MPR SHRI PARAS DARSHAN
by MPR GROUP · Kandivali West, MumbaiAlso near Borivali
Possession date of MPR SHRI PARAS DARSHAN: 1 June 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800080359, and currently active. Its completion date is now June 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MPR SHRI PARAS DARSHAN?
How the possession date of MPR SHRI PARAS DARSHAN has moved
1 February 2028
Completion date given when the project was registered
1 June 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: MPR SHRI PARAS DARSHAN’s extension records on MahaRERA (P51800080359), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MPR SHRI PARAS DARSHAN
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800080359
- Status
- Registered and active
- Builder
- MPR GROUP
- Location
- Kandivali West, Mumbai · 400067
- Project type
- Others
- Registered on
- 26 May 2025
- Completion date at registration
- February 2028
- Latest completion date
- June 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 40
- Sold or booked
- 36%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of MPR SHRI PARAS DARSHAN, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MPR SHRI PARAS DARSHAN | 100% | 47% | 15% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- MPR SHRI PARAS DARSHAN: covers PLINTH LEVEL
Latest CC order on MahaRERA: dated 04/09/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MPR SHRI PARAS DARSHAN every month.
MPR SHRI PARAS DARSHAN: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 549 – 1,437 | 24 |
| 3 BHK | 836 – 1,133 | 14 |
| Shops | 220 – 529 | 8 |
| Office Space | 385 – 1,195 | 5 |
| 1 BHK | 428 – 978 | 2 |
- Buildings: MPR SHRI PARAS DARSHAN (20 floors, 53 units)
- Car parking: 69 covered
- Land: 1,213 sq m (about 0.3 acres) · sanctioned built-up 2,584 sq m
The builder’s record and reviews
MPR Group (a group of 4 linked companies) has 7 projects on MahaRERA since 2022, this one included. Of the 7 GharKundli has checked: 3 finished, all within the promised date; 4 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of MPR SHRI PARAS DARSHAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MPR SHRI PARAS DARSHAN: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MPR SHRI PARAS DARSHAN
What is the possession date of MPR SHRI PARAS DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MPR SHRI PARAS DARSHAN in Kandivali West, Mumbai is 1 June 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MPR SHRI PARAS DARSHAN?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MPR SHRI PARAS DARSHAN's builder has filed on MahaRERA, the official one, is 1 June 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of MPR SHRI PARAS DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MPR SHRI PARAS DARSHAN in Kandivali West, Mumbai is P51800080359.
Is MPR SHRI PARAS DARSHAN registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MPR SHRI PARAS DARSHAN is registered as P51800080359 and its status is "Registered and active".
What is the construction status of MPR SHRI PARAS DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), MPR SHRI PARAS DARSHAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MPR SHRI PARAS DARSHAN is 47% done and internal work 15%. GharKundli's full report compares construction progress with the deadline.
Does MPR SHRI PARAS DARSHAN have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is MPR SHRI PARAS DARSHAN safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MPR SHRI PARAS DARSHAN is registered on MahaRERA as P51800080359, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MPR SHRI PARAS DARSHAN's possession date changes?
The latest dates are on MPR SHRI PARAS DARSHAN's MahaRERA page (P51800080359). GharKundli's Kundli Watch sends a free WhatsApp update on MPR SHRI PARAS DARSHAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MPR SHRI PARAS DARSHAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), MPR SHRI PARAS DARSHAN has one building filed: MPR SHRI PARAS DARSHAN with 20 floors and 53 units.
What are the flat sizes (carpet area) in MPR SHRI PARAS DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for MPR SHRI PARAS DARSHAN: 2 BHK: 549 to 1437 sq ft carpet (24 homes); 3 BHK: 836 to 1133 sq ft carpet (14 homes); 1 BHK: 428 to 978 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does MPR SHRI PARAS DARSHAN have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 69 covered car parking spaces for MPR SHRI PARAS DARSHAN.
How big is the land of MPR SHRI PARAS DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), MPR SHRI PARAS DARSHAN stands on 1,213 sq m of land (about 0.3 acres), with 2,584 sq m of sanctioned built-up area.
What is the track record of MPR SHRI PARAS DARSHAN's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), MPR Group (a group of 4 linked companies) has 7 projects on MahaRERA since 2022, this one included. Of the 7 GharKundli has checked: 3 finished, all within the promised date; 4 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MPR SHRI PARAS DARSHAN?
Google Maps has reviews of MPR SHRI PARAS DARSHAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MPR SHRI PARAS DARSHAN?
MPR SHRI PARAS DARSHAN by MPR GROUP is in Kandivali West, Mumbai (pincode 400067), near Borivali, Maharashtra, and is registered on MahaRERA as P51800080359, per GharKundli's check of MahaRERA records.
How many homes are in MPR SHRI PARAS DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), MPR SHRI PARAS DARSHAN has 40 homes in 1 tower registered on MahaRERA, and 36% of them are sold or booked.
When was MPR SHRI PARAS DARSHAN registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MPR SHRI PARAS DARSHAN was registered on MahaRERA on 26 May 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on MPR SHRI PARAS DARSHAN?
No court cases are listed for MPR SHRI PARAS DARSHAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of MPR SHRI PARAS DARSHAN?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MPR GROUP, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MPR SHRI PARAS DARSHAN
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai Suburban →
Other projects in pincode 400067
- PRIME SQUARE
- LA SERENA Tower 5, Tower 6 and Tower 7
- CHARKOP SHREE GANESH CHS LTD
- SAFFRONWOODS CHSL
- SIGMA AMBER
- VIRGO
- Avenue Wing B phase 2
- JAYAKAR HOUSE
Other projects by MPR GROUP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.