Center Plaza Phase 1

by B V ENTERPRISES (Sethia) · Malad East, Mumbai 400097Also near malad west, Kurar Village, Borivali West

What’s in the report? →

Possession date of Center Plaza Phase 1 (MahaRERA P51800034832): 30 April 2028, moved from 31 December 2023 (48 months later). No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800034832, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800034832, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Center Plaza Phase 1?

1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Center Plaza Phase 1 has moved

  1. 31 December 2023

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA23062501710)

    Reason the builder gave MahaRERA:
    “This is to inform you that our project name Center Plaza Phase 1 located at plot bearing C.T.S. No. 357 at village Malad (East) and C.TS. No. 521 522 of Village Kurar, Taluka Borivali, Mumbai - 400 097 Bearing Rera No P51800034832. The only…” Read the full reason“This is to inform you that our project name Center Plaza Phase 1 located at plot bearing C.T.S. No. 357 at village Malad (East) and C.TS. No. 521 522 of Village Kurar, Taluka Borivali, Mumbai - 400 097 Bearing Rera No P51800034832. The only pending work of the Mechanical Car Parking Tower has going to start from June 2026 and we expect to complete it by June 2027 and obtain the full OC by 31/12/2027 Therefore, request you to kindly consider our application for extension till 31/12/2027”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Center Plaza Phase 1’s extension records on MahaRERA (P51800034832), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Center Plaza Phase 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800034832
Status
Registered and active
Builder
B V ENTERPRISES
Location
Malad East, Mumbai · 400097
Project type
Commercial
Registered on
28 Apr 2022
Completion date at registration
December 2023
Latest completion date
April 2028
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
89%
Towers
1
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found

Construction progress of Center Plaza Phase 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Center Plaza100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Center Plaza: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Center Plaza Phase 1 every 1–2 months.

Center Plaza Phase 1: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Shops25 – 44828

The builder’s record and reviews

Sethia Infrastructure (a group of 6 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 35 months); 7 still being built, 5 past the promised date (typically 18 months late). 38 complaints on MahaRERA across 4 projects.

Read Google reviews of Center Plaza Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Center Plaza Phase 1: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Center Plaza Phase 1

What is the possession date of Center Plaza Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Center Plaza Phase 1 in Malad East, Mumbai is 30 April 2028 — 48 months later than 31 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 48 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Center Plaza Phase 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Center Plaza Phase 1's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 31 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Center Plaza Phase 1 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Center Plaza Phase 1's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "This is to inform you that our project name Center Plaza Phase 1 located at plot bearing C.T.S. No. 357 at village Malad (East) and C.TS. No. 521 522 of Village Kurar, Taluka Borivali, Mumbai - 400 097 Bearing Rera No P51800034832. The only pending work of the Mechanical Car Parking Tower has going to start from June 2026 and we expect to complete it by June 2027 and obtain the full OC by 31/12/2027 Therefore, request you to kindly consider our application for extension till 31/12/2027". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Center Plaza Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Center Plaza Phase 1 in Malad East, Mumbai is P51800034832.

Is Center Plaza Phase 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Center Plaza Phase 1 is registered as P51800034832 and its status is "Registered and active".

What is the current construction status of Center Plaza Phase 1? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Center Plaza Phase 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Center Plaza is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Center Plaza Phase 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Center Plaza Phase 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Center Plaza Phase 1 is registered on MahaRERA as P51800034832, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Center Plaza Phase 1?

Center Plaza Phase 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Center Plaza Phase 1?

For a flat in Center Plaza Phase 1 (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Center Plaza Phase 1 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Center Plaza Phase 1 is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Center Plaza Phase 1 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Center Plaza Phase 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Center Plaza Phase 1's possession date changes?

The latest dates are on Center Plaza Phase 1's MahaRERA page (P51800034832). GharKundli's Kundli Watch sends a free WhatsApp update on Center Plaza Phase 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Center Plaza Phase 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Center Plaza Phase 1 has one building filed: Center Plaza with 4 floors and 28 units.

How big is the land of Center Plaza Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Center Plaza Phase 1 stands on 2,216 sq m of land (about 0.5 acres), with 1,076 sq m of sanctioned built-up area.

What is the track record of Center Plaza Phase 1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sethia Infrastructure (a group of 6 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 35 months); 7 still being built, 5 past the promised date (typically 18 months late). 38 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of Center Plaza Phase 1?

Google Maps has reviews of Center Plaza Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Center Plaza Phase 1?

Center Plaza Phase 1 by B V ENTERPRISES (Sethia) is in Malad East, Mumbai, pincode 400097 (near malad west, Kurar Village, Borivali West), Maharashtra, and is registered on MahaRERA as P51800034832, per GharKundli's check of MahaRERA records. Its boundaries filed there include 18 3 M Daftary Road. Its land is filed as FP No 25 and FP No 26. GharKundli lists all 195 MahaRERA projects in Malad East (400097).

How many flats are in Center Plaza Phase 1, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Center Plaza Phase 1 has 0 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.

When was Center Plaza Phase 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Center Plaza Phase 1 was registered on MahaRERA on 28 April 2022. GharKundli did not find a title report on the land on file there.

Does Center Plaza Phase 1 have any legal issues or court cases?

1 court case is listed for Center Plaza Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

A court case can stall a project or tie up the land. See what the case is about →

Who is the builder / developer of Center Plaza Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is B V ENTERPRISES, the company Sethia files this project under.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Malad East (400097)

All 195 projects in Malad East (400097) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.