AVENUE WING B

by Dharmesh Constructions Private Limited (Acme) · Kandivali, MumbaiAlso near Bandra, Iraniwadi, Malad West

Possession date of AVENUE WING B: 30 December 2026, moved from 30 June 2021 (66 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800004402, and currently active. MahaRERA has issued 2 regulatory orders on this project. 36 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AVENUE WING B?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AVENUE WING B has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 29 June 2022

    Extended at the builder's request (MahaRERA application EXT51800009382)

    Reason the builder gave MahaRERA:
    “2016: PLOT BOUNDARY DEMARCATION ISSUE 2016: DUMPING GROUND ISSUE 2016: DEMONITISATION 2017: IMPLEMENTATION OF RERA ACT 2017: GST IMPACT 2018: AMENDMENT IN DCR 2018: 33/38 PROCEEDINGS UNDER SLUMS ACT INITIATED AGAINST TENANTS WHO WERE NOT VA…” Read the full reason“2016: PLOT BOUNDARY DEMARCATION ISSUE 2016: DUMPING GROUND ISSUE 2016: DEMONITISATION 2017: IMPLEMENTATION OF RERA ACT 2017: GST IMPACT 2018: AMENDMENT IN DCR 2018: 33/38 PROCEEDINGS UNDER SLUMS ACT INITIATED AGAINST TENANTS WHO WERE NOT VACATING 2019: FURTHER 33/38 PROCEEDINGS 2019: ROAD GOING THROUGH OUR PROPERTY INCORRECTLY SHOWN IN DP 2034 TILL DATE: Non-payment of outstanding dues by many flat purchasers affecting the pace of work and delaying the project TILL DATE: CORONA VIRUS- COVID 19 PANDEMIC”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800015056)

    Reason the builder gave MahaRERA:
    “• 29 Months Delay - We applied for Plot Demarcation on 27/09/2016 and received it finally on 12/02/2019 from Approving Authority. • 14 Months Delay Till Date - 24 slum tenants had refused to vacate the plot and we had to go to Court to vaca…” Read the full reason“• 29 Months Delay - We applied for Plot Demarcation on 27/09/2016 and received it finally on 12/02/2019 from Approving Authority. • 14 Months Delay Till Date - 24 slum tenants had refused to vacate the plot and we had to go to Court to vacate them as per 33(38) provision of Slum Act which is to vacate their respective premises for the purpose of demolition so that further work for the project can commence, hence we have initiated 33(38) proceedings in SRA on 23/10/2018 and obtained order against few non-cooperating members on 13/03/2019. • 13 Months Delay Till Date - Under DCPR 2034 and new…”
  4. 30 December 2026

    Extended at the builder's request (MahaRERA application EXT51800024747)

    Reason the builder gave MahaRERA:
    “• 29 Months Delay - We applied for Plot Demarcation on 27/09/2016 and received it finally on 12/02/2019 from Approving Authority. • 14 Months Delay Till Date 24 slum tenants had refused to vacate the plot and we had to go to Court to vacate…” Read the full reason“• 29 Months Delay - We applied for Plot Demarcation on 27/09/2016 and received it finally on 12/02/2019 from Approving Authority. • 14 Months Delay Till Date 24 slum tenants had refused to vacate the plot and we had to go to Court to vacate them as per 33(38) provision of Slum Act which is to vacate their respective premises for the purpose of demolition so that further work for the project can commence, hence we have initiated 33(38) proceedings in SRA on 23/10/2018 and obtained order against few non-cooperating members on 13/03/2019. • 13 Months Delay Till Date Under DCPR 2034 and new DP,…”

Source: AVENUE WING B’s extension records on MahaRERA (P51800004402), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AVENUE WING B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 36 complaints and 2 court cases, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800004402
Status
Registered and active
Builder
Dharmesh Constructions Private Limited
Location
Kandivali, Mumbai · 400067
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
June 2021
Latest completion date
December 2026
Delay so far
66 months
Homes
174
Sold or booked
88%
Towers
1
Complaints on MahaRERA
36
Court cases listed
2
Appeals at the tribunal
6
MahaRERA regulatory orders
2
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of AVENUE WING B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Avenue B wing100%85%40%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AVENUE WING B every month.

AVENUE WING B: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK668 – 74278
3 BHK995 – 1,05652
Other491 – 51944

The builder’s record and reviews

Acme Complex (a group of 3 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 23 months); 3 still being built, 3 past the promised date (typically 52 months late); 2 lapsed. 54 complaints on MahaRERA across 5 projects.

Read Google reviews of AVENUE WING B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AVENUE WING B: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AVENUE WING B

What is the possession date of AVENUE WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AVENUE WING B in Kandivali, Mumbai is 30 December 2026 — 66 months later than 30 June 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for AVENUE WING B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AVENUE WING B's builder has filed on MahaRERA, the official one, is 30 December 2026, already 66 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AVENUE WING B extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AVENUE WING B's builder applied to MahaRERA to extend the completion date 3 times: to 29 June 2022, giving the reason "2016: PLOT BOUNDARY DEMARCATION ISSUE 2016: DUMPING GROUND ISSUE 2016: DEMONITISATION 2017: IMPLEMENTATION OF RERA ACT 2017: GST IMPACT 2018: AMENDMENT IN DCR 2018: 33/38 PROCEEDINGS UNDER SLUMS ACT INITIATED AGAINST TENANTS WHO WERE NOT VACATING 2019: FURTHER 33/38 PROCEEDINGS 2019: ROAD GOING THROUGH OUR PROPERTY INCORRECTLY SHOWN IN DP 2034 TILL DATE: Non-payment of outstanding dues by many flat purchasers affecting the pace of work and delaying the project TILL DATE: CORONA VIRUS- COVID 19 PANDEMIC"; to 31 December 2024, giving the reason "• 29 Months Delay - We applied for Plot Demarcation on 27/09/2016 and received it finally on 12/02/2019 from Approving Authority. • 14 Months Delay Till Date - 24 slum tenants had refused to vacate the plot and we had to go to Court to vacate them as per 33(38) provision of Slum Act which is to vacate their respective premises for the purpose of demolition so that further work for the project can commence, hence we have initiated 33(38) proceedings in SRA on 23/10/2018 and obtained order against few non-cooperating members on 13/03/2019. • 13 Months Delay Till Date - Under DCPR 2034 and new…"; to 30 December 2026, giving the reason "• 29 Months Delay - We applied for Plot Demarcation on 27/09/2016 and received it finally on 12/02/2019 from Approving Authority. • 14 Months Delay Till Date 24 slum tenants had refused to vacate the plot and we had to go to Court to vacate them as per 33(38) provision of Slum Act which is to vacate their respective premises for the purpose of demolition so that further work for the project can commence, hence we have initiated 33(38) proceedings in SRA on 23/10/2018 and obtained order against few non-cooperating members on 13/03/2019. • 13 Months Delay Till Date Under DCPR 2034 and new DP,…".

What is the RERA number of AVENUE WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AVENUE WING B in Kandivali, Mumbai is P51800004402.

Is AVENUE WING B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AVENUE WING B is registered as P51800004402 and its status is "Registered and active".

What is the construction status of AVENUE WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), AVENUE WING B's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Avenue B wing is 85% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.

Does AVENUE WING B have complaints on MahaRERA?

36 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AVENUE WING B safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AVENUE WING B is registered on MahaRERA as P51800004402, its completion date has moved 66 months since registration and 36 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does AVENUE WING B have other wings or phases?

Yes. MahaRERA lists 3 other registrations of the same project, each with its own possession date: AVENUE WING A (P51800002030, possession 30 Dec 2021); Avenue Wing A phase 2 (P51800030589, possession 31 Dec 2024); Avenue Wing B phase 2 (P51800031398, possession 31 Dec 2029). Check that your agreement names the registration of your own wing.

How can I get updates if AVENUE WING B's possession date changes?

The latest dates are on AVENUE WING B's MahaRERA page (P51800004402). GharKundli's Kundli Watch sends a free WhatsApp update on AVENUE WING B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AVENUE WING B have?

According to GharKundli's check of MahaRERA records (updated October 2026), AVENUE WING B has one building filed: Avenue B wing with 28 floors and 174 units.

What are the flat sizes (carpet area) in AVENUE WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for AVENUE WING B: 2 BHK: 668 to 742 sq ft carpet (78 homes); 3 BHK: 995 to 1056 sq ft carpet (52 homes); Other: 491 to 519 sq ft carpet (44 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of AVENUE WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), AVENUE WING B stands on 698 sq m of land (about 0.2 acres), with 14,280 sq m of sanctioned built-up area.

What is the track record of AVENUE WING B's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Acme Complex (a group of 3 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 23 months); 3 still being built, 3 past the promised date (typically 52 months late); 2 lapsed. 54 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of AVENUE WING B?

Google Maps has reviews of AVENUE WING B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 36 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AVENUE WING B?

AVENUE WING B by Dharmesh Constructions Private Limited (Acme) is in Kandivali, Mumbai (pincode 400067), near Bandra, Iraniwadi, Malad West, Maharashtra, and is registered on MahaRERA as P51800004402, per GharKundli's check of MahaRERA records.

How many homes are in AVENUE WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), AVENUE WING B has 174 homes in 1 tower registered on MahaRERA, and 88% of them are sold or booked.

When was AVENUE WING B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AVENUE WING B was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on AVENUE WING B?

2 court cases are listed for AVENUE WING B on MahaRERA, and 6 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of AVENUE WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Dharmesh Constructions Private Limited, the company Acme files this project under, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400067

All 318 projects in Kandivali West (400067) →

Other projects by Dharmesh Constructions Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.