SJK Shilpa Grandeur
by SJK BUILDCON LLP · Jain Society Sion Main Road, Mumbai 400022Also near Matunga East, Dharavi, Sion WestRegistered on MahaRERA as “SHILPA GRANDEUR”
What’s in the report? →Possession date of SJK Shilpa Grandeur (MahaRERA PM1180002500909): 30 October 2028. It has 25 homes (1 Room Kitchen, 1 BHK and 2 BHK, 421–1436 sq ft carpet), 7% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PM1180002500909, and currently active. Its completion date is now October 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PM1180002500909, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about SJK Shilpa Grandeur?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of SJK Shilpa Grandeur has moved
30 June 2028
Completion date given when the project was registered
30 October 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SJK Shilpa Grandeur’s extension records on MahaRERA (PM1180002500909), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SJK Shilpa Grandeur
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1180002500909
- Status
- Registered and active
- Builder
- SJK BUILDCON LLP
- Location
- Jain Society Sion Main Road, Mumbai · 400022
- Project type
- Mixed
- Registered on
- 23 Sep 2025
- Completion date at registration
- June 2028
- Latest completion date
- October 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 25
- Sold or booked
- 7%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SJK Shilpa Grandeur, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHILPA GRANDEUR | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SHILPA GRANDEUR: covers Plinth
Latest CC order on MahaRERA: dated 04/07/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SJK Shilpa Grandeur every 1–2 months.
SJK Shilpa Grandeur: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 3 BHK | 768 – 1,178 | 11 |
| Shops | 118 – 952 | 10 |
| 1 Room Kitchen | 444 | 4 |
| Multi Purpose Room | 421 | 4 |
| 2 BHK | 907 – 1,214 | 3 |
| Office Space | 500 – 667 | 2 |
| 1 BHK | 538 – 578 | 2 |
| 4 BHK | 1,436 | 1 |
- Buildings: SHILPA GRANDEUR (20 floors, 37 units)
- Car parking: 84 covered
- Land: 777 sq m (about 0.2 acres) · sanctioned built-up 2,698 sq m
- Boundaries filed include: SION MAIN ROAD
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SJK Shilpa Grandeur →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SJK Shilpa Grandeur: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about SJK Shilpa Grandeur
What is the possession date of SJK Shilpa Grandeur?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SJK Shilpa Grandeur in Jain Society Sion Main Road, Mumbai is 30 October 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SJK Shilpa Grandeur?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SJK Shilpa Grandeur's builder has filed on MahaRERA, the official one, is 30 October 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SJK Shilpa Grandeur?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SJK Shilpa Grandeur in Jain Society Sion Main Road, Mumbai is PM1180002500909.
Is SJK Shilpa Grandeur registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SJK Shilpa Grandeur is registered as PM1180002500909 and its status is "Registered and active".
What is the current construction status of SJK Shilpa Grandeur? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), SJK Shilpa Grandeur's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHILPA GRANDEUR is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does SJK Shilpa Grandeur have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SJK Shilpa Grandeur safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SJK Shilpa Grandeur is registered on MahaRERA as PM1180002500909, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in SJK Shilpa Grandeur?
SJK Shilpa Grandeur is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in SJK Shilpa Grandeur are 421 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in SJK Shilpa Grandeur?
For a flat in SJK Shilpa Grandeur (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has SJK Shilpa Grandeur received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), SJK Shilpa Grandeur is still under construction, with 30 October 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is SJK Shilpa Grandeur a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), SJK Shilpa Grandeur is a redevelopment: 23 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has SJK Shilpa Grandeur uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for SJK Shilpa Grandeur was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if SJK Shilpa Grandeur's possession date changes?
The latest dates are on SJK Shilpa Grandeur's MahaRERA page (PM1180002500909). GharKundli's Kundli Watch sends a free WhatsApp update on SJK Shilpa Grandeur every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SJK Shilpa Grandeur have?
According to GharKundli's check of MahaRERA records (updated October 2026), SJK Shilpa Grandeur has one building filed: SHILPA GRANDEUR with 20 floors and 37 units.
What are the flat sizes (carpet area) in SJK Shilpa Grandeur?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SJK Shilpa Grandeur: 3 BHK: 768 to 1178 sq ft carpet (11 homes); 1 Room Kitchen: 444 sq ft carpet (4 homes); Multi Purpose Room: 421 sq ft carpet (4 homes); 2 BHK: 907 to 1214 sq ft carpet (3 homes); 1 BHK: 538 to 578 sq ft carpet (2 homes); 4 BHK: 1436 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does SJK Shilpa Grandeur have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 84 covered car parking spaces for SJK Shilpa Grandeur.
How big is the land of SJK Shilpa Grandeur?
According to GharKundli's check of MahaRERA records (updated October 2026), SJK Shilpa Grandeur stands on 777 sq m of land (about 0.2 acres), with 2,698 sq m of sanctioned built-up area.
What are the reviews of SJK Shilpa Grandeur?
Google Maps has reviews of SJK Shilpa Grandeur written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of SJK Shilpa Grandeur?
SJK Shilpa Grandeur by SJK BUILDCON LLP is in Jain Society Sion Main Road, Mumbai, pincode 400022 (near Matunga East, Dharavi, Sion West), Maharashtra, and is registered on MahaRERA as PM1180002500909, per GharKundli's check of MahaRERA records. Its boundaries filed there include SION MAIN ROAD. GharKundli lists all 98 MahaRERA projects in Sion (400022).
How many flats are in SJK Shilpa Grandeur, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), SJK Shilpa Grandeur has 25 homes in 1 tower registered on MahaRERA, and 7% of them are sold or booked.
When was SJK Shilpa Grandeur registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SJK Shilpa Grandeur was registered on MahaRERA on 23 September 2025. GharKundli did not find a title report on the land on file there.
Does SJK Shilpa Grandeur have any legal issues or court cases?
No court cases are listed for SJK Shilpa Grandeur on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of SJK Shilpa Grandeur?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SJK BUILDCON LLP.
Check it yourself on MahaRERA
- How to check the possession date of SJK Shilpa Grandeur
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Mumbai City →
Other projects in Sion (400022)
- Kings Hill View
- Dosti Mezzo 22
- Privia Navkar
- Arihant Niwara Sky
- Dhanishtha
- Shankesh Crown
- Seaplaza
- Shankheshwar Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.