Municipal Staff Sahayog CHS LTD
by Konark Structural Engineers Private Limited · Andeheri West, Mumbai
Registered on MahaRERA under PR1180002501238, and currently active. Its completion date has moved from December 2029 to April 2030, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
- MahaRERA registration
- PR1180002501238
- Status
- Registered and active
- Builder
- Konark Structural Engineers Private Limited
- Location
- Andeheri West, Mumbai · 400061
- Project type
- Residential / Group Housing
- Registered on
- 15 Oct 2025
- Completion date at registration
- December 2029
- Latest completion date
- April 2030
- Delay so far
- 4 months
- Homes
- 109
- Sold or booked
- 0%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 9
GharKundli’s full report on Municipal Staff Sahayog CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Kundli Watch
Municipal Staff Sahayog CHS LTD: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about Municipal Staff Sahayog CHS LTD
Is Municipal Staff Sahayog CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Municipal Staff Sahayog CHS LTD is registered as PR1180002501238 and its status is "Registered and active".
Where is Municipal Staff Sahayog CHS LTD?
Municipal Staff Sahayog CHS LTD by Konark Structural Engineers Private Limited is in Andeheri West, Mumbai (pincode 400061), Maharashtra, and is registered on MahaRERA as PR1180002501238, per GharKundli's check of MahaRERA records.
When is possession of Municipal Staff Sahayog CHS LTD due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Municipal Staff Sahayog CHS LTD in Andeheri West, Mumbai is 30 April 2030 — 4 months later than 31 December 2029, the date given at registration.
Does Municipal Staff Sahayog CHS LTD have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of Municipal Staff Sahayog CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Konark Structural Engineers Private Limited, which has 9 other projects registered on MahaRERA.
Other projects in pincode 400061
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.