SAMARTH TANISH
by NITIN DATTARAM SAMANT · Goregaon East, MumbaiAlso near Goregaon West, Cama Estate, Dindoshi, Malad East
Possession date of SAMARTH TANISH: 30 April 2027, moved from 30 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800003379, and currently active. Its completion date has moved from December 2023 to April 2027: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 14 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAMARTH TANISH?
How the possession date of SAMARTH TANISH has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51800018167)
Reason the builder gave MahaRERA: “DUE TO COVID 19 WE ARE NOT ABLE TO COMPLETE OUR PROJECT AND SHORTAGE OF MATERIAL PLEASE GRANT US EXTENSION FOR 12 MONTHS”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800025885)
Reason the builder gave MahaRERA:
“With reference to delay in possession of the site Samarth Tanish, we would like to clarify on certain points as mentioned below. On 26/09/19 as per IOD Flats bearing 269 sq.ft were converted into 300 sq.ft area as the overall process consum…” Read the full reason
“With reference to delay in possession of the site Samarth Tanish, we would like to clarify on certain points as mentioned below. On 26/09/19 as per IOD Flats bearing 269 sq.ft were converted into 300 sq.ft area as the overall process consumed nearly one year. On 07/11/19 & 24/03/21 there were changes in Plan / CC endorsement and because of the re-endorsed plans there was delay in execution of the site progress. On 2021 as per DPCR 2034, number of Sale flats in A Wing were increased and therefore the procedure consumed 7 to 8 months of time. Above mentioned points have resulted in delayed po…”31 December 2026
Extended at the builder's request (MahaRERA application EA10022619780)
Reason the builder gave MahaRERA:
“We reference to the above subject we Samarth Erectors and Developers would like mention the reasons for overall delay in completing the site. We had received LOI for constructing area of 225 sq.ft flats but later was revised to area I of 26…” Read the full reason
“We reference to the above subject we Samarth Erectors and Developers would like mention the reasons for overall delay in completing the site. We had received LOI for constructing area of 225 sq.ft flats but later was revised to area I of 269 sq.ft flats. Vacating of site (tenants shifting work) was carried out for another three years span. Again due to change in rules we had to apply for revised LOI ie area of 269 sq.ft flats were converted to to 300 sqft. Corona pandemic hit so badly that the site work stopped completely for nearly two years. In Feb 2023, SRA issued letter to stop work and…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SAMARTH TANISH’s extension records on MahaRERA (P51800003379), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAMARTH TANISH
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 14 complaints and 1 court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800003379
- Status
- Registered and active
- Builder
- NITIN DATTARAM SAMANT
- Location
- Goregaon East, Mumbai · 400063
- Project type
- Residential / Group Housing
- Registered on
- 5 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- April 2027
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 133
- Sold or booked
- 48%
- Towers
- 1
- Complaints on MahaRERA
- 14
- Court cases listed
- 1
- Appeals at the tribunal
- 2
- Title report on file
- Not found
Construction progress of SAMARTH TANISH, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAMARTH TANISH | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- SAMARTH TANISH: covers ground floor + 22 upper floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAMARTH TANISH every month.
SAMARTH TANISH: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 300 – 454 | 133 |
- Buildings: SAMARTH TANISH (25 floors, 133 units)
- Land: 1,527 sq m (about 0.4 acres) · sanctioned built-up 3,832 sq m · recreational space 122 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAMARTH TANISH →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAMARTH TANISH: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAMARTH TANISH
What is the possession date of SAMARTH TANISH?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAMARTH TANISH in Goregaon East, Mumbai is 30 April 2027 — 36 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SAMARTH TANISH?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAMARTH TANISH's builder has filed on MahaRERA, the official one, is 30 April 2027, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAMARTH TANISH extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMARTH TANISH's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "DUE TO COVID 19 WE ARE NOT ABLE TO COMPLETE OUR PROJECT AND SHORTAGE OF MATERIAL PLEASE GRANT US EXTENSION FOR 12 MONTHS"; to 31 December 2025, giving the reason "With reference to delay in possession of the site Samarth Tanish, we would like to clarify on certain points as mentioned below. On 26/09/19 as per IOD Flats bearing 269 sq.ft were converted into 300 sq.ft area as the overall process consumed nearly one year. On 07/11/19 & 24/03/21 there were changes in Plan / CC endorsement and because of the re-endorsed plans there was delay in execution of the site progress. On 2021 as per DPCR 2034, number of Sale flats in A Wing were increased and therefore the procedure consumed 7 to 8 months of time. Above mentioned points have resulted in delayed po…"; to 31 December 2026, giving the reason "We reference to the above subject we Samarth Erectors and Developers would like mention the reasons for overall delay in completing the site. We had received LOI for constructing area of 225 sq.ft flats but later was revised to area I of 269 sq.ft flats. Vacating of site (tenants shifting work) was carried out for another three years span. Again due to change in rules we had to apply for revised LOI ie area of 269 sq.ft flats were converted to to 300 sqft. Corona pandemic hit so badly that the site work stopped completely for nearly two years. In Feb 2023, SRA issued letter to stop work and…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of SAMARTH TANISH?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAMARTH TANISH in Goregaon East, Mumbai is P51800003379.
Is SAMARTH TANISH registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMARTH TANISH is registered as P51800003379 and its status is "Registered and active".
What is the construction status of SAMARTH TANISH?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMARTH TANISH's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAMARTH TANISH is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SAMARTH TANISH have complaints on MahaRERA?
14 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAMARTH TANISH safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMARTH TANISH is registered on MahaRERA as P51800003379, its completion date has moved 36 months since registration and 14 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAMARTH TANISH's possession date changes?
The latest dates are on SAMARTH TANISH's MahaRERA page (P51800003379). GharKundli's Kundli Watch sends a free WhatsApp update on SAMARTH TANISH every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAMARTH TANISH have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMARTH TANISH has one building filed: SAMARTH TANISH with 25 floors and 133 units.
What are the flat sizes (carpet area) in SAMARTH TANISH?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SAMARTH TANISH: 1 BHK: 300 to 454 sq ft carpet (133 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SAMARTH TANISH?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMARTH TANISH stands on 1,527 sq m of land (about 0.4 acres), with 3,832 sq m of sanctioned built-up area and 122 sq m of recreational open space.
Where can I read reviews of SAMARTH TANISH?
Google Maps has reviews of SAMARTH TANISH written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 14 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAMARTH TANISH?
SAMARTH TANISH by NITIN DATTARAM SAMANT is in Goregaon East, Mumbai (pincode 400063), near Goregaon West, Cama Estate, Dindoshi, Malad East, Maharashtra, and is registered on MahaRERA as P51800003379, per GharKundli's check of MahaRERA records.
How many homes are in SAMARTH TANISH?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMARTH TANISH has 133 homes in 1 tower registered on MahaRERA, and 48% of them are sold or booked.
When was SAMARTH TANISH registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAMARTH TANISH was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SAMARTH TANISH?
1 court case is listed for SAMARTH TANISH on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SAMARTH TANISH?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NITIN DATTARAM SAMANT.
Check it yourself on MahaRERA
- How to check the possession date of SAMARTH TANISH
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400063
- ASTORIA TOWER B
- AVANT HILLWAY
- AVANT HILLWAY
- Satellite Elegance
- 104 EAST
- SEJAL SQUARE
- S-CITY-R2
- Sheetal Sangam
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.