GREEN NEST
by BHAVYA PARSHVA REALTY LLP · Goregaon East, MumbaiAlso near Jogeshwari East, Oshiwara District Centre, Ram Mandir Road
Possession date of GREEN NEST: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800080833, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about GREEN NEST?
How the possession date of GREEN NEST has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: GREEN NEST’s extension records on MahaRERA (P51800080833), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GREEN NEST
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800080833
- Status
- Registered and active
- Builder
- BHAVYA PARSHVA REALTY LLP
- Location
- Goregaon East, Mumbai · 400065
- Project type
- Residential / Group Housing
- Registered on
- 16 Jul 2025
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 80
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of GREEN NEST, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GREEN NEST | 100% | 22% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- GREEN NEST: covers upto top of 19th upper residential floors
Latest CC order on MahaRERA: dated 27/05/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GREEN NEST every month.
GREEN NEST: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 603 – 620 | 40 |
| 1 BHK | 269 – 598 | 40 |
| Shops | 212 | 8 |
- Buildings: GREEN NEST (23 floors, 88 units)
- Car parking: 64 covered
- Land: 681 sq m (about 0.2 acres) · sanctioned built-up 4,432 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of GREEN NEST →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GREEN NEST: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GREEN NEST
What is the possession date of GREEN NEST?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GREEN NEST in Goregaon East, Mumbai is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for GREEN NEST?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GREEN NEST's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of GREEN NEST?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GREEN NEST in Goregaon East, Mumbai is P51800080833.
Is GREEN NEST registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GREEN NEST is registered as P51800080833 and its status is "Registered and active".
What is the construction status of GREEN NEST?
According to GharKundli's check of MahaRERA records (updated October 2026), GREEN NEST's status on MahaRERA is "Registered and active". As filed by the builder, slab work on GREEN NEST is 22% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does GREEN NEST have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is GREEN NEST safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GREEN NEST is registered on MahaRERA as P51800080833, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GREEN NEST's possession date changes?
The latest dates are on GREEN NEST's MahaRERA page (P51800080833). GharKundli's Kundli Watch sends a free WhatsApp update on GREEN NEST every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GREEN NEST have?
According to GharKundli's check of MahaRERA records (updated October 2026), GREEN NEST has one building filed: GREEN NEST with 23 floors and 88 units.
What are the flat sizes (carpet area) in GREEN NEST?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for GREEN NEST: 2 BHK: 603 to 620 sq ft carpet (40 homes); 1 BHK: 269 to 598 sq ft carpet (40 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does GREEN NEST have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 64 covered car parking spaces for GREEN NEST.
How big is the land of GREEN NEST?
According to GharKundli's check of MahaRERA records (updated October 2026), GREEN NEST stands on 681 sq m of land (about 0.2 acres), with 4,432 sq m of sanctioned built-up area.
Where can I read reviews of GREEN NEST?
Google Maps has reviews of GREEN NEST written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GREEN NEST?
GREEN NEST by BHAVYA PARSHVA REALTY LLP is in Goregaon East, Mumbai (pincode 400065), near Jogeshwari East, Oshiwara District Centre, Ram Mandir Road, Maharashtra, and is registered on MahaRERA as P51800080833, per GharKundli's check of MahaRERA records.
How many homes are in GREEN NEST?
According to GharKundli's check of MahaRERA records (updated October 2026), GREEN NEST has 80 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was GREEN NEST registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GREEN NEST was registered on MahaRERA on 16 July 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on GREEN NEST?
No court cases are listed for GREEN NEST on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of GREEN NEST?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BHAVYA PARSHVA REALTY LLP.
Check it yourself on MahaRERA
- How to check the possession date of GREEN NEST
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in Goregaon East
- VATSALYA
- SAMARTH TANISH
- SHEETAL TAPOVAN
- CONWOOD PARAGON
- DGS HEIGHTS
- PIXEL
- Agarwal Floresta - Maple
- GOREGAON ADWAIT CHSL - VIJAY SADAN
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.