Avenue Wing B phase 2
by Dharmesh Constructions Private Limited (Acme) · Charkop gaon, MumbaiAlso near Kandivali West, Borivali
Possession date of Avenue Wing B phase 2: 31 December 2029, moved from 31 December 2025 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800031398, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
Sales frozen by MahaRERA: quarterly reports not filed
MahaRERA has put this project in abeyance for not filing its quarterly progress reports (October 2021). Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about Avenue Wing B phase 2?
How the possession date of Avenue Wing B phase 2 has moved
31 December 2025
Completion date given when the project was registered
31 December 2029
Extended at the builder's request (MahaRERA application EA20082622273)
Reason the builder gave MahaRERA:
“• 29 Months - We applied for Plot Demarcation on 27/09/2016 and received it finally on 12/02/2019 from Approving Authority. • 14 Months - Till Date 24 slum tenants had refused to vacate the plot and we had to go to Court to vacate them as p…” Read the full reason
“• 29 Months - We applied for Plot Demarcation on 27/09/2016 and received it finally on 12/02/2019 from Approving Authority. • 14 Months - Till Date 24 slum tenants had refused to vacate the plot and we had to go to Court to vacate them as per 33(38) provision of Slum Act which is to vacate their respective premises for the purpose of demolition so that further work for the project can commence, hence we have initiated 33(38) proceedings in SRA on 23/10/2018 and obtained order against few non-cooperating members on 13/03/2019. Although, in 13/03/2019 we received notice, we had to take approv…”
Source: Avenue Wing B phase 2’s extension records on MahaRERA (P51800031398), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Avenue Wing B phase 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- AVENUE WING AP51800002030 · possession 30 Dec 2021
- Avenue Wing A phase 2P51800030589 · possession 31 Dec 2024
- AVENUE WING BP51800004402 · possession 30 Dec 2026
- MahaRERA registration
- P51800031398
- Status
- Registered and active
- Builder
- Dharmesh Constructions Private Limited
- Location
- Charkop gaon, Mumbai · 400067
- Project type
- Residential / Group Housing
- Registered on
- 23 Oct 2021
- Completion date at registration
- December 2025
- Latest completion date
- December 2029
- Delay so far
- 48 months
- Homes
- 95
- Sold or booked
- 14%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Avenue Wing B phase 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Avenue Wing B phase 2 | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Avenue Wing B phase 2: covers 1 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Avenue Wing B phase 2 every month.
Avenue Wing B phase 2: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 518 – 742 | 67 |
| 3 BHK | 1,056 | 28 |
- Buildings: Avenue Wing B phase 2 (15 floors, 95 units)
- Land: 698 sq m (about 0.2 acres) · sanctioned built-up 7,564 sq m
The builder’s record and reviews
Acme Complex (a group of 3 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 23 months); 3 still being built, 3 past the promised date (typically 52 months late); 2 lapsed. 54 complaints on MahaRERA across 5 projects.
Read Google reviews of Avenue Wing B phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Avenue Wing B phase 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Avenue Wing B phase 2
What is the possession date of Avenue Wing B phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Avenue Wing B phase 2 in Charkop gaon, Mumbai is 31 December 2029 — 48 months later than 31 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Avenue Wing B phase 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Avenue Wing B phase 2's builder has filed on MahaRERA, the official one, is 31 December 2029, already 48 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Avenue Wing B phase 2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Wing B phase 2's builder applied to MahaRERA to extend the completion date once: to 31 December 2029, giving the reason "• 29 Months - We applied for Plot Demarcation on 27/09/2016 and received it finally on 12/02/2019 from Approving Authority. • 14 Months - Till Date 24 slum tenants had refused to vacate the plot and we had to go to Court to vacate them as per 33(38) provision of Slum Act which is to vacate their respective premises for the purpose of demolition so that further work for the project can commence, hence we have initiated 33(38) proceedings in SRA on 23/10/2018 and obtained order against few non-cooperating members on 13/03/2019. Although, in 13/03/2019 we received notice, we had to take approv…".
What is the RERA number of Avenue Wing B phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Avenue Wing B phase 2 in Charkop gaon, Mumbai is P51800031398.
Is Avenue Wing B phase 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Wing B phase 2 is registered as P51800031398 and its status is "Registered and active". On MahaRERA's own list: Sales frozen by MahaRERA: quarterly reports not filed. MahaRERA has put this project in abeyance for not filing its quarterly progress reports (October 2021). Its bank account is frozen, and the builder may not sign agreements for sale or sale deeds with buyers until it complies.
What is the construction status of Avenue Wing B phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Wing B phase 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Avenue Wing B phase 2 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Avenue Wing B phase 2 have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Avenue Wing B phase 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Wing B phase 2 is registered on MahaRERA as P51800031398, its completion date has moved 48 months since registration, 1 complaint is listed against it and it is on MahaRERA's list "Sales frozen by MahaRERA: quarterly reports not filed". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Avenue Wing B phase 2 have other wings or phases?
Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: AVENUE WING A (P51800002030, possession 30 Dec 2021); Avenue Wing A phase 2 (P51800030589, possession 31 Dec 2024); AVENUE WING B (P51800004402, possession 30 Dec 2026). Check that your agreement names the registration of your own wing.
How can I get updates if Avenue Wing B phase 2's possession date changes?
The latest dates are on Avenue Wing B phase 2's MahaRERA page (P51800031398). GharKundli's Kundli Watch sends a free WhatsApp update on Avenue Wing B phase 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Avenue Wing B phase 2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Wing B phase 2 has one building filed: Avenue Wing B phase 2 with 15 floors and 95 units.
What are the flat sizes (carpet area) in Avenue Wing B phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Avenue Wing B phase 2: 2 BHK: 518 to 742 sq ft carpet (67 homes); 3 BHK: 1056 sq ft carpet (28 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Avenue Wing B phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Wing B phase 2 stands on 698 sq m of land (about 0.2 acres), with 7,564 sq m of sanctioned built-up area.
What is the track record of Avenue Wing B phase 2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Acme Complex (a group of 3 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 23 months); 3 still being built, 3 past the promised date (typically 52 months late); 2 lapsed. 54 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Avenue Wing B phase 2?
Google Maps has reviews of Avenue Wing B phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Avenue Wing B phase 2?
Avenue Wing B phase 2 by Dharmesh Constructions Private Limited (Acme) is in Charkop gaon, Mumbai (pincode 400067), near Kandivali West, Borivali, Maharashtra, and is registered on MahaRERA as P51800031398, per GharKundli's check of MahaRERA records.
How many homes are in Avenue Wing B phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Wing B phase 2 has 95 homes in 1 tower registered on MahaRERA, and 14% of them are sold or booked.
When was Avenue Wing B phase 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Avenue Wing B phase 2 was registered on MahaRERA on 23 October 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Avenue Wing B phase 2?
No court cases are listed for Avenue Wing B phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Avenue Wing B phase 2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Dharmesh Constructions Private Limited, the company Acme files this project under, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Avenue Wing B phase 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in pincode 400067
- PRIME SQUARE
- LA SERENA Tower 5, Tower 6 and Tower 7
- CHARKOP SHREE GANESH CHS LTD
- MPR SHRI PARAS DARSHAN
- SAFFRONWOODS CHSL
- SIGMA AMBER
- VIRGO
- JAYAKAR HOUSE
Other projects by Dharmesh Constructions Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.