is registered as PR1181012500079 and its status is "Registered and active".
What is the current construction status of The Westpark Phase-1? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), The Westpark Phase-1's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does The Westpark Phase-1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is The Westpark Phase-1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), The Westpark Phase-1 is registered on MahaRERA as PR1181012500079, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in The Westpark Phase-1?
The Westpark Phase-1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in The Westpark Phase-1 are 245 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in The Westpark Phase-1?
For a flat in The Westpark Phase-1 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has The Westpark Phase-1 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), The Westpark Phase-1 is still under construction, with 30 October 2032 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has The Westpark Phase-1 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for The Westpark Phase-1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if The Westpark Phase-1's possession date changes?
The latest dates are on The Westpark Phase-1's MahaRERA page (PR1181012500079). GharKundli's Kundli Watch sends a free WhatsApp update on The Westpark Phase-1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does The Westpark Phase-1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), The Westpark Phase-1 has 4 buildings filed: Tower 2 with 44 floors and 67 units; Tower 3 with 44 floors and 139 units; Tower 4 with 44 floors and 103 units; Tower 5 with 44 floors and 107 units.
What are the flat sizes (carpet area) in The Westpark Phase-1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for The Westpark Phase-1: 3 BHK: 1048 to 1368 sq ft carpet (394 homes); 4 BHK: 1246 to 2278 sq ft carpet (13 homes); Other: 245 to 478 sq ft carpet (5 homes); 5 BHK: 1825 sq ft carpet (4 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does The Westpark Phase-1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 844 covered car parking spaces for The Westpark Phase-1.
How big is the land of The Westpark Phase-1?
According to GharKundli's check of MahaRERA records (updated October 2026), The Westpark Phase-1 stands on 40,609 sq m of land (about 10.0 acres), with 57,510 sq m of sanctioned built-up area.
What are the reviews of The Westpark Phase-1?
Google Maps has reviews of The Westpark Phase-1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of The Westpark Phase-1?
The Westpark Phase-1 by WESTPARK DEVELOPERS PRIVATE LIMITED is in Oshiwara-Jogeshwari West, Mumbai, pincode 400102 (near Andheri West, Goregaon West, Adarsh Nagar), Maharashtra, and is registered on MahaRERA as PR1181012500079, per GharKundli's check of MahaRERA records. GharKundli lists all 117 MahaRERA projects in Jogeshwari West (400102).
How many flats are in The Westpark Phase-1, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), The Westpark Phase-1 has 416 homes in 4 towers registered on MahaRERA, and 98% of them are sold or booked.
When was The Westpark Phase-1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), The Westpark Phase-1 was registered on MahaRERA on 16 June 2025. GharKundli did not find a title report on the land on file there.
Does The Westpark Phase-1 have any legal issues or court cases?
31 court cases are listed for The Westpark Phase-1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what each case is about →
Who is the builder / developer of The Westpark Phase-1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is WESTPARK DEVELOPERS PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of The Westpark Phase-1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Jogeshwari West (400102)
- Arkan
- A. H. Heights
- Live Well Chs Ltd
- Infra - Azura Height
- Esquina Private Residence
- Lotus Sky Plaza
- Gurukrupa Ekam
- 24 Karat
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.