Ameya Residency
by Ameya Realtors Private Limited · Chunabhatti, Mumbai 400022Also near Chembur, Nehru Nagar, Sion
What’s in the report? →Possession date of Ameya Residency (MahaRERA PR1180002500624): 30 April 2030. It has 95 homes (1 BHK, 1 Room Kitchen and 2 BHK, 234–930 sq ft carpet), 50% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1180002500624, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PR1180002500624, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Ameya Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Ameya Residency has moved
31 December 2029
Completion date given when the project was registered
30 April 2030
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Ameya Residency’s extension records on MahaRERA (PR1180002500624), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ameya Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2030 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1180002500624
- Status
- Registered and active
- Builder
- Ameya Realtors Private Limited
- Location
- Chunabhatti, Mumbai · 400022
- Project type
- Residential / Group Housing
- Registered on
- 21 Aug 2025
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 95
- Sold or booked
- 50%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Ameya Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GURUPRASAD CHS | 100% | 40% | 6% | 0% |
| PRABHUNAM CHS | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- GURUPRASAD CHS: covers 15 floors
- PRABHUNAM CHS: covers 0 floors
Latest CC order on MahaRERA: dated 26/06/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ameya Residency every 1–2 months.
Ameya Residency: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 600 – 730 | 70 |
| 3 BHK | 785 – 930 | 19 |
| 1 BHK | 395 – 475 | 5 |
| 1 Room Kitchen | 234 | 1 |
- Buildings: GURUPRASAD CHS (17 floors, 57 units) · PRABHUNAM CHS (15 floors, 38 units)
- Car parking: 170 covered
- Land: 3,079 sq m (about 0.8 acres) · sanctioned built-up 6,625 sq m · recreational space 616 sq m
- Boundaries filed include: V.N.Purav marg
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Ameya Developers (a group of 2 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 12 months); 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Ameya Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ameya Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Ameya Residency
What is the possession date of Ameya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Ameya Residency in Chunabhatti, Mumbai is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Ameya Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ameya Residency's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Ameya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Ameya Residency in Chunabhatti, Mumbai is PR1180002500624.
Is Ameya Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ameya Residency is registered as PR1180002500624 and its status is "Registered and active".
What is the current construction status of Ameya Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Ameya Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 40% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Ameya Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Ameya Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Ameya Residency is registered on MahaRERA as PR1180002500624, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Ameya Residency?
Ameya Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Ameya Residency are 234 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Ameya Residency?
For a flat in Ameya Residency (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Ameya Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Ameya Residency is still under construction, with 30 April 2030 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Ameya Residency a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Ameya Residency is a redevelopment: 57 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Ameya Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Ameya Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Ameya Residency's possession date changes?
The latest dates are on Ameya Residency's MahaRERA page (PR1180002500624). GharKundli's Kundli Watch sends a free WhatsApp update on Ameya Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ameya Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Ameya Residency has 2 buildings filed: GURUPRASAD CHS with 17 floors and 57 units; PRABHUNAM CHS with 15 floors and 38 units.
What are the flat sizes (carpet area) in Ameya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Ameya Residency: 2 BHK: 600 to 730 sq ft carpet (70 homes); 3 BHK: 785 to 930 sq ft carpet (19 homes); 1 BHK: 395 to 475 sq ft carpet (5 homes); 1 Room Kitchen: 234 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does Ameya Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 170 covered car parking spaces for Ameya Residency.
How big is the land of Ameya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Ameya Residency stands on 3,079 sq m of land (about 0.8 acres), with 6,625 sq m of sanctioned built-up area and 616 sq m of recreational open space.
What is the track record of Ameya Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Ameya Developers (a group of 2 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 4 finished, 3 within the promised date and 1 needed more time (typically 12 months); 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Ameya Residency?
Google Maps has reviews of Ameya Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Ameya Residency?
Ameya Residency by Ameya Realtors Private Limited is in Chunabhatti, Mumbai, pincode 400022 (near Chembur, Nehru Nagar, Sion), Maharashtra, and is registered on MahaRERA as PR1180002500624, per GharKundli's check of MahaRERA records. Its boundaries filed there include V.N.Purav marg. GharKundli lists all 98 MahaRERA projects in Sion (400022).
How many flats are in Ameya Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Ameya Residency has 95 homes in 2 towers registered on MahaRERA, and 50% of them are sold or booked.
When was Ameya Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Ameya Residency was registered on MahaRERA on 21 August 2025. GharKundli did not find a title report on the land on file there.
Does Ameya Residency have any legal issues or court cases?
No court cases are listed for Ameya Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Ameya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ameya Realtors Private Limited, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Ameya Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2030 in Mumbai City →
Other projects in Sion (400022)
- DNS Anuutham
- Kings Hill View
- Dosti Mezzo 22
- Privia Navkar
- Dhanishtha
- Shankesh Crown
- Seaplaza
- Shankheshwar Heights
Other projects by Ameya Realtors Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.