Vastunemi Good Luck Apartment
by VASTUNEMI BUILDTECH LLP · Malad East, Mumbai 400097Also near malad west, Kurar Village, Borivali West
What’s in the report? →Possession date of Vastunemi Good Luck Apartment (MahaRERA PM1180002500832): 30 April 2029. It has 32 homes (1 BHK, 2 BHK and 3 BHK, 430–785 sq ft carpet), 30% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PM1180002500832, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PM1180002500832, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Vastunemi Good Luck Apartment?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Vastunemi Good Luck Apartment has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Vastunemi Good Luck Apartment’s extension records on MahaRERA (PM1180002500832), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vastunemi Good Luck Apartment
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1180002500832
- Status
- Registered and active
- Builder
- VASTUNEMI BUILDTECH LLP
- Location
- Malad East, Mumbai · 400097
- Project type
- Mixed
- Registered on
- 18 Sep 2025
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 32
- Sold or booked
- 30%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Vastunemi Good Luck Apartment, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Bldg | 0% | 32% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Bldg: covers Plinth
Latest CC order on MahaRERA: dated 31/07/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vastunemi Good Luck Apartment every 1–2 months.
Vastunemi Good Luck Apartment: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 668 | 16 |
| 1 BHK | 430 | 15 |
| Shops | 1,145 | 1 |
| Office Space | 1,297 | 1 |
| 3 BHK | 785 | 1 |
- Buildings: Bldg (19 floors, 34 units)
- Car parking: 34 covered
- Land: 709 sq m (about 0.2 acres) · sanctioned built-up 2,077 sq m
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Vastunemi Good Luck Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vastunemi Good Luck Apartment: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Vastunemi Good Luck Apartment
What is the possession date of Vastunemi Good Luck Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vastunemi Good Luck Apartment in Malad East, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Vastunemi Good Luck Apartment?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vastunemi Good Luck Apartment's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Vastunemi Good Luck Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vastunemi Good Luck Apartment in Malad East, Mumbai is PM1180002500832.
Is Vastunemi Good Luck Apartment registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunemi Good Luck Apartment is registered as PM1180002500832 and its status is "Registered and active".
What is the current construction status of Vastunemi Good Luck Apartment? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunemi Good Luck Apartment's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Bldg is 32% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Vastunemi Good Luck Apartment have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vastunemi Good Luck Apartment safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunemi Good Luck Apartment is registered on MahaRERA as PM1180002500832, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Vastunemi Good Luck Apartment?
Vastunemi Good Luck Apartment is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Vastunemi Good Luck Apartment are 430 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Vastunemi Good Luck Apartment?
For a flat in Vastunemi Good Luck Apartment (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Vastunemi Good Luck Apartment received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vastunemi Good Luck Apartment is still under construction, with 30 April 2029 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Vastunemi Good Luck Apartment a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunemi Good Luck Apartment is a redevelopment: 14 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Vastunemi Good Luck Apartment uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vastunemi Good Luck Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Vastunemi Good Luck Apartment's possession date changes?
The latest dates are on Vastunemi Good Luck Apartment's MahaRERA page (PM1180002500832). GharKundli's Kundli Watch sends a free WhatsApp update on Vastunemi Good Luck Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vastunemi Good Luck Apartment have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunemi Good Luck Apartment has one building filed: Bldg with 19 floors and 34 units.
What are the flat sizes (carpet area) in Vastunemi Good Luck Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Vastunemi Good Luck Apartment: 2 BHK: 668 sq ft carpet (16 homes); 1 BHK: 430 sq ft carpet (15 homes); 3 BHK: 785 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Vastunemi Good Luck Apartment have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 34 covered car parking spaces for Vastunemi Good Luck Apartment.
How big is the land of Vastunemi Good Luck Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunemi Good Luck Apartment stands on 709 sq m of land (about 0.2 acres), with 2,077 sq m of sanctioned built-up area.
What are the reviews of Vastunemi Good Luck Apartment?
Google Maps has reviews of Vastunemi Good Luck Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Vastunemi Good Luck Apartment?
Vastunemi Good Luck Apartment by VASTUNEMI BUILDTECH LLP is in Malad East, Mumbai, pincode 400097 (near malad west, Kurar Village, Borivali West), Maharashtra, and is registered on MahaRERA as PM1180002500832, per GharKundli's check of MahaRERA records. GharKundli lists all 195 MahaRERA projects in Malad East (400097).
How many flats are in Vastunemi Good Luck Apartment, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunemi Good Luck Apartment has 32 homes in 1 tower registered on MahaRERA, and 30% of them are sold or booked.
When was Vastunemi Good Luck Apartment registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunemi Good Luck Apartment was registered on MahaRERA on 18 September 2025. GharKundli did not find a title report on the land on file there.
Does Vastunemi Good Luck Apartment have any legal issues or court cases?
No court cases are listed for Vastunemi Good Luck Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Vastunemi Good Luck Apartment?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VASTUNEMI BUILDTECH LLP.
Check it yourself on MahaRERA
- How to check the possession date of Vastunemi Good Luck Apartment
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in Malad East (400097)
- Aarambh Phase III by group Satellite
- L&T Realty Ahana Tower B
- Namo Whispering Bliss
- Upper East 97
- Nivetia Heights
- Vardhan Royale
- L&T Realty Ahana Tower A
- Pearl Solitaire
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.